CCM Certified Contract Manager Questions and Answers

Questions 4

Before applying the procurement process of any FIDIC Book, the Employer should always check if there are local procurement rules that also apply. Which one of these responses is correct?

Options:

A.

No, because the FIDIC procurement process is universal.

B.

No, because Employers never have specific procurement rules.

C.

Yes, based on the law system, internal governance or type of Employer additional procurement rules can apply.

D.

Yes, but this is only applicable for public entities like governments. If the Employer is a private organisation (like a company), they are free to procure how they want.

Buy Now
Questions 5

Under the FIDIC Red Book (edition 1999), as part of the Contractor submission of Statement, any amount to be deducted for retention, will be calculated by applying the percentage of retention stated in the Appendix to Tender to the total of: (two correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The estimated contract value of the Works executed.

B.

Any amounts to be added and/or deducted for the advance payment and repayments under Sub-Clause 14.2.

C.

Any amounts to be added and deducted for changes in legislation and changes in cost.

D.

Any amounts to be added and deducted for Plant and Materials in accordance with Sub-Clause 14.5.

Buy Now
Questions 6

If defects are identified during the Tests on Completion, which one of the following options is not available to the Parties under the Contract?

Options:

A.

If the defects do not affect the use of the Works for their intended purpose, the Engineer can issue the Taking-Over Certificate.

B.

By giving reasons, the Engineer can refuse to accept the Works until repeated tests have been successfully performed.

C.

The Employer can request to take over the Works.

D.

The Party which is not liable for the cost of rectifying defects can expect the other Party to pay the cost of performing the repeated tests.

Buy Now
Questions 7

If a FIDIC Red, Yellow, or Silver Book (edition 2017) is applied, in which of the following two cases is the Contractor required to submit a revised programme?

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor shall revise the Programme only by request from the Engineer or the Employer (in case of FIDIC Silver Book).

B.

To accurately reflect the actual progress of the Works, but only if any Programme ceases to reflect actual progress with at least 42 days.

C.

To accurately reflect the actual progress of the Works, whenever any Programme ceases to reflect actual progress or is otherwise inconsistent with the Contractor's obligations.

D.

Upon a request from the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) notifying it that the Programme fails to comply with the Contract, to a specified extent, or no longer reflects actual progress or is otherwise inconsistent with the Contractor's obligations.

Buy Now
Questions 8

FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 9

Which one of the following statements is NOT correct in respect of FIDIC Red Book (both editions)?

Options:

A.

The Letter of Tender may be worded by the Contractor (at its discretion) so as to allow for the alternative of the Contract to become effective when the Employer issues a Letter of Acceptance.

B.

The Contract typically becomes legally effective when the Employer issues the Letter of Acceptance to the Contractor.

C.

The Contract is administered by the Engineer who is appointed by the Employer. If disputes arise, they are referred to a Dispute Adjudication Board (DAB) for its decisions.

D.

The General Conditions allocate the risks between the parties on a fair and equitable basis.

Buy Now
Questions 10

A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 11

You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?

Options:

A.

The Contractor submits a Value Engineering proposal, in which it proposed to change the colour of the outdoor paint. The Engineer approved the proposal.

B.

The Engineer instructs a change in slopes of stairs to the parking lot with an Instruction in accordance with Sub-Clause 3.3.

C.

The Engineer requests a proposal regarding a change in type of windows and doors of the business centre.

D.

The Employer verbally instructs a change in the layout of the rooftop restaurant. The Engineer issued an Instruction describing the required change with revised design drawings.

Buy Now
Questions 12

What does discharge confirm under the FIDIC Red Book (edition 1999)?

Options:

A.

It confirms interim settlement of all money due to the Contractor

B.

It confirms full and final settlement of all money due to the Contractor.

C.

It confirms the immediate end to the Contract unconditionally whenever issued.

D.

None of the above three statements is correct.

Buy Now
Questions 13

Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme?

Choose all of the correct answers (multiple possibilities)

Options:

A.

All internationally recognized holiday periods.

B.

The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).

C.

The sequence and timing of the remedial work.

D.

Only the delivery dates of Plant and Materials which have not been delivered on Site yet.

Buy Now
Questions 14

Is the Employer obliged under FIDIC Silver Book (edition 1999) to describe which Documents are to be submitted to the Employer? (1 correct response applies)

Options:

A.

No, according to Sub-Clause 5.7 provisional operation and maintenance manuals are always required.

B.

No, because the Contractor has a duty to supply the Employer with every Document, given Sub-Clause 7.4.

C.

Yes, because otherwise the Contractor doesn't have to submit any Document until Completion of the Works as stated in Sub-Clause 1.8.

D.

Yes, the Employer should define which documents it wants to receive from the Contractor as Contractor's Documents in the Employer's Requirements, as stated in Sub-Clause 5.2.

Buy Now
Questions 15

Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 16

Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?

Options:

A.

True

B.

False

Buy Now
Questions 17

Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor failed to renew the Tender Security.

B.

The Contractor abandons the Works and the Employer did not issue Notice of termination.

C.

The Employer had submitted a claim under Sub-Clause 20.2.

D.

The Engineer had issued instruction to replace part of the Works.

E.

The Contractor failed to extend the validity of the Performance Security.

Buy Now
Questions 18

Which of the following form a Contractor's entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

Right after the expiry of the payment deadline, the Contractor may terminate the contract.

B.

If the payment is not made within the time period required, after the expiry of such period, from the next day onwards, the Contractor is entitled to suspend all his/her activities on Site.

C.

In case the Employer paid the Contractor late, the Contractor becomes entitled to receive financing charges applying the % included in the Contract Data (if this is not stated, then applying the percentage as included under the corresponding Sub-Clause).

