CCM Certified Contract Manager Questions and Answers

Questions 4

Which one of the following statements best describes the requirements of Time for Completion?

Options:

A.

This is the Contractor ' s fundamental time-related obligation, namely completion the whole of the Works within the Time for Completion calculated from the Commencement Date.

B.

This is the Contractor ' s fundamental time-related obligation, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Commencement Date.

C.

This is one of the Contractor ' s obligations, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Commencement Date.

D.

This is one of the Contractor ' s obligations, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Effective Date.

Buy Now
Questions 5

(Which of the following two statements are correct regarding subcontractors under FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The Contractor shall obtain the Engineer’s and the Employer’s prior consent to all Subcontractors.

B.

If no maximum allowable accumulated value of work subcontracted is stated in the Contract Data, the Contractor shall not be entitled to subcontract the whole of the Works without prior consent of the Engineer.

C.

The Contractor shall not be responsible for the acts or defaults of any Subcontractor.

D.

The Contract Data may identify parts of the Works which the Contractor is not entitled to subcontract.

Buy Now
Questions 6

When is the Employer obliged to return the Performance Security (PS) under the FIDIC Red Book (edition 1999)?

Options:

A.

Without undue delay after the issuance of the Taking-Over Certificate.

B.

Without undue delay after the issuance of the Performance Certificate.

C.

Within 21 days after the issuance of the Taking-Over Certificate.

D.

Within 21 days after the issuance of the Performance Certificate.

Buy Now
Questions 7

(You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999). There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter? (1 correct answer applies))

Options:

A.

Each index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works.

B.

The current index or price.

C.

Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever is more favourable to the Employer.

D.

Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever is agreed by the Parties.

Buy Now
Questions 8

(You are the Contract Manager in a contract using the FIDIC Red Book with a Dispute Avoidance and Adjudication Board. The DAAB is already appointed (standing DAAB). You are coaching your team on the steps to be followed to request for informal assistance from the DAAB during a Site visit. Which one of the following does NOT belong to those steps?)

Options:

A.

The Employer and the Contractor have identified an issue and disagreement, and have agreed between themselves that they want the DAAB to provide assistance and/or informally discuss and attempt to resolve that issue/disagreement.

B.

The Engineer has made a non-objection letter, in which it is stated that the issue/disagreement does not concern the matter that is being dealt with by the Engineer.

C.

The Employer and the Contractor have made a " joint request " in writing before the DAAB gives the requested assistance.

D.

Both Parties should be present at the meeting in which the DAAB provides assistance.

Buy Now
Questions 9

You are the Contract Manager of the Contractor in a building project. The Contract has been awarded to your firm, but the Engineer has not been selected. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, which must be done within 14 days after the signing of the Contract Agreement. The Employer requested your firm to commence works on the 14th day after signing the Contract Agreement. Your director, Y, wants to wait with commencing the works until the Engineer has been selected or until the 42 days since the date your firm receives Letter of Acceptance. Is Y correct?

Options:

A.

Yes

B.

No

Buy Now
Questions 10

If a FIDIC Red, Yellow, or Silver Book (edition 2017) is applied, in which of the following two cases is the Contractor required to submit a revised programme?

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor shall revise the Programme only by request from the Engineer or the Employer (in case of FIDIC Silver Book).

B.

To accurately reflect the actual progress of the Works, but only if any Programme ceases to reflect actual progress with at least 42 days.

C.

To accurately reflect the actual progress of the Works, whenever any Programme ceases to reflect actual progress or is otherwise inconsistent with the Contractor ' s obligations.

D.

Upon a request from the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) notifying it that the Programme fails to comply with the Contract, to a specified extent, or no longer reflects actual progress or is otherwise inconsistent with the Contractor ' s obligations.

Buy Now
Questions 11

You are teaching a group of early career professionals in the Contract Management department about the FIDIC 2017 Rainbow Suite of contract, and you are explaining about the intention of Delay Damages. Which one of the following statements is correct?

Options:

A.

Delay Damages is intended to provide full compensation to the Employer for all damages that it is expected to suffer as a result of the delay.

B.

