Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

CCP Certified Cost Professional (CCP) Exam Questions and Answers

Questions 4

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Which of the following statements of the measures of central tendency is correct?

Options:

A.

The mean is the measure that of the large data set

B.

The median is the measure that is mostly affected by extreme values

C.

The mode only uses the two extreme values and ignores the test of the data set

D.

The mode would be frequently applied in marketing to determine shirt sizes or shoes sizes

Buy Now
Questions 5

A work breakdown structure (WBS) is developed because:

Options:

A.

It avoids omissions of key product activities through a systematic planning process; removes the complexity of the project by dividing it into manageable units; and provides a framework.

B.

It defines specific tasks within a project from which schedules can be developed; it aids in linking activities with resources; it facilitates communication; and it allows integration of project plans

C.

It can be illustrated by individual bars for major phases, such as permitting, funding, engineering, procurement construction, commission/startup

D.

It can be illustrated by a simple bar, with important milestones represented by symbols at the planned time of occurrence

Buy Now
Questions 6

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is a method for figuring estimate at completion (EAC)?

Options:

A.

BCWP + (BAG - ACWP)

B.

ACWP + (BAC - BCWS)

C.

BCWS + (BAG -ACWP)

D.

ACWP + (BAC - BCWP)

Buy Now
Questions 7

A small hole construction project has a baseline budget of $1,000,000. The project is scheduled to be constructed in 12 months. At the and of the first month, the project data is reported as below:

CCP Question 7

The longest path depends upon relationships driving the timing of activity starts, therefore the following scheduling features should not be used in calculating file longest path.

Options:

A.

milestone activities

B.

activities with lag

C.

activities with short durations

D.

constraints, resource leveling, and interruptible activities

Buy Now
Questions 8

If a project is said to be on a "fast track program/' the fast track method is:

Options:

A.

Simultaneous working engineering, procurement, and construction, with appropriate overlap from each phase of work so that delays are eliminated and all the work is streamlined into a correct plan of logic/sequence and duration for all of the work

B.

First completing engineering and procurement, then executing construction

C.

Analyzing the project and specifying the basic approach to be used in its execution; segmenting the project into reasonable number of activities; estimating the time required to perform each activity; placing the activities in time order, considering both sequential and parallel performance

D.

Revising the schedule logic to make it possible to identify constraints of faulty logic; revising the durations in the n p schedule that have been based on assumptions regarding the \hay the work would be performed; revise the resources to work multiple shifts; evaluate the use of overtime

Buy Now
Questions 9

____________ is the application of total resources ($-workers-supports) and activity durations of the logic diagram.

Options:

A.

Planning

B.

Forecasting

C.

Scheduling

D.

Modeling

Buy Now
Questions 10

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

Which of the following should be included in the life-cycle cost analysis of a power plant?

Options:

A.

Construction cost, operating cost, maintenance cost

B.

Factory expenses, distribution expenses, mark-up

C.

Capacity factor, end product units, physical dimensions

D.

Resources, work activities, final cost objects

Buy Now
Questions 11

When measuring progress using tasks that lack readily definable intermediate milestones and level of effort required is difficult to measure, the best methods to use is:

Options:

A.

Start/finish

B.

Weighted or equivalent units

C.

Incremental milestones

D.

Cost ratio

Buy Now
Questions 12

A concrete slab measuring 10 feet wide by 13.5 feet long by 6 inches deep is to be installed. How many cubic yards of concrete will be required?

Options:

A.

3.0 cubic yards

B.

2.0 cubic yards

C.

3.5 cubic yards

D.

2.5 cubic yards

Buy Now
Questions 13

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

Options:

A.

Activity total slack

B.

Remaining duration

C.

Just-in-time" scheduling

D.

Free float

Buy Now
Questions 14

In a fixed price contract the:

Options:

A.

Contractor has no risk in the project

B.

Contactor assumes all the performance risk

C.

Contractor is paid for actual costs

D.

