C_ACTIVATE12 SAP Certified Associate - SAP Activate Project Manager Questions and Answers

Questions 4

When do you perform User Acceptance Testing during the Agile Build?

Please choose the correct answer.

Response:

Options:

A.

Before Integration Testing

B.

During each Firm-up Sprint

C.

After each Sprint

D.

After Integration Testing

Buy Now
Questions 5

Which of the following building blocks are part of the SAP S/4HANA platform?

There are 2 correct answers to this question.

Response:

Options:

A.

SAP Fiori UX

B.

SAP HANA in-memory database

C.

SAP Solution Manager

D.

LOB Cloud Solution

Buy Now
Questions 6

Which tool can you use to collaborate with other SAP Activate methodology practitioners?

Please choose the correct answer.

Response:

Options:

A.

SAP Jam

B.

SAP Solution Manager

C.

SAP Implementation Assistant

D.

Roadmap Viewer

Buy Now
Questions 7

In which phase you execute the User Acceptance Test?

Please choose the correct answer.

Response:

Options:

A.

Build and Test

B.

Deploy

C.

Final Preparation

D.

Realize

Buy Now
Questions 8

What SAP Cloud Platform integration tool would you use to integration SAP S/4HANA Cloud and SAP S/4HANA on premise?

Options:

A.

SAP Cloud Platform, Open Connectors

B.

SAP Cloud Platform, Cloud Integration

C.

SAP Cloud Platform, API Management

D.

SAP Cloud Platform, Connectivity

Buy Now
Questions 9

What are some of the intelligent technologies that enable end-to-end automation?

Options:

A.

Embedded Analytics

B.

Predictive Analytics

C.

Machine Learning

D.

Fundamental Simplification

E.

Conversational AI

Buy Now
Questions 10

What does SAP define as the three key components of how a data center works?

Options:

A.

Cooling

B.

Backup Retention Procedures

C.

Power Supply

D.

Certification Standards

E.

Controlled Access

Buy Now
Questions 11

What is the objective of a sprint retrospective meeting?

Please choose the correct answer.

Response:

Options:

A.

Define the stakeholder management approach

B.

Review andprioritize the backlog

C.

Provide formal feedback to the project manager

D.

Improve the SCRUM process

Buy Now
Questions 12

What are the three cornerstones of SAP's cloud security strategy?

Options:

A.

Secure People

B.

Secure Operations

C.

Secure Company

D.

Secure Cloud

E.

Secure Products

Buy Now
Questions 13

What does "SSCUI" stand for?

Options:

A.

Self-Service Customization User Interface

B.

Self-Service Configuration User Interface

C.

Self-Service Creation User Interface

D.

Self-Service Collection User Interface

Buy Now
Questions 14

According to the Definition of Done, which activity must be completed for each sprint?

Please choose the correct answer.

Response:

Options:

A.

End user training must be delivered

B.

Solution must be built and configured in the development system (DEV)

C.

Functionality must be tested in the Quality system (QAS)

D.

Functionality must be released to the business

Buy Now
Questions 15

What does it mean if an SSCUI has a "Yes" in the "Redo in P System" column?

Options:

A.

Youmust manually redo the configuration in the production system, because it is not captured in change projects.

B.

SSCUI records are specific to a company or country and every country has its own unique configuration records.

C.

The configuration is transferred from the quality system to the production system in change projects.

D.

The configuration records are the same for all countries and all country solutions have the same data.

Buy Now
Questions 16

In Which phase does the Transition toOperations work stream start?

Please choose the correct answer.

Response:

Options:

A.

Explore

B.

Realize

C.

Deploy

D.

Prepare

Buy Now
Questions 17

What are the three pillars of SAP Activate?

There are 3 correct answers to thisquestion.

Response:

Options:

A.

SAP Activate Methodology

B.

SAP Best Practices

C.

SAP S/4HANA in-memory database

D.

SAP Solution Manager

E.

Guided Configuration

Buy Now
Questions 18

Who determines the priority of user stories in the backlog of an Agile project?

Please choose the correct answer.

Response:

Options:

A.

Project Manager

B.

Project Team

C.

SCRUM Master

D.

Product Owner

Buy Now
Questions 19

In which phase do you create a prioritized list of user requirements?

Please choose the correct answer.

Response:

Options:

A.

Realize

B.

Explore

C.

Prepare

D.

Deploy

Buy Now
Exam Code: C_ACTIVATE12
Exam Name: SAP Certified Associate - SAP Activate Project Manager
Last Update: Jul 8, 2020
Questions: 161