Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

API-936 API 936 - Refractory Personnel Questions and Answers

Questions 4

Abrasion resistance of a material is reported as loss of:

Options:

A.

density.

B.

mass.

C.

volume.

D.

area.

Buy Now
Questions 5

Which term is used to describe a newly installed monolithic refractory lining that has not been exposed to either a dry-out or initial heating?

Options:

A.

Castable refractory

B.

Green refractory

C.

Wet refractory

D.

Installed refractory

Buy Now
Questions 6

The contractor on a field vibration casting job is preparing for a continuous pour that will last for three 12-hour shifts. The weather report predicts a nighttime low temperature of 35°F (2°C). How should the contractor be prepared?

Options:

A.

Have the castable dry mix heated to > 50°F (10°C)

B.

Be ready to stop pouring if the temperature drops below 35°F (2°C)

C.

Make no special preparations

D.

Keep the install material and shell > 50°F (10°C)

Buy Now
Questions 7

How many specimens per sample are required for testing by ASTM C-704?

Options:

A.

One

B.

Two

C.

Three

D.

Four

Buy Now
Questions 8

The installation contractor is required to secure an advance agreement that concerns all the installation details from the:

Options:

A.

Engineering company.

B.

Inspector.

C.

Owner.

D.

Manufacturer.

Buy Now
Questions 9

Which of the following conditions must be met for test results from trial mixes of low cement castables to be accepted for qualification?

Options:

A.

The water content must not vary more than ±1.0% from that recommended by the manufacturer.

B.

Specimens must be fired at 1500°F (815°C) and held for a minimum of 3 hours.

C.

Bulk density and CCS must exceed average values published in ASTM C401.

D.

The drying process must be conducted at 220°F (104°C) for at least 48 hours before firing.

Buy Now
Questions 10

The term "shelf life" refers to the maximum time:

Options:

A.

material may be stored and remains in usable condition.

B.

for material tests (expiration of test results).

C.

it takes for products to be manufactured and installed.

D.

the mixed material can sit prior to use.

Buy Now
Questions 11

The physical attributes testing of manufactured bricks during pre-shipment testing shall require a minimum Acceptable Quality Limit (AQL) of:

Options:

A.

1%

B.

4%

C.

5%

D.

10%

Buy Now
Questions 12

Which of the following is a quality control element?

(This may have more than one correct answer; please select all answers that apply.)

Options:

A.

As-installed testing

B.

Initial Inspection

C.

Installation monitoring

D.

Report writing

Buy Now
Questions 13

Selection, installation, inspection, and testing of anchors shall be in accordance with:

Options:

A.

contractor's QA/QC department

B.

API RP 577

C.

welding code

D.

drawing and specifications

Buy Now
Questions 14

Surface preparation and welding procedures are the responsibility of the:

Options:

A.

Owner.

B.

Contractor.

C.

Inspector.

D.

Manufacturer.

Buy Now
Questions 15

Gunning test panels are constructed with removable back panels:

Options:

A.

because removal back panels make the reclaiming of anchors easier.

B.

to allow inspection for voids and lamination in the castable.

C.

to facilitate the determination of the green-to-fired weight of the castable required for compliance.

D.

because a mechanical inspection by hammer test is required.

Buy Now
Questions 16

Newly applied cast linings must cure before stripping the forms per the:

Options:

A.

manufacturer's recommendations.

B.

owner's recommendations.

C.

MSDS.

D.

inspector's recommendations.

Buy Now
Questions 17

Apparent porosity values are reported as:

Options:

A.

cubic inches/centimeters.

B.

percentages.

C.

pounds per square inch/kilograms per square centimeter.

D.

inches/centimeters.

Buy Now
Questions 18

Which of the following is the inspector responsible for?

Options:

A.

Hammer testing newly installed linings

B.

Providing compliance data sheets

C.

Testing water to be used

D.

Qualification testing

Buy Now
Questions 19

Test results received from cast sample mock-ups will serve to qualify the:

API-936 Question 19

Options:

Buy Now
Questions 20

Testing to verify that the application equipment and personnel are capable of meeting specified quality standards is called:

Options:

A.

applicator qualification testing.

B.

material qualification testing.

C.

as-installed testing.

D.

quality control testing.

Buy Now
Questions 21

In the absence of owner specification, which party or individual sets the temperature limits for refractory and mix water?

Options:

A.

Contractor

B.

Manufacturer

C.

Inspector

D.

Independent refractory laboratory

Buy Now
Questions 22

Which of the following is the term for aggregate and/or cement that bounces away from a surface against which refractory is being projected by gunning?

Options:

A.

Slurry

B.

Trimmings

C.

Rebound

D.

Overspray

Buy Now
Questions 23

For as-installed testing in casting applications, what is the minimum number of cast samples required by each mixing crew per material per shift?

Options:

A.

One

B.

Two

C.

Three

D.

Four

Buy Now
Questions 24

Before application of a curing compound the hydraulic bond castable surface shall not be allowed to air dry longer than:

Options:

A.

1 hour.

B.

2 hours.

C.

8 hours.

D.

24 hours.

Buy Now
Questions 25

Which of the following statements regarding curing of hydraulic bonded castables is true?

Options:

A.

Apply a manufacturer approved membrane-type curing compound before the surface is dry to the touch

B.

The membrane curing compound shall burn off at a temperature not less than 500°F (260°C)

C.

After remaining in place for 24 hours, forms shall be removed and a curing compound applied within 1 hour of form removal

D.

No part of the lining shall be allowed to air dry more than 3 hours before application of a curing compound

Buy Now
Exam Code: API-936
Exam Name: API 936 - Refractory Personnel
Last Update: May 21, 2026
Questions: 85

PDF + Testing Engine

$64.99   $185.69

Testing Engine

$49.99   $142.83

PDF (Q&A)

$54.99   $157.11