Owner has all the risk

Buy Now
Questions 15

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

Which of the following interest rates disregards the effects of compounding periods that occur more frequent than annually?

Options:

A.

Continuous compounding rate

B.

Simple interest rate

C.

Minimum attractive rate of return

D.

Nominal interest rate

Buy Now
Questions 16

_____________is defined as the budget for the cost (work) account times the percent complete for that account.

Options:

A.

Percent complete

B.

Forecast

C.

Cost to complete

D.

Earned value

Buy Now
Questions 17

AACE International defines _____________as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.

Options:

A.

Risk analysis

B.

Benefit/Cost ratio (B/C) method

C.

Net present worth method

D.

Life cycle costs method (LCC)

Buy Now
Questions 18

As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.

The following revenue and expense relationships are predicted:

CCP Question 18

Marketing has determined that XY2 can safely increase their per unit selling price to SO.55. The new break even amount for sales (in units) based on the new contribution margin is:

Options:

A.

40,000 units

B.

6,000 units

C.

50,000 units

D.

60,000 units

Buy Now
Questions 19

CCP Question 19

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of 30 months, copper prices will have increased by what percentage over today's price?

Options:

A.

4.6%

B.

3.5%

C.

6.6%

D.

2.5%

Buy Now
Questions 20

Any combination of unique letters, numbers, or blanks, which describes and identifies any activity or task shown on the schedule, is:

Options:

A.

Activity ID

B.

WBS Code

C.

Resource

D.

Account number

Buy Now
Questions 21

CCP Question 21

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the relative frequency of unit costs from Atlanta, GA?

Options:

A.

$40.59

B.

3

C.

$48.33

D.

33.33%

Buy Now
Questions 22

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

CCP Question 22

The amount of interest paid during the fifth year of depreciation would be:

Options:

A.

$126.00

B.

$1,200.00

C.

$1,260.00

D.

$12,000.00

Buy Now
Questions 23

What relationship more accurately defines a situation model of parallel activities that require a partial start of one activity?

Options:

A.

Start to start

B.

Star to finish

C.

Finish to start

D.

Finish to finish

Buy Now
Questions 24

How can the quality of a cost/capacity factor estimate be improved?

Options:

A.

Validate the capacity factor from similar, recently completed projects

B.

Validate law productivity from recently completed projects

C.

Verify the labor rates used in the estimate

D.

Verify the equipment costs used in the estimate

Buy Now
Questions 25

CCP Question 25

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is 1.03. How many hours were planned?

Options:

A.

10,586

B.

9,280

C.

9,559

D.

10,278

Buy Now
Questions 26

Which of the following best describes the concept of total cost management:

Options:

A.

A method of quantifying construction damages where the total job costs are subtracted from the original bid or estimate to determine the total cost amount for a claim

B.

The practices and processes utilized to manage the total life cycle cost investment in a portfolio of strategic assets

C.

A job cost system for ensuring all aspects of a particular manufacturing process are accumulated completely

D.

An integrating process that maps the fields of practice of cost engineering without linking it to project management, resource management, or accounting

Buy Now
Questions 27

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Assuming the average life span of a lithium battery is two years and is normally distributed with a standard deviation of two months, what is the probability the battery will last between 20 months and 26 months?

Options:

A.

82%

B.

75%

C.

90%

D.

84%

Buy Now
Questions 28

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The return on investment at the end of the fifth year would be:

Options:

A.

Greater than 10%

B.

Unknown

C.

Equal to 10%

D.

Less than 10%

Buy Now
Questions 29

A bond that guarantees the bidder will enter into a contract on the basis of his/her bid is referred to as:

Options:

A.

Surety bond

B.

Performance bond

C.

Bid bond

D.

Liability bond

Buy Now
Questions 30

CCP Question 30

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

An unbalanced bid methodology can best be used by:

Options:

A.

Engineer/contractor working for the owner (Plan B)

B.

