Black Friday Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

CDT Construction Documents Technologist Questions and Answers

Questions 4

Which of the following participants is involved in the Integrated Project Delivery (IPD) method?

Options:

A.

Authority having jurisdiction

B.

Commissioning agent

C.

Contractor

D.

Inspector

Buy Now
Questions 5

Which of the following is an example of quality assurance?

Options:

A.

Performing compaction testing

B.

Field observations

C.

Validating quantities for payment

D.

Scheduling and sequencing of the work

Buy Now
Questions 6

Which documents are commonly included as procurement documents?

Options:

A.

Project record documents

B.

Contract documents

C.

Consensus documents

D.

Bidding documents

Buy Now
Questions 7

What is the primary purpose of MasterFormat®?

Options:

A.

To create a master list of Level 3 and Level 4 section titles

B.

To organize cost estimates by major project element

C.

To establish an order of information within specification sections

D.

To provide a uniform system for the organization of information in project manuals

Buy Now
Questions 8

What does Divisions 02-49 of the construction project manual address?

Options:

A.

Procurement instructions

B.

Distinct work results areas

C.

Temporary facilities and controls

D.

Life cycle activities

Buy Now
Questions 9

Which member of the project team initiates the project, assumes the risk, controls and manages the design and construction process, and provides the funding?

Options:

A.

Contractor

B.

Designer

C.

Supplier

D.

Owner

Buy Now
Questions 10

An architect/engineer (A/E) is reviewing a claim from a contractor asking for more money and time on the project. The A/E plans to reject this claim based on documentation supplied by the contractor indicating what reason?

Options:

A.

There was active interference by the owner.

B.

There were conditions beyond the control of the contractor or owner.

C.

The A/E modified the contract documents.

D.

There is defective work needing repair.

Buy Now
Questions 11

When the specifications allow controlled substitutions, a substitution may be approved during the bidding period only if what?

Options:

A.

An addendum is issued to all the bidders

B.

The proposer of the substitution is notified in writing

C.

The architect/engineer accepts the substitution during the pre-bid meeting

D.

Specifications are revised and reissued to include the substitution

Buy Now
Questions 12

Which of the following statements is correct?

Options:

A.

Contract documents are complementary

B.

Requirement of one of the contract documents may be superseded by others

C.

Specifications take precedence over drawings

D.

The architect/engineer may require the contractor to perform at a higher level than the contract documents require

Buy Now
Questions 13

Which of the following is a component of project design team coordination during the construction documents phase?

Options:

A.

Duplication of important information by each discipline

B.

Ensuring drawing note terminology is differentiated from specification terminology

C.

Requiring the owner to hire a third-party to write the Division 01 specifications independently

D.

Quality assurance tasks shared between design and consulting teams

Buy Now
Questions 14

What is the compositional format for standardizing the presentation of specification information on a printed page in a way that is meant to be easy to read and quick to navigate?

Options:

A.

UniFormat®

B.

PPDFormat®

C.

PageFormat®

D.

SectionFormat®

Buy Now
Questions 15

In construction documents, what does the agreement refer to?

Options:

A.

The agreement between the owner and the architect/engineer

B.

The general conditions of the contract for construction

C.

The agreement between the owner and the contractor

D.

The agreement between the contractor and the subcontractor

Buy Now
Questions 16

A drawing set arranged in the following order is an example of what type of drawing organization?

Cover Sheet, Sheet Index, Life Safety, Demolition, Civil, Landscaping, Architectural, Interiors, Structural, Mechanical, Electrical, Plumbing, Fire Protection

Options:

A.

Traditional drawing set organization

B.

Uniform Drawing System

C.

AIA CAD Layer Guidelines

D.

BIM Implementation

Buy Now
Questions 17

What is MasterFormat® keyword index used for?

Options:

A.

Identifying Level 4 sections

B.

Identifying specification format

C.

Locating subject titles and numbers

D.

Specifying correct word usage

Buy Now
Questions 18

The owner's budget may not be adequate to pay for the entire project. What method is used to allow flexibility in the event that the budget is exceeded by the bids?

Options:

A.

Cash allowance

B.

Quantity allowance

C.

Unit pricing

D.

Alternates

Buy Now
Questions 19

As a project manager representing a private client, which of the following instances would best benefit from a constructability review meeting?

Options:

A.

The client is unfamiliar with this type of project.

B.

The project team consists of multiple new members.

C.

The site presents unusual challenges and constraints.

D.

The contractor is unable to commit to original schedule.

Buy Now
Questions 20

What determines the responsibilities of the participants on the project team?

Options:

A.

Size of the project

B.

Nature of the project

C.

Cost of construction

D.

Project delivery type

Buy Now
Questions 21

Which of the following elements should be included in Supplementary Conditions?

Options:

A.

Requirements for a schedule of values

B.

Claims and dispute resolution requirements

C.

