1z0-1057-22 Oracle Project Management Cloud 2022 Implementation Professional Questions and Answers

Questions 4

Your company uses an accounting calendar with periods that are identical to calendar months. A contract resource has been identified to work for six months on an accounting close cycle project. The resource is planned to start with 10 days left in the first period and to end 20 days into the last period. For the remaining periods, the resource must be loaded on all working days of the month. You are required to distribute the budget, forecast, and planning amounts across periods based on the task duration.

Which predefined spread curve must be used to meet this requirement? (Choose the best answer.)

Options:

A.

Daily Spread Basis

B.

Back Loaded

C.

Bell Curve

D.

S-Curve

E.

Even

Buy Now
Questions 5

Your organization has created an Enterprise Project Structure (EPS) and your executives review the overall project labor demand by using the EPS. Identify two correct statements about the periodic project labor demand. (Choose two.)

Options:

A.

Labor Demand FTE is calculated as Quarterly Allocation hours divided by Quarterly FTE hours, if a quarter is used as the basis for viewing labor demand.

B.

Labor Demand FTE is calculated as Yearly Allocation hours divided by Yearly FTE hours, if a year is used as the basis for viewing labor demand.

C.

Labor Demand FTE is calculated as Project Allocation hours divided by Project FTE hours, if project duration is used as the basis for viewing labor demand.

D.

Labor Demand FTE is calculated as Monthly Allocation hours divided by Monthly FTE hours, if a period is used as the basis for viewing labor demand.

Buy Now
Questions 6

Your organization has a requirement to send notifications to the owners of the associated tasks when the status of a deliverable is set to Complete. You have been asked to evaluate generate public events for project deliverable status changes feature to manage this requirement.

Which two statements are true about this feature? (Choose two.)

Options:

A.

The public event is not generated when the priority of a deliverable changes.

B.

The public event is not generated when a deliverable is created or deleted.

C.

The public event is generated when a deliverable is created or deleted.

D.

The public event is generated when the progress status for a deliverable changes.

Buy Now
Questions 7

Which three are valid password complexity criteria while setting up password policies? (Choose three.)

Options:

A.

Complex: At least 8 characters, 1 uppercase, and 1 number

B.

Very Complex: At least 8 characters, 1 uppercase, 1 number, and 2 special characters

C.

Very Complex: At least 6 characters, 1 uppercase, 1 number, and 1 special character

D.

Very Complex: At least 8 characters, 1 uppercase, 1 number, and 1 special character

E.

Simple: At least 8 characters and 1 number

Buy Now
Questions 8

You are implementing Project Portfolio Management (PPM) for a professional services firm. The firm rents multiple buildings for its operations. At the end of each month, they review the rent expense for the month and want to allocate the rental cost to all the projects and tasks that are executed by associates in each of the buildings. The source amounts must be proportionally allocated to the tasks based on the raw costs of the tasks from the previous month. Considering that all these costs are in General Ledger, what three allocation setups should you complete in PPM? (Choose three.)

Options:

A.

Allocate rental costs once each accounting period by using the “full” allocation method.

B.

Allocate to all eligible tasks and prorate the allocation by the total actual raw cost accrued for each task during the previous accounting period.

C.

Define allocation basis by using Actual Amounts with a project-to-date amount class.

D.

Define allocation basis by using Actual Amounts with a period-to-date amount class.

E.

Allocate rental costs once each accounting period by using the “spread evenly” allocation method.

Buy Now
Questions 9

Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.

What are three conditions for new employees to show up in the list? (Choose three.)

Options:

A.

Current date is before the effective date of the resource, and you did not enable the “Include people with future-dated effective start dates” option during the search.

B.

All new employees created as persons must have an active supervisor.

C.

All new employees created as persons must be assigned to a department.

D.

All new employees created as persons must have an active assignment.

E.

All new employees created as persons must have an active project role.

Buy Now
Questions 10

Your customer has the following setups on the project plan type that they are using for their projects:

Use Task Planned Dates as Task Assignment Dates = Yes

Automatically Roll Up Task Planned Dates = Yes

Synchronize Task Transaction Dates with Planned Dates = No

With these setups in place, you perform the following actions:

1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.

2. Create another new subtask (Sub Task 2) after the previous action is saved.

What would the correct behavior of the application be after these actions? (Choose the best answer.)

Options:

A.

After the creation of Sub Task 1, Project Start Date would remain unchanged as 01-Jul-2016 and Sub Task 2 would be created with 15-Jun-2016.

B.

After the creation and saving of Sub Task 1, Task Start Date would be changed to 01-Jul-2016 and Sub Task 2 would be created with 01-Jul-2016.

C.

After the creation of Sub Task 1, Project Start Date would be changed to 15-Jun-2016 and Sub Task 2 would be created with 15-Jun-2016.

D.

Project Start Date would remain unchanged as 01-Jul-2016 for both actions but the start dates on both subtasks would remain 15-Jun-2016.

Buy Now
Questions 11

You recently made some changes to a project contract and the current status of the contract is Under Amendment. Identify the correct sequence of activities that can take place on that contract. (Choose the best answer.)

Options:

A.

On Hold > Pending Acceptance > Active

B.

On Hold > Pending Approval > Active

C.

Pending Approval > Pending Acceptance > Active

D.

Pending Acceptance > Pending Approval > Active

Buy Now
Questions 12

Which three file-based data imports are available for use in Oracle Project Portfolio Management Cloud?

Options:

A.

Project Tasks

B.

Project Budgets

C.

Project Billing Events

D.

Project Templates

E.

Capital Rate Schedule

Buy Now
Questions 13

Which product offering simplifies the planning, budgeting, and forecasting capabilities as part of Project Management Cloud?

Options:

A.

Enterprise Contract Management

B.

Project Billing

C.

Project Control

D.

Project Costing

Buy Now
Questions 14

You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)

Options:

A.

1000

B.

900

C.

800

D.

600

Buy Now
Questions 15

You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.

Identify two reasons for this problem. (Choose two.)

Options:

A.

The corresponding Oracle Payables Cloud accounting period has not been closed.

B.

Transactions entered in an integrated Oracle Cloud Application are accounted, but not yet transferred and imported into Oracle Project Portfolio Management Cloud.

C.

Pending burden summarization items have not been processed.

D.

Unaccounted transactions are not imported.

E.

Unaccounted transactions have not been swept to the next period.

Buy Now
Questions 16

You search for resources to fulfill a project resource request but are unable to proceed after receiving the following error message: “The search for resources cannot be completed because the project resource search index is not available. Contact your help desk.”

Identify the cause for this error message. (Choose the best answer.)

Options:

A.

The index is not in the process.

B.

The index has been built.

C.

The index is in the process of being updated.

D.

The most recent update of the index finished successfully.

Buy Now
Questions 17

Your client has decided to import time cards into Project Costing from Oracle Fusion Time and Labor. They have a requirement to make adjustments to time card entries whenever needed.

In which work area will the employees and contingent workers be able to modify their time cards?

Options:

A.

Both Time and Cost

B.

Cost

C.

Asset

D.

Time

Buy Now
Questions 18

Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets based on the construction-in-process cost of each asset. Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement. (Choose the best answer.)

Options:

A.

Standard Unit Cost

B.

Actual Unit

C.

Current Cost

D.

Estimated Cost

E.

Spread Evenly