Subcontractor working for contractor (Plan A or B)

C.

Contractor working directly for engineer (plan A or B)

D.

Engineer working for the owner (Plan A)

Buy Now
Questions 31

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The value of the truck at the end of year five (5) would be:

Options:

A.

$0

B.

$14,265

C.

$25,000

D.

$23,366

Buy Now
Questions 32

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve. Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assume money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If $10,000 is invested now at 10% compounded annually, what will the investments be worth 10 years from now?

Options:

A.

$25,940

B.

$29,450

C.

$21,345

D.

$16,180

Buy Now
Questions 33

Budgeted cost of work scheduled is all of the following except:

Options:

A.

Total costs incurred in accomplishing work in a given-time period

B.

Baseline for performance measurement

C.

Sum of the budgets for work scheduled

D.

Includes portion of the budget for level-of-effort work

Buy Now
Questions 34

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

CCP Question 34

The following question requites your selection of Scenario 1.4.150 from the tight side of your split screen. using the drop down menu, to reference during your response/choice o' responses

The present worth interest factor for this purchase in the fifth year would be:

Options:

A.

0.6209

B.

1.6474

C.

1.6105

D.

0.6070

Buy Now
Questions 35

CCP Question 35

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If the owner in A has a primary goal of completion within budget, the following contract types with the engineer/contractor would be best:

Options:

A.

Engineer — cost plus, contractor fixed price

B.

Engineer — cost plus, contractor cost plus

C.

Engineer fixed price, contactor cost plus

D.

Engineer — fixed price, contractor fixed price

Buy Now
Questions 36

CCP Question 36

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal)

Options:

A.

8.7%

B.

8.2%

C.

4.6%

D.

8.0%

Buy Now
Questions 37

CCP Question 37

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

The entire pipe has been received, hangers have been installed, and all pipes are in place. None has been welded or flushed. What percent complete is this project?

Options:

A.

45%

B.

50%

C.

95%

D.

30%

Buy Now
Questions 38

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What class of estimate is used for the preliminary design phase of a project?

Options:

A.

Class 5 - order of magnitude estimate with +50% / -30% accuracy

B.

Class 1 - order of magnitude with +30% / -30% accuracy

C.

Class 4 - budget estimate with +30% / -15% accuracy

D.

Class 2 - definitive estimate with +15%/-5% accuracy

Buy Now
Questions 39

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

In Rensis1 4 model system, the exploitative-authoritative management style is one in which:

Options:

A.

Management makes most decisions and passes them down

B.

Informal organizations generally support the goals of the formal organization

C.

Management issues orders, but employees have some freedom to comment

D.

Management has a lot of confidence in the employees

Buy Now
Questions 40

CCP Question 40

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of Year 4, the commodity which experienced the greatest projected percentage price index increase over today is:

Options:

A.

None of the above

B.

Manufacturing labor

C.

Steel

D.

Copper

Buy Now
Questions 41

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Which statement best describes the type of information available for a design phase estimate?

Options:

A.

Home office detail, specific vendor quotes, preliminary quantities with labor and material factors applied

B.

Square footage of buildings, factored indirects, types of rides and exhibits identified, utility requirements, conceptual layouts

C.

Detailed construction drawings, quantity takeoffs, detailed labor hours and material costs applied, quotes from all major subcontractors

D.

Utility requirements, detailed building plans and (- specifications, types of rides and exhibits identified, all vendor quotes or estimates received from subcontractors

Buy Now
Questions 42

As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.

The following revenue and expense relationships are predicted:

CCP Question 42

If the fixed rent remains unchanged, and XYZ pays S0.01 per unit as additional rent, the monthly breakeven point in numbers of units becomes:

Options:

A.

48,500 units

B.

66,667 units

C.

52,500 units

D.

33,333 units

Buy Now
Questions 43

Cost performance index (CPI) is defined by AACE International as: (assume no change in budgeted quantities)

Options:

A.

ACWP/BCWS

B.