Delay Damages is intended to be treated as an incentive for the Contractor to perform on time.

C.

Delay Damages is not intended to remove burden for the Employer to demonstrate and prove that it has suffered any loss or damage.

D.

None of the above.

Buy Now
Questions 12

(Under the FIDIC Red, Yellow, and Silver Books (1999 editions), the Engineer/Employer shall be entitled to withhold from the release of retention money the estimated cost of any work which remains to be executed under Clause 11 (Defects Liability) in the Red Book or under Clause 12 (Tests after Completion) in the Yellow and Silver Books. Is this statement true or false?)

Options:

A.

True

B.

False

Buy Now
Questions 13

(Under the FIDIC Red, Yellow, and Silver Books (edition 1999), which of the following entitlements of the Employer can result in a deduction of the Contract Price and Payment Certificates subject to Sub-Clause 2.5? (2 correct answers apply))

Options:

A.

Paying the Nominated Subcontractor directly.

B.

Compensation for the costs of the initial review of the Contractor ' s Documents.

C.

Delay Damages.

D.

Cost of using the Employer ' s materials.

Buy Now
Questions 14

(Which two FIDIC Books (edition 2017) should especially be considered for use if the Employer needs the Contractor to take responsibility for the design and execution of the project. The construction will involve substantial work underground or work in other areas which tenderers cannot inspect.

Choose all of the correct answers (multiple possibilities).)

Options:

A.

Yellow Book

B.

Red Book

C.

Silver Book by amending Sub-Clause 4.12 in the Particular Conditions

D.

Silver Book without amending Sub-Clause 4.12 in the Particular Conditions

Buy Now
Questions 15

Which one of the following is not a required document to be submitted by the Contractor if the Employer requests a proposal, prior to instructing a Variation, for FIDIC 2017 Yellow Book?

Options:

A.

A description of the varied work.

B.

A description of the proposed design.

C.

Details of the resources and methods to be adopted by the Contractor.

D.

A Programme for execution of the varied work.

Buy Now
Questions 16

You are the Contract Manager of the Engineer in a hotel project. In May 2020, the Employer and the Contractor signed a Contract based on the FIDIC Yellow Book (edition 2017), as per which the Contractor will design and build a hotel project with Contract Price of 5,100,000 USD. The Time for Completion for this project is 12 months (May 2021). The Contract also named a nominated Subcontractor (as referred to in Sub-Clause 4.5) who provides mechanical, electrical, and plumbing services for the project (including the fire fighting system), which was accepted by the Contractor without any discussions.

The Project was delayed due to issues with the fire fighting system, and you issued the Taking-Over Certificate in June 2022.

The Employer sent a Notice of Claim to the Contractor on Delay Damages with a maximum value equal to 10% of Contract Price (510,000 USD). The Employer also gave a Notice to the Contractor stating that the Contractor has failed to submit the evidence of payment to the nominated Subcontractor as well as the reason for withholding payment to the nominated Subcontractor. Therefore, the Employer has paid the nominated Subcontractor directly the entire amount due, coming to 100,000 USD. The Employer intends to include this amount as a deduction in the Final Payment to the Contractor.

As Contract Manager of the Engineer, you are tasked to make a fair determination of the Notices of the Employer. In your " Notice of the Engineer ' s determination " , what is your determination for the deduction of the next Interim Payment to the Contractor in relation to the amount directly paid to the nominated Subcontractor?

Options:

A.

The Employer is entitled to deduct the amount directly paid.

B.

The Employer is not entitled to deduct the amount directly paid.

Buy Now
Questions 17

There are four reasons that the Employer/Contractor shall advise in advance each other and the Engineer of any known or future events or circumstances.

Which two of the following statements are NOT applicable reasons?

(Choose all correct answers — multiple possibilities)

Options:

A.

Delay the execution of the Works or a Section.

B.

Decrease the Contract Price.

C.

Adversely affect the work of the Contractor ' s Personnel.

D.

Increase the performance of the Works when completed.

Buy Now
Questions 18

Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 19

Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?

Choose all of the correct answers (multiple possibilities).

Options:

A.

