Planning Central has collected manufacturing data for a Work Order WO-2045 (Make Item AS1000), where actual duration of work order is 2 days. Item AS1000 manufacturing lead time is 1.25 days.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.
A user wants to transfer the work order status updates and resource transaction data for costed resources to Cost Management.
Whichscheduled process should you run to achieve this requirement?
You are monitoring the production status on your shop floor. The production operator informs you that a particular resource that was not functioning for the past week is now back in operation.
Which option shows the steps to quickly release the work orders affected by this operation, which were put on hold using the mobile application?
In your customer’s manufacturing facility, different types of Movement Requests are created. Key manufacturing components are issued to the work orders form the manufacturing subinventory. The manufacturing subinventory receives its supplies formthe Warehouse subinventory through automatically created Movement Requests.
Which type of Movement Requests should you use to fill the manufacturing subinventory form the Warehouse subinventory?
The production user wants to report Work Order completion.
Identify two ways of reporting the progress of work order at work order operation level.