Equal employment opportunity requirements

D.

Termination of the work by owner or contractor

Buy Now
Questions 22

Which of these is NOT a graphical format used to establish order and organization of construction drawings?

Options:

A.

United States National CAD Standard

B.

American Institute of Architects (AIA) CAD Layer Guidelines

C.

Construction Specifications Institute (CSI) Uniform Drawing System

D.

MasterFormat®

Buy Now
Questions 23

What does the Integrated Project Delivery (IPD) process involve?

Options:

A.

A collaborative, integrated, and productive team composed of key project participants

B.

Traditional delivery methods and team relationships for improving project performance by understanding the qualifications and attributes of team members

C.

Responsibility silos for greater efficiencies, leading to project success

D.

Segregat knowledge gathered as needed with paper-based communications to team members

Buy Now
Questions 24

Which document obligates the architect/engineer to review submittals during construction administration?

Options:

A.

AIA Document A201, General Conditions of the Contract for Construction

B.

AIA Document B101, Standard Form of Agreement Between Owner and Architect

C.

AIA Document D200, Project Checklist

D.

AIA Document G612, Owners Instructions to the Architect

Buy Now
Questions 25

During the bid period, what does the architect issue if it is necessary to modify the procurement documents?

Options:

A.

Addenda

B.

Construction change directives

C.

Change order

D.

RFI response

Buy Now
Questions 26

Which of the following is LEAST important to log when documenting the decision-making process?

Options:

A.

Date, time, and location of the meeting

B.

List of attendees and who they represent

C.

Length of time each attendee spent speaking

D.

Action items with responsibilities assigned and date to accomplish

Buy Now
Questions 27

The names of the project, owner, architect/engineer and consultants, and the general project data such as a location map are normally included in which of the following?

Options:

A.

Sheet index

B.

Cover sheet

C.

General notes

D.

Building code summary

Buy Now
Questions 28

During which stage of a facility's life cycle are operations and maintenance documents presented to the owner?

Options:

A.

After the authorities having jurisdiction issues a permit

B.

Closeout phase

C.

Preconstruction phase

D.

Construction phase

Buy Now
Questions 29

In the MasterFormat® specification system, which subgroup contains requirements of MEP, fire protection, and telecom systems?

Options:

A.

Site and Infrastructure Subgroup (Divisions 30–39)

B.

Facility Services Subgroup (Divisions 20–29)

C.

Facility Construction Subgroup (Divisions 02–19)

D.

Part 2 – Products

Buy Now
Questions 30

Which document directly modifies the requirements of the general conditions?

Options:

A.

Division 01, General Requirements

B.

Supplementary Conditions

C.

Agreement

D.

Instructions to Bidders

Buy Now
Questions 31

During design, in a design-build delivery method, what is the design-builder responsible for delivering to the owner?

Options:

A.

Submittals

B.

Record documents

C.

Geotechnical reports

D.

Construction documents

Buy Now
Questions 32

When is decommissioning required for a facility?

Options:

A.

When the entire building is going to be demolished

B.

When the facility is no longer needed for operations

C.

When the facility will not be used again in the future

D.

When the building changes owners

Buy Now
Questions 33

Cost classification, data organization, and specifications use which written formats?

Options:

A.

OmniClass and UniFormat

B.

UniFormat and MasterFormat

C.

OmniClass and MasterFormat

D.

SectionFormat® and MasterFormat

Buy Now
Questions 34

Under SectionFormat®, where would the Article "Manufacturers" be found?

Options:

A.

Either Part 1 or Part 2

B.

Part 1 only

C.

Part 2 only

D.

Part 3 only

Buy Now
Questions 35

Which of the following is a format that standardizes the way text is arranged in specification pages so that it is best suited for easy reading and rapid reference?

Options:

A.

SectionFormat®

B.

PageFormat

C.

MasterFormat®

D.

UniFormat®

Buy Now
Questions 36

You are working on a project that is subject to regulatory reviews both at the city and at the state level. Both agencies have acknowledged receiving the construction documents. This project has already been awarded to a general contractor, and you are representing the owner who wants to start construction immediately. How would you advise the owner?

Options:

A.

Construction may begin immediately as long as a safety manager is present, and the contractor avoids all excavation work until after the permits are issued.

B.

Since the state approval is more critical than the city approval, construction may proceed immediately after the state permits are issued.

C.

Since the city approval is more critical than the state approval, construction may proceed immediately after the city permits are issued.

D.

Construction may begin only after both city and state permits have been issued.

Buy Now
Exam Code: CDT
Exam Name: Construction Documents Technologist
Last Update: Nov 21, 2025
Questions: 120

PDF + Testing Engine

$63.52  $181.49

Testing Engine

$50.57  $144.49
buy now CDT testing engine

PDF (Q&A)

$43.57  $124.49
buy now CDT pdf