If a Daywork Schedule is not included in the Contract, the Sub-Clause related to dayworks shall not apply.

B.

The dayworks related Sub-Clause is also applicable to other types of works.

C.

The dayworks related Sub-Clause is only used for remeasurement in the FIDIC Red Book (both editions) only.

D.

The Engineer (or the Employer in case of FIDIC Silver Book) may instruct that " a Variation shall " be executed on a daywork basis.

Buy Now
Questions 20

You are the Contract Manager of the Engineer for a contract using FIDIC Yellow Book (edition 2017). You are drafting a notice holding the Commencement Date. Which one of the following approaches has the most clear and unambiguous drafting?

Options:

A.

I hereby give notice, in accordance with Sub-Clause 8.1 of the Conditions of Contract, the Commencement Date shall be 17 April 2023.

B.

The Contractor is kindly notified that the project shall be started by 17 April 2023.

C.

The commencement date of this project under Sub-Clause 8.1 of the Conditions of Contract will be 10 days from 7 April 2023.

D.

I hereby give notice, in accordance with Sub-Clause 1.1.84 and 8.2 of the Conditions of Contract, that the Time for Completion shall commence from 17 April 2023.

Buy Now
Questions 21

Choose which one statement consists of an example of an unclear and ambiguously drafted Particular Conditions.

Options:

A.

Provisions of the General Conditions are deleted and replaced in the Particular Conditions solely by the words " not used " .

B.

All deletions of a General Conditions are replaced with new Particular Conditions that cover the same scope.

C.

Clarifications to the meaning of tender documents together with answers to tenderers ' inquiries made during the tender period by the Employer should be e-mailed in a Excel table in both PDF and XLS file format.

D.

The clarifications to the Contract given during the tender period are never to be attached to the Contract, as such clarifications are reflected by amending the Particular Conditions.

Buy Now
Questions 22

(In FIDIC contracts, a number of time limits are included for the Parties and the Engineer to perform various obligations. How are failures to comply with these time limits most typically being dealt with in these forms of contracts? [2017 Edition] (1 correct answer))

Options:

A.

In all these cases, the stakeholder not performing a required action within the allocated time limit loses all of his/her related rights that he/she otherwise would have in relation to this matter.

B.

If a Party fails to perform an obligation within the allocated time limit, then the failing party shall pay damages to the other Party.

C.

In these cases, there is a " deemed " outcome if the stakeholder does not take action within the pre-set period of time – all enabling to secure continuity of contractual processes.

D.

A Party ' s failure to perform an obligation within the allocated time limit would mean that the Engineer ' s or Employer’s decision becomes automatically binding.

Buy Now
Questions 23

Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme?

Choose all of the correct answers (multiple possibilities)

Options:

A.

All internationally recognized holiday periods.

B.

The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).

C.

The sequence and timing of the remedial work.

D.

Only the delivery dates of Plant and Materials which have not been delivered on Site yet.

Buy Now
Questions 24

Under the FIDIC Red and Yellow Books (edition 1999): if the Engineer gives an instruction which requires the Employer ' s prior approval, the Contractor is required to verify whether the Engineer has obtained the Employer ' s prior approval or not. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Questions 25

(The Employer is a leading company in the hospital and medical care sector who wishes to build a new hospital. The Employer is considering approaching a financial institute to secure most of the funds; therefore, he requires clarity and stability in terms of the Project ' s budget and time for completion. Which book do you recommend?)

Options:

A.

Red Book

B.

Yellow Book

C.

Silver Book

D.

All the above

Buy Now
Questions 26

Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities)

Options:

A.

In case the Engineer refuses to issue a Performance Certificate or to issue one with a correct date under Sub-Clause 11.9, and the Contractor has disagreed with the requested entitlement or relief in connection with this refusal, Dispute shall be deemed to have arisen.

B.

If a Party is dissatisfied with the determination and has given Notice of Dissatisfaction (NOD) to the other party within a strict 28-day time limit, a Dispute arises and either Party may proceed under Sub-Clause 21.4 to obtain a DAAB decision on it.

C.

The Dispute must be submitted to the Dispute Avoidance and Adjudication Board (DAAB) within 42 days, otherwise the NOD is deemed to have lapsed and is no longer valid.