BCWS/BCWP

C.

ACWP/BCWP

D.

BCWP/ACWP

Buy Now
Questions 44

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

All of the following are included in "income tax" calculations except:

Options:

A.

Annual income

B.

Annual expenditures

C.

Depreciation

D.

Initial cost of investment

Buy Now
Questions 45

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The main financial objective of many enterprises is:

Options:

A.

To maximize the total long-term economic return

B.

Subject to a well-conceived quality control plan

C.

To balance opportunities and risks

D.

Dependent on the backlog projects and the availability of resources

Buy Now
Questions 46

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If $20,000 is invested at the end of each fiscal year for the next 10 years, how much would our total investment be worth assuming the interest is at 10%?

Options:

A.

$289,370

B.

$318,740

C.

$265,798

D.

$420,236

Buy Now
Questions 47

When the project plan is implemented:

Options:

A.

Activities are carefully monitored and controlled against the baseline

B.

The basis for payment applications is formalized

C.

The forward and backward pass is identified

D.

CPI and SPI can be calculated and reported

Buy Now
Questions 48

The four steps to writing are:

Options:

A.

Introduction, paragraph, conclusion, works cited

B.

Start, write, complete, revise

C.

Abstract, body conclusion, bibliography

D.

Plan, write, cool, revise

Buy Now
Questions 49

The measure of number of units completed divided by work-hours consumed is referred to as:

Options:

A.

lined value

B.

Credit work-hours

C.

Productivity

D.

Cost performance Index (CPI)

Buy Now
Questions 50

SCENARIO: A can manufacturing company requested you to provide data for their decision making The unit prices of the can varies but an average selling price of $0.55 cents and average cost of S45 cents is estimated.

The monthly fixed costs are:

Rant-$1,500

Wages - $4.000

Miscellaneous fixed expenses - $500

If the rent increases by 100% and the unit sales/other costs remain unchanged, the new break even amount is?

Options:

A.

$60,000

B.

$41,250

C.

$33,000

Buy Now
Questions 51

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Cost engineers who feel completely satisfied and fulfilled by their work as part of a project team are said to have reached the ______________ stage of Maslow's hierarchy of needs.

Options:

A.

Need satisfaction

B.

Belonging needs

C.

Self-actualizations

D.

Esteem

Buy Now
Questions 52

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Profits that could not be formally recognized during a specific financial accounting period because the goods and services did not satisfy all the customer's requirements are:

Options:

A.

Marginal profits

B.

Lost profits

C.

Incurred profits

D.

Postponed profits

Buy Now
Questions 53

An effort by a prime contractor to reduce the price quoted by a vendor, by providing the bid price to other vendors in an attempt to get the other vendors to underbid the original price quoted is referred to as:

Options:

A.

Costing

B.

Cost-price analysis

C.

Bid shopping

D.

Negotiating a best and final offer

Buy Now
Questions 54

CCP Question 54

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. What is the current cost performance index (CPI)?

Options:

A.

0.96

B.

0.84

C.

1.14

D.

0.88

Buy Now
Questions 55

What do you call a person authorized to represent another (the principal) in some capacity? He/she can only act within this capacity or "scope of authority" to bind the principal.

Options:

A.

Engineer

B.

Alternate

C.

Project Manager

D.

Agent

Buy Now
Questions 56

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

CCP Question 56

The following question requires your selection of Scenario 1.4.15Q from the right side of your split screen. using the drop down menu, to reference during your response/choice of responses

What is the amount of capital recovery with salvage?

Options:

A.

$11,499.00

B.

$4,124.00

C.

$9,876.00

D.

$10,765.00

Buy Now
Exam Code: CCP
Exam Name: Certified Cost Professional (CCP) Exam
Last Update: May 19, 2026
Questions: 189

PDF + Testing Engine

$64.99   $185.69

Testing Engine

$49.99   $142.83

PDF (Q&A)

$54.99   $157.11