Summer Certification Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

AD0-E911 Adobe Workfront Project Manager Certified Professional Questions and Answers

Questions 4

A project manager has been asked to create a report showing the planned completion date for all the project manager ' s projects. The report must show results in a calendar view and all entries should be purple. What steps should the project manager take to create this view?

Options:

A.

Visit the Reports page and create a new report. In the filter, update the project Owner ID field with the project manager’s name and set the Color ID field to purple. Add a column for Planned Completion Date and set the default view to “Calendar View.”

B.

Visit the Calendars page and create a new calendar. In the filter, update the date field to Planned Dates and update the Project Owner ID field with the project manager’s name. Set the color to purple.

C.

Visit the Reports page and create a new calendar. In the filter, update the Project Owner ID field with the project manager’s name and set the Color ID field to purple. Add a column for Planned Completion Date.

Buy Now
Questions 5

To whom or what would a project owner assign a task so the task is visible in a Scrum or Kanban backlog?

Options:

A.

A user that has access to a burndown

B.

A job role labeled as Agile User

C.

A team marked as an agile team

Buy Now
Questions 6

A project manager is updating a project in Workfront that is behind schedule.

Which action could be taken so that all tasks are completed by the requested completion date?

Options:

A.

Give all tasks a Task Constraint of “Must Start On”

B.

Reduce the durations of the tasks.

C.

Adjust all of the Planned Start Dates to the same day.

Buy Now
Questions 7

A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?

Options:

A.

Visit the Project page and create a new filter. Update the " Pending Approval " filter to " true " and update the Project Owner ID field to the project manager’s name. In the grouping tab, add a grouping for project name.

B.

Visit the Reports page and create a task report and an issue report. In the filter tab for each report, update the " Pending Approval " filter to " true, " and update the Project Owner ID field with the project manager’s name. In the grouping tab for each report, add a grouping for project name. Add both reports to a new dashboard.

C.

Visit the Reports page and create a Pending Approvals report. In the filter tab, update the Project Owner ID field with the project manager’s name and update the Object ID field to " tasks " and " issues. " In the grouping tab, add a grouping for project name.

Buy Now
Questions 8

A project manager would like to assign tasks across projects to a team without having to navigate to each project.

How can the project manager do this?

Options:

A.

Assign work using the Resource Planner.

B.

Assign work by drag-and-drop.

C.

Assign work in bulk.

Buy Now
Questions 9

A task won’t close when trying to select “Complete.”

Which two reasons block someone from being able to close a task? (Choose two.)

Options:

A.

A predecessor task is “In Progress.”

B.

The subtasks are not “Complete.”

C.

The task is a predecessor to another task.

D.

The task is assigned to a job role and not an individual user.

E.

The project is “Active.”

Buy Now
Questions 10

A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.

What action should the task owner take?

Options:

A.

Set the task condition to At Risk.

B.

Update the Commit Date on the task.

C.

Work on the task and complete it in the given duration.

Buy Now
Questions 11

Which initial project setting would a project owner use to identify and report on key tasks on a project?

Options:

A.

Milestone Path

B.

Schedule

C.

Resource Leveling Mode

Buy Now
Questions 12

A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

Options:

A.

Actual Completion Date

B.

Progress Status

C.

Status

Buy Now
Questions 13

A project manager is looking to create a task that must take place from September 10th through September 17th of this year.

Which action must be taken?

Options:

A.

Set the Task Constraint to Fixed Dates.

B.

Set a Predecessor for the task.

C.

Set the Duration of One week.

Buy Now
Questions 14

A project manager is asked to provide a list of all projects the Marketing Group is working on for Acme Company.

What steps should the project manager take to create a custom Workfront report with this information?

Options:

A.

Visit the Reports page, create a new Project report, and add filters for Company ID and Group ID.

B.

Visit the Reports page, create a new Project report, and add filters for Company ID and Owner ID.

C.

Visit the Reports page, create a new Project report, and add filters for Owner ID and Project Status.