D.

Both ' Disagreement ' and ' Dispute ' are defined terms under the Conditions of Contract.

Buy Now
Questions 27

You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition 2017). The project had been suspended due to a material change in the Employer ' s financial arrangement. You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?

Options:

A.

A prolonged suspension for more than 1 year has affected the whole of the Works.

B.

The Contractor does not receive the amount due under the latest Payment Certificate for more than 4 months after the due date.

C.

The Contractor has requested the Employer but has not received any evidence that the financial arrangement is being maintained, despite having sent a notice thereto 4 months earlier.

D.

The Employer failed to comply with a final and binding determination issued by the Engineer, and such failure constitutes a material breach of the Employer ' s obligations under the Contract.

Buy Now
Questions 28

Which one of the following statements is NOT correct in respect of FIDIC Red Book (both editions)?

Options:

A.

The Letter of Tender may be worded by the Contractor (at its discretion) so as to allow for the alternative of the Contract to become effective when the Employer issues a Letter of Acceptance.

B.

The Contract typically becomes legally effective when the Employer issues the Letter of Acceptance to the Contractor.

C.

The Contract is administered by the Engineer who is appointed by the Employer. If disputes arise, they are referred to a Dispute Adjudication Board (DAB) for its decisions.

D.

The General Conditions allocate the risks between the parties on a fair and equitable basis.

Buy Now
Questions 29

Which two statements are true under the FIDIC Red Book (edition 1999)?

(Choose all of the correct answers — multiple possibilities)

Options:

A.

The Performance Certificate is deemed to constitute the acceptance of the Works.

B.

The Performance Certificate constitutes acceptance of the Works and full performance of all obligations of each Party.

C.

The Engineer shall issue the Performance Certificate within 28 days at the latest: by the end of the Defects Notification Periods, and once the Contractor has supplied all the Contractor ' s Documents and completed and tested all Works including remedying any defects in accordance with the Contract.

D.

The Performance Certificate is deemed to be issued on fulfilment of certain conditions stated in the respective Sub-Clause.

Buy Now
Questions 30

Which of the following form a Contractor ' s entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

Right after the expiry of the payment deadline, the Contractor may terminate the contract.

B.

If the payment is not made within the time period required, after the expiry of such period, from the next day onwards, the Contractor is entitled to suspend all his/her activities on Site.

C.

In case the Employer paid the Contractor late, the Contractor becomes entitled to receive financing charges applying the % included in the Contract Data (if this is not stated, then applying the percentage as included under the corresponding Sub-Clause).

D.

The Contractor is entitled to suspend the works or reduce the rate of progress of the work, after giving a due Notice (21 days) about this intention.

E.

Beyond receiving the financing charges, the Contractor has no further entitlements in such a case.

Buy Now
Questions 31

(Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to give notice to the Employer if it discovers errors or defects of a technical nature. Is this statement true or false?)

Options:

A.

True

B.

False

Buy Now
Questions 32

(Please select the one answer in which the mentioned documents are in the correct order (hierarchy), as mentioned in the standard Contract Agreement form of the FIDIC Silver Book (edition 1999).)

Options:

A.

Contract Agreement, Conditions of Contract, Employer’s Requirements, Contractor ' s Tender, Addenda.

B.

Contract Agreement, Conditions of Contract, Addenda, Contractor ' s Tender, Employer’s Requirements.

C.

Contract Agreement, Conditions of Contract, Addenda, Employer’s Requirements, Contractor ' s Tender.

D.

Contract Agreement, Addenda, Conditions of Contract, Employer’s Requirements, Contractor ' s Tender.

Buy Now
Questions 33

(Which of the following types of insurances belong to the basic (typical) scope of insurances? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).)

Options:

A.

Injury to persons and damage to property.

B.

Force Majeure Insurance.

C.

Insurance of Goods and other things brought to Site.

D.

Insurance for non-performance of the Works.

Buy Now
Questions 34

Regarding the FIDIC Red Book (edition 1999), which two statements are true?

Options:

A.

In emergency situations notices can also be submitted verbally (rather than (also) in writing).

