A Project Manager is at the project kick-off meeting. He confidently states the vision and mission for the project. This PM is exhibiting the following leadership style:
Which of the following correctly explains the term " progressive elaboration " ?
The Project Integration Management knowledge area includes which of the following set of processes?
In a control chart, the consecutive measurements are 11, 13, 09, 07, 08, 09, 09, 09, 08, and 12. For the entire process, the goal is 10 and the standard deviation is 1.
For this data set, it is correct to say that the process:
How many communication channels will be required in a project in which 5 individual are participating?
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
Which type of network diagram is also referred to activity-on-arrow (AOA) diagrams?
At what point in a project do you have the highest probability that it will fail?
Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?
You are project manager and now in middle of creating RFP (Request for proposal). RFP (Request for proposal) is done in _______.
When you are developing the estimates for project, you choose to add the individual estimates for the activities that comprise each phase. What type of estimation method are you using?
You are the project manager of a project that just went into extinction mode. This means that your project __________.
_________ is the international organization that controls the standards for quality.
Which of the following is the most important task of the project manager during the Execution and Control phase?
You are the project manager of a project. Your project just went into integration mode. This means that your project __________.
Which of the following relationship is used in the Arrow Diagramming Method [ADM] :
Identification of Mandatory Dependencies is done during which of the following process:
Your company create software products, and introducing a new product. To determine the characteristics and features of the new product line, you will have to perform ________.
In which type of organization, a project manager is in complete control of the project?
Which type of analysis is used as a general management technique within the Plan Procurements Process?
Which of the following is a tool and technique to the Manage Stakeholder Expectations process?
What is the lowest level in the WBS at which the cost and activity durations for the work can be reliably estimated and managed?
A project team is in which of the following processes when they finalize all activities across all of the management process groups to formally complete the project?
Reserve analysis is a tool and technique used in which of the following processes?
Initiating, Planning, Executing, Monitoring and Controlling and Closing are called:
Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the project CV?
Given the following values, what is the calculated expected activity cost (CE) when using PERT?
CO = $7,000
CM = $10,500
CP = $11,000
Which of the following is a strategy to deal with positive risks or opportunities?
Which of the following must be taken into account for every process, even if they are not explicitly listed as inputs in the process specifications?
The project manager decides to conduct a meeting with the team and management after a new risk has been identified. After the meeting, the decision is to allow the risk to occur.
This is an example of which type of risk response strategy?
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Which tool and technique identifies inefficient and ineffective policies, processes and procedures?
In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in which the activity will be completed?
Control Charts, Flowcharting, Histograms, Pareto Charts, Scatter Diagrams are tools and techniques of what process?
Reviewing, tracking, and regulating the process to meet performance objectives defined in the project management plan are part of which process?
Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?
What is the communication channel delta if the members in the communication plan are increased from 5 to 10?
_________ is always the lowest risk for the buyer if the scope of work is not well defined.
Which monitoring or controlling activities would not result in preventive action being applied?
You have been with the organization; you constantly hear rumours about a certain CAPM failing to live up to the CAPM Code. What you should do?
You are the project manager of a project. If there are approved changes to the original scope, what you do with the old original scope?
Which of the following technique to identify the underlying cause of a problem and take steps to prevent further occurrence?
Which of the following project document is best suited for tracking costs of resources?
___________ is a group of processes required to purchase or acquire the products, services, or results needed from outside the project team to perform the work.
You are project manager of a project and as part of the team acquisition process; you hire a new employee and assigns him to your project team. According to Maslow ' s hierarchy of needs, what needs level he most likely is at?
Function of the __________ is to make sure that changes to anything in the project are recorded and agreed to by the stakeholders.
Make-or-buy decisions measure the costs of both options. What are the two options?
Collect Requirements process starts in Project Planning Phase and uses the outputs of the __________.
When communicating with large audiences, which communication method works most effectively?
In which of the team development stages are the teams interdependent and work through issues smoothly and effectively?
Which of the following is defined by a project ' s life cycle and varies by application area?
What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measure for a future project?
Monitor and control project work is a process of which of the following knowledge areas?
What quality control tool graphically represents how various elements of a system interrelate?
Which schedule format usually shows both the project network logic and the project ' s critical path schedule activities with activity date information?
In which of the following team development stages does the team meet and learn about the project and their formal roles and responsibilities?
Company A is launching a new communications satellite system. Resource B was assigned combined projects of design, construction, integration, and launch of the satellite.
Resource B ' s role is that of a:
The approval of which of the following indicates formal initiation of the project?
Using the following data, what is the Schedule Performance Index (SPI)?
EV = $500
PV= $750
AC= $1000
BAC= $1200
Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?
An activity that consumes no time or resource and shows only that a dependency exists between two activities is called:
You are project manager of a project and you are offering an estimate that you know will be changed after the contract is signed is ___________.
Which of the following plans is not done during the writing of a project plan?
Which type of network diagram allows you to depict four types of dependencies (finish-to-start, finish-to-finish, start-to-start, and start-to-finish)?
With triangular distribution, the low, likely and high values are 20, 30 and 40, respectively. The mean is _____.
You are the project manager for a Project. Project is a global project. Some peoples are working from US and some are from India. Client says budget should not cost more than $12 million. Because of the global concerns, the final budget must be in U.S. dollars. This is an example of which of the following?
Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of:
Which of the following is ensuring that all features and functions are included in a product or service
Define Scope involves subdividing the major project deliverables into smaller, more manageable components to __________.
If you are project manager for a Project and will need as many inputs to the initiation phase as possible. Of the following, which is the best source of information for your project?
You are the project manager of a project and the project is a month into the executing phase. There are some cliques forming among the team members. Which leadership style you follow for best outcome?
When you are developing the estimates for project, you choose in a mathematical model to predict estimate. What type of estimation method are you using?
Which of the following is not a part of the project cost baseline but is included in the project budget?