D.

The Contractor is entitled to suspend the works or reduce the rate of progress of the work, after giving a due Notice (21 days) about this intention.

E.

Beyond receiving the financing charges, the Contractor has no further entitlements in such a case.

Buy Now
Questions 19

You are the Contract Manager of the Contractor in a building project. The Contract has been awarded to your firm, but the Engineer has not been selected. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, which must be done within 14 days after the signing of the Contract Agreement. The Employer requested your firm to commence works on the 14th day after signing the Contract Agreement. Your director, Y, wants to wait with commencing the works until the Engineer has been selected or until the 42 days since the date your firm receives Letter of Acceptance. Is Y correct?

Options:

A.

Yes

B.

No

Buy Now
Questions 20

You are the Contract Manager of the Employer's Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer's Requirements require that: "the Contractor design in accordance with international and national technical regulations, and standards, [etc.]".

For piling works, the Employer's Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for 200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer's Requirements.

In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m. However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding. The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.

As the Employer's Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.

In your "Notice of the Employer's Representative's determination", what is your determination for the Contractor?

Options:

A.

The Contractor is not entitled to either of the Claims.

B.

The Contractor is entitled to the Claim for additional costs in relation to the piling, based on errors in the Employer's Requirement only.

C.

The Contractor is entitled to the Claim for the additional flood wall based on Unforeseeable difficulties only.

D.

The Contractor is entitled to both Claims.

Buy Now
Questions 21

A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?

Options:

A.

If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.

B.

The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.

C.

In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.

D.

If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.

Buy Now
Questions 22

You are the Contract Manager of the Engineer for a contract using FIDIC Yellow Book (edition 2017). You are drafting a notice holding the Commencement Date. Which one of the following approaches has the most clear and unambiguous drafting?

Options:

A.

I hereby give notice, in accordance with Sub-Clause 8.1 of the Conditions of Contract, the Commencement Date shall be 17 April 2023.

B.

The Contractor is kindly notified that the project shall be started by 17 April 2023.

C.

The commencement date of this project under Sub-Clause 8.1 of the Conditions of Contract will be 10 days from 7 April 2023.

D.

I hereby give notice, in accordance with Sub-Clause 1.1.84 and 8.2 of the Conditions of Contract, that the Time for Completion shall commence from 17 April 2023.

Buy Now
Questions 23

In case a Variation is initiated by the Engineer for prompt implementation ...... [FIDIC Red, and Yellow Books, 2017 Editions]

Choose all of the correct answers (multiple possibilities).

Options:

A.

... the Contractor may send a Notice to the Engineer, that the subject of the Variation was Unforeseeable (having regard to the scope and nature of the Works), hence, the Contractor is not to start implementing the varied work promptly.

B.

... the Contractor is required to commence implementing the varied works and take records of all the details ( ... regarding the details of the varied works executed, expenditures incurred, and impact on progress etc.)

C.

... the Contractor is required to commence implementing the varied works even if it would pose immediate hazard to the safety of public areas surrounding the Site

D.

... the Contractor within 28 days after receiving such instruction shall submit to the Engineer a description of the varied work, a programme for its execution and a proposal for adjustment of the Contract Price.

E.

... the Contractor is not bound to start implementing the varied works right up until the price for the varied works is fully agreed (or determined)

Buy Now
Questions 24

Which one of the following statements best describes the requirements of Time for Completion?

Options:

A.

This is the Contractor's fundamental time-related obligation, namely completion the whole of the Works within the Time for Completion calculated from the Commencement Date.

B.

This is the Contractor's fundamental time-related obligation, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Commencement Date.

C.

This is one of the Contractor's obligations, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Commencement Date.

D.

This is one of the Contractor's obligations, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Effective Date.

Buy Now
Questions 25

The details of all the matters that have been clarified and agreed between the Employer and tenderers during the tender stage are recorded by, for instance, a memorandum of understanding. The Employer may award the contract to the tenderer through a letter of formal acceptance, signed by the Employer. This process is in compliance with which one of the following Golden Principles (GP's)?

Options:

A.

GP 3

B.

GP 1

C.

GP 2

D.

GPA

Buy Now
Questions 26

Through which two of the following documents may the Employer give information to the Contractor of a planned timetable of meetings such as management meetings, site meetings, technical meetings, and progress meetings?

Choose all of the correct answers (multiple possibilities).

Options:

A.

General Conditions of Contract

B.

Specification

C.

Special Conditions

D.

Employer's Requirements

Buy Now
Questions 27

Which two statements reflect an INCORRECT application of a Golden Principle?

Options:

A.

Any deletions of General Conditions (GC) must be replaced with Particular Conditions (PC) that cover the same scope, and do not leave any roles, duties, obligations, rights, and risk allocation undefined.

B.

When applying the FIDIC Red Book or Yellow Book, the Commencement Date shall be within 60 days after the Contractor receives the Letter of Acceptance, in lieu of 42 days.

C.

The Contractor's right to suspend work (or reduce the rate of work) effective after giving not less than 3 months (in lieu of 21 days) notice to the Employer.

D.

Deleting all the clauses in the General Conditions that refer to the DAAB/DAB.

Buy Now
Questions 28

Which of the following statements are not correct? [2017 Edition]

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor or the Engineer can request a meeting.

B.

Only the Engineer can call for a meeting

C.

Subcontractors cannot attend management or progress meetings unless the Engineer's approval is obtained.

D.

Only the Employer can call for a meeting.

E.

The Engineer shall keep records of the Progress Meetings.

Buy Now
Exam Code: CCM
Exam Name: Certified Contract Manager
Last Update: Sep 24, 2025
Questions: 100