B.

A notice is to be signed by the Engineer, Contractor ' s Representative or Employer ' s Authorised Representative.

C.

A notice and other communications may be delivered by hand, courier and mail. In each case with proof of receipt is required to qualify as legally valid.

D.

Notices and other communications may be sent in hand written, type written, in print or through an electronic original transmission system.

Buy Now
Questions 35

Which of the following FIDIC contract forms require certification in the payment process? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

FIDIC Conditions of Contract for Construction ( " Red Book " ).

B.

FIDIC Conditions of Contract for Plant and Design Build ( " Yellow Book " ).

C.

FIDIC Conditions of Contract for EPC/Turnkey Projects ( " Silver Book " ).

Buy Now
Questions 36

Under the FIDIC Red Book (edition 1999): the Contractor submitted Final Statement in accordance with the Contract and the Contractor wants to correct it. Can the Contractor correct the Final Statement?

Options:

A.

Yes

B.

No

Buy Now
Questions 37

You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer – a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted?

Choose all of the correct answers (multiple possibilities).

Options:

A.

Specify Commencement Date in the Minutes of Meeting of Contract Negotiation.

B.

Specify Commencement Date in the Contract Agreement.

C.

Specify Commencement Date in the Particular Conditions.

D.

Inform the Commencement Date to the tenderers by email, and attach that email in the list of Contract Documents.

Buy Now
Questions 38

Under the FIDIC Construction Contract, which one of the following statements is correct?

Options:

A.

Payments of a DAB Member ' s retainer fee is the sole responsibility of the Contractor.

B.

For an ad-hoc DAB, a retainer fee for each DAB Member must be paid to the Member on the first day of each calendar month.

C.

Payment to DAB Members must be certified by the Employer.

D.

If all persons nominated to serve as members of an ad hoc DAB do not sign a DAB Agreement, an appointing entity can make appointments.

E.

A DAB must give its decision in writing on any dispute when requested by one of the Parties.

Buy Now
Questions 39

If the Engineer is required to obtain the Employer ' s prior approval to issue determinations (including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

Remain silent and not do anything in the subject.

B.

The Engineer should refer the matter in subject to the DAB.

C.

Issuing the determination to the Contractor in the form and with the content agreeable to the Employer, with a remark, that it is the Employer ' s determination and not the Engineer ' s determination.

D.

Informing the Contractor of their inability of issuing the determination, in lack of the Employer ' s necessary approval.

Buy Now
Questions 40

You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow Book (edition 2017). The Employer demands perfection in the project ' s design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?

Options:

A.

The Contractor submits a Value Engineering proposal regarding the lighting system for the operation rooms. The Engineer is positive about the proposal and tells the Contractor they need to look into it.

B.

The Engineer instructs a change in slopes of the access road to the intensive care unit to meet the Employer ' s Requirement. The Engineer does so with a Notice in accordance with Sub-Clause 3.5.

C.

The Engineer requests a proposal regarding a change in type of windows and doors. The Contractor submitted the proposal accordingly to the Engineer. The Engineer instructs the Variation.

D.

The Employer verbally instructs a change in the type of doors. The Engineer issued a Notice describing the required change and denying any costs for the Contractor.

Buy Now
Questions 41

(FIDIC Red Book (edition 2017) stipulates that the measurement shall be made as per the actual quantities executed at Site. Which one of the following statements is correct?)

Options:

A.

The measurement shall be always made of the net actual quantity of each item of the Permanent Works.

B.

The measurement shall be made of actual quantity of each item of the Permanent Works with allowance of shrinkage of the used materials.

C.

Measurements of the actual quantity of an item of the Permanent Works that was not specified in the Bill of Quantities, the Contractor will choose the appropriate price.

D.

None of the above are correct.

Buy Now
Exam Code: CCM
Exam Name: Certified Contract Manager
Last Update: Apr 3, 2026
Questions: 140

PDF + Testing Engine

$63.52  $181.49

Testing Engine

$50.57  $144.49
buy now CCM testing engine

PDF (Q&A)

$43.57  $124.49
buy now CCM pdf