Buy Now
Questions 15

A project manager compares the original schedule for a task to another set of dates that moved later after predecessors slipped and the assignee changed a completion commitment.

What do these later, system-calculated dates represent?

Options:

A.

They are Planned Dates that show the originally scheduled task dates.

B.

They are Projected Dates that show the current forecast for task start and finish.

C.

They are Milestone Path Dates that show when milestone tasks are expected to occur.

Buy Now
Questions 16

AD0-E911 Question 16

Identified in red on a Gantt chart, what are the tasks called whose changes may affect the overall timeline of a project?

Options:

A.

Critical Path

B.

Baselines

C.

Milestones

Buy Now
Questions 17

An IT department needs to see the Group and Portfolio of each of its projects for reporting purposes.

In which project area does this information reside?

Options:

A.

Queue Details

B.

Project Details

C.

Metrics

Buy Now
Questions 18

A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started.

What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?

Options:

A.

Load the project template once the team has bandwidth to start on the project.

B.

Create projects but leave the roles in place without assigning users.

C.

Create a custom status for Backlog to use prior to using the Planning status.

Buy Now
Questions 19

A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.

What task setting needs to change to allow 4 users to complete this in less than 3 days?

Options:

A.

Change the Task Duration Type to Effort Driven

B.

Change the Task Duration Type to Calculated Work

C.

Change the Task Constraint to Fixed Dates

D.

Change the Task Constraint to As Soon As Possible

Buy Now
Questions 20

A team wants to combine structured project planning with the flexibility to manage tasks in sprints.

Which Workfront methodology allows for this hybrid approach?

Options:

A.

Scrum

B.

Waterfall

C.

Kanban

Buy Now
Questions 21

A project manager would like to see the Budgeted Variances between the hours for the current week. Where is that information found at the project level?

Options:

A.

Utilization section

B.

Hours tab

C.

Finance section

Buy Now
Questions 22

A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it.

What impact does this have on the project progress status?

Options:

A.

The next team member cannot start his task.

B.

No impact as the task is not overdue.

C.

The project shows an At Risk automatic condition.

Buy Now
Questions 23

Executive stakeholders require both current metric reports and a weekly recap on a project.

How can both needs be met?

Options:

A.

Create a program-specific dashboard for the metrics and set up a weekly automated report to send.

B.

Create a program-specific dashboard for the metrics, then download a dashboard weekly to email to the stakeholder team.

C.

Create a program-specific dashboard for the metrics and add a calendar reminder for the team to review the report.

Buy Now
Questions 24

How would a project manager create a custom Workfront report to show information about issues logged to the projects they own?

Options:

A.

Visit the Dashboard page, create a new Issue report, and update the Issue Owner ID filter with their name, and group by project name.

B.

Visit the Reports page, create a new Project report, update the Project Owner ID filter with their name, and add a column for issues.

C.

Visit the Reports page, create a new Issue report, update the Project Owner ID filter with their name, and group by project name.

Buy Now
Questions 25

Which project Condition is set when the Progress Status of the project is Behind or At Risk?

Options:

A.

Late

B.

At Risk

C.

In Trouble

Buy Now
Questions 26

Which wildcard should be used in a task report when using an Assigned To filter to show the logged-in user all tasks to which she is assigned as the primary task owner?

Options:

A.

USER.NAME

B.

USER.ID

C.

USER.roleID

Buy Now
Questions 27

Which Workfront collection of users allows a task or issue to be assigned to multiple people?

Options:

A.

Team

B.

Group

C.

Project Team

Buy Now
Questions 28

An organization has created unique data fields relevant to their projects. Starting by navigating from a project ' s landing page, where is this data found?

Options:

A.

Project Details > Custom Forms

B.

Project Details > Overview

C.

Business Case > Project Info

Buy Now
Exam Code: AD0-E911
Exam Name: Adobe Workfront Project Manager Certified Professional
Last Update: Jun 12, 2026
Questions: 95

PDF + Testing Engine

$64.99   $185.69

Testing Engine

$49.99   $142.83

PDF (Q&A)

$54.99   $157.11