Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

AD0-E911 Adobe Workfront Project Manager Certified Professional Questions and Answers

Questions 4

Which project Condition is set when the Progress Status of the project is Behind or At Risk?

Options:

A.

Late

B.

At Risk

C.

In Trouble

Buy Now
Questions 5

A user wants to know if a task is pending approval.

Which task field would the user review?

Options:

A.

Status

B.

Critical Path

C.

Priority

Buy Now
Questions 6

An IT department needs to see the Group and Portfolio of each of its projects for reporting purposes.

In which project area does this information reside?

Options:

A.

Queue Details

B.

Project Details

C.

Metrics

Buy Now
Questions 7

A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?

Options:

A.

Visit the Project page and create a new filter. Update the " Pending Approval " filter to " true " and update the Project Owner ID field to the project manager’s name. In the grouping tab, add a grouping for project name.

B.

Visit the Reports page and create a task report and an issue report. In the filter tab for each report, update the " Pending Approval " filter to " true, " and update the Project Owner ID field with the project manager’s name. In the grouping tab for each report, add a grouping for project name. Add both reports to a new dashboard.

C.

Visit the Reports page and create a Pending Approvals report. In the filter tab, update the Project Owner ID field with the project manager’s name and update the Object ID field to " tasks " and " issues. " In the grouping tab, add a grouping for project name.

Buy Now
Questions 8

Which project elements can be used to measure a project’s adherence to its original schedule?

Options:

A.

Number of tasks, actual completion dates, and project status

B.

Project baselines, planned completion dates, and actual completion dates

C.

Workload balancer data, planned completion dates, and expenses

Buy Now
Questions 9

The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.

Which task settings should be configured to meet these requirements?

Options:

A.

The task Duration should be set to 2 days. A predecessor with a Finish-Start Dependency Type should be added to the second task with a lag of 5 days.

B.

Planned Hours should be set to 48 hours. A predecessor with a Finish-Start Dependency Type should be added to the first task with a lag of 5 days.

C.

The task Duration should be set to 48 hours. A predecessor with a Start-Finish Dependency Type should be added to the second task with a lag of 5 days.

Buy Now
Questions 10

What is unique to a Scrum iteration?

Options:

A.

Backlog of stories and issues

B.

Workload Balancer for assigning users to tasks

C.

Burndown Chart

Buy Now
Questions 11

A project manager has been asked by their manager to create a report on the assignments everyone on the team has been given.

Which report type should they use?

Options:

A.

Task

B.

Work Item

C.

Issue

Buy Now
Questions 12

What are two ways to associate milestone steps to tasks? (Choose two.)

Options:

A.

In-line editing a task list on a project

B.

From the Milestone View in the Projects area

C.

Through bulk-editing multiple tasks

D.

In the settings area of a task

Buy Now
Questions 13

Which initial project setting would a project owner use to identify and report on key tasks on a project?

Options:

A.

Milestone Path

B.

Schedule

C.

Resource Leveling Mode

Buy Now
Questions 14

A contract requires custom billing rates.

Where can a project manager update this on the project?

Options:

A.

Project Details > Billing Information

B.

Project Settings > Access Levels

C.

Project Finances > Override Project-Level Billing Rates

Buy Now
Questions 15

A portfolio owner has asked to see milestone statuses for all projects in their portfolio. The report must filter out any complete projects. What steps should the project manager take to create this view?

Options:

A.

Visit the Dashboards page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects.

B.

Visit the Projects page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select " Show the Milestone view on the Details tab. "

C.

Visit the Reports page and create a Project report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select " Show the Milestone view on the Details tab. "

Buy Now
Questions 16

Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.

Why may this be the case?

Options:

A.

The primary task owner has time off logged in Workfront.

B.

The team needs to review the task before confirming the start date.

C.

The task duration and planned hours are set to begin on Friday.

Buy Now
Questions 17

A company expects managers to complete a Workfront Business Case and submit it to the Project Sponsor for approval before a project enters Planning status.

What Workfront process will effectively facilitate the Project Sponsor review?

Options:

A.

Request Approval Process

B.

Request Submission Process

C.

Project Submission Process

D.

Project Approval Process

Buy Now
Questions 18

A project manager is looking to create a task that must take place from September 10th through September 17th of this year.

Which action must be taken?

Options:

A.

Set the Task Constraint to Fixed Dates.

B.

Set a Predecessor for the task.

C.

Set the Duration of One week.

Buy Now
Questions 19

A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.

How should the project manager keep these team members apprised of updates?

Options:

A.

Subscribe the team members to the request.

B.

Ask the team members to add the request to their favorites.

C.

Make the team members all primary contacts on the request.

Buy Now
Questions 20

A project manager is updating a project in Workfront that is behind schedule.

Which action could be taken so that all tasks are completed by the requested completion date?

Options:

A.

Give all tasks a Task Constraint of “Must Start On”

B.

Reduce the durations of the tasks.

C.

Adjust all of the Planned Start Dates to the same day.

Buy Now
Questions 21

A statement of work is uploaded to the document section of a project as reference material. How should the file be uploaded into Workfront?

Options:

A.

Document

B.

Proof

C.

Approval

Buy Now
Questions 22

When a project owner grants Contribute access on a project to a user with the same access level as the project owner, what can that user do?

Options:

A.

Add a custom form

B.

Attach a template to the project

C.

Add tasks

Buy Now
Questions 23

A user wants to add users to a proof based on who requested the project and the additional approvers listed in the request.

Which Workflow should the user choose?

Options:

A.

Automated

B.

Basic

C.

Manual

Buy Now
Questions 24

What are two characteristics of a Group in Workfront? (Choose two.)

Options:

A.

A Group can be tagged in an Update thread communication.

B.

A Group assignment is not required for a user.

C.

A Group can be associated with a Company or a Project.

D.

A user can be assigned as Group Administrator of a Group.

Buy Now
Questions 25

The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions.

Which report grants the executive team this visibility?

Options:

A.

A project report showing active projects grouped by portfolio showing project condition, project priority, and custom data aligning the project initiative to business goals.

B.

A portfolio report showing all projects grouped by team showing project condition, the alignment score, and custom data aligning the project initiative to business goals.

C.

A program report showing active projects grouped by department showing program health, project urgency, and custom data aligning the project initiative to business goals.

Buy Now
Questions 26

Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?

Options:

A.

Projected Date

B.

Planned Date

C.

Estimated Date

Buy Now
Questions 27

AD0-E911 Question 27

What do the connector lines between tasks in a Gantt chart represent?

Options:

A.

Critical path

B.

Multiple assignments

C.

Predecessor relationship

Buy Now
Questions 28

Which project status will default the automatic Project Condition to “On Time”?

Options:

A.

Idea

B.

Planning

C.

On Hold

Buy Now
Exam Code: AD0-E911
Exam Name: Adobe Workfront Project Manager Certified Professional
Last Update: May 2, 2026
Questions: 95

PDF + Testing Engine

$63.52  $181.49

Testing Engine

$50.57  $144.49
buy now AD0-E911 testing engine

PDF (Q&A)

$43.57  $124.49
buy now AD0-E911 pdf