Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

CDT Construction Documents Technologist Questions and Answers

Questions 4

Which of the following is NOT a method of specifying?

Options:

A.

Perspective

B.

Proprietary

C.

Performance

D.

Reference standard

Buy Now
Questions 5

Where are the limits of the work of each alternate defined?

Options:

A.

Agreement

B.

Bid Form

C.

Division 01

D.

Sections in Divisions 02–49

Buy Now
Questions 6

An architect/engineer (A/E) is reviewing a claim from a contractor asking for more money and time on the project. The A/E plans to reject this claim based on documentation supplied by the contractor indicating what reason?

Options:

A.

There was active interference by the owner.

B.

There were conditions beyond the control of the contractor or owner.

C.

The A/E modified the contract documents.

D.

There is defective work needing repair.

Buy Now
Questions 7

What is a fundamental principle required to provide fairness in a competitive bidding process?

Options:

A.

Bid securities provide protection to all bidders for unfair practices of others.

B.

The bid shopping process provides the most beneficial pricing to the owner.

C.

All bids are prepared based on identical conditions, information, and time constraints.

D.

A minimum of three bids are required to assure sufficient competition.

Buy Now
Questions 8

Under a single prime contract, shop drawings should be routed to the architect/engineer from whom?

Options:

A.

Contractor

B.

Material supplier

C.

Owner

D.

Subcontractor

Buy Now
Questions 9

Which of the following is an example of preconstruction submittals?

Options:

A.

Product data

B.

Shop drawings

C.

Schedule of values

D.

Warranty documentations

Buy Now
Questions 10

When is the owner entitled to stop the work?

Options:

A.

If the architect/engineer fails to represent owner properly

B.

If the contractor fails to correct work that is not compliant with the contract documents

C.

If the contractor is presumed to be bankrupt

D.

If there is a safety problem on the site

Buy Now
Questions 11

What is the term used to describe the time it takes to procure an item on site?

Options:

A.

Estimated time of arrival

B.

Procurement time

C.

Lead time

D.

Manufacturing time

Buy Now
Questions 12

When does a project reach substantial completion?

Options:

A.

When the project is sufficiently complete to allow its intended use

B.

When the project receives final inspections from the authorities having jurisdiction

C.

When the contractor ' s final application for payment is approved

D.

When all of the close-out documents have been reviewed and approved

Buy Now
Questions 13

Which of the following statements is correct?

Options:

A.

Contract documents are complementary

B.

Requirement of one of the contract documents may be superseded by others

C.

Specifications take precedence over drawings

D.

The architect/engineer may require the contractor to perform at a higher level than the contract documents require

Buy Now
Questions 14

Which of the following is a component of the contract documents ?

Options:

A.

Procurement requirements

B.

Resource drawings

C.

Shop drawings

D.

Addenda

Buy Now
Questions 15

An electrical engineer completes a set of electrical drawings and specifications for a project, except for the site electrical work which is indicated on the civil drawings. Which of the following is the intent of the contract documents?

Options:

A.

The civil contractor is to place the concrete bases and the electrical contractor is to install the site lighting.

B.

The civil contractor is to place the concrete bases and the site lighting, with the electrical contractor making the final connections.

C.

The general contractor needs to coordinate the work and verify that the electrical subcontractor bids the site electrical.

D.

The electrical engineer does not need to control how the work is to be assigned to subcontractors.

Buy Now
Questions 16

What four considerations are included in site selection programming?

Options:

A.

Use, space, funds, date

B.

Function, form, economy, time

C.

Purpose, shape, cost, schedule

D.

Goal, condition, budget, calendar

Buy Now
Questions 17

How long after bid opening is a bidder required to honor their bid price for a project?

Options:

A.

It should be no less than the time period acknowledged on the bid form.

B.

The time period is thirty days for a private project and indefinitely for a public project.

C.

The time period should conform to requirements set by the Associated General Contractors of America.

D.

The time period as established by the contract for construction.

Buy Now
Questions 18

To avoid miscommunication problems during construction, which best practice should the design professional use?

Options:

A.

Develop a good working relationship for verbally addressing problems as they arise

B.

Mark emails and electronic communications as " Urgent! " to ensure they are read right away

C.

Distribute meeting minutes to all attendees and concerned parties documenting key decisions and action items resulting from the meeting

D.

Leave detailed voicemail messages describing everything that needs to be done so there is a record of the direction

Buy Now
Questions 19

According to standard general conditions, which of the following is true about shop drawings?

Options:

A.

They are contract documents.

B.

They illustrate some portion of the work.

C.

They are reviewed only by the architect/engineer.

D.

They include performance charts, instructions, and brochures.

Buy Now
Questions 20

Which of the following is an example of quality assurance?

Options:

A.

Performing compaction testing

B.

Field observations

C.

Validating quantities for payment

D.

Scheduling and sequencing of the work

Buy Now
Questions 21

Where should the contractor maintain record documents?

Options:

A.

Contractor ' s office

B.

Contractor ' s office with a copy sent to the owner

C.

Owner ' s office

D.

The jobsite

Buy Now
Questions 22

Which member of the project team initiates the project, assumes the risk, controls and manages the design and construction process, and provides the funding?

Options:

A.

Contractor

B.

Designer

C.

Supplier

D.

Owner

Buy Now
Questions 23

The emphasis shifts from overall relationships and functions to more technical issues during which design phase?

Options:

A.

Preliminary design

B.

Schematic design

C.

Design development

D.

Construction documents

Buy Now
Questions 24

When developing an operation and maintenance (O & M) budget for a facility, what should form the basis for budget decisions?

Options:

A.

The architect/engineer’s projected operating costs

B.

The construction manager’s life cycle analysis

C.

The estimator’s preliminary project description

D.

The facility manager’s historical record of actual costs

Buy Now
Questions 25

When a public works project utilizes design-bid-build, which option would NOT minimize the risk of bid shopping?

Options:

A.

The architect/engineer/owner team can consider bid listing and bid depository provisions.

B.

Require bidders to provide a list of their intended subcontractors along with their bid.

C.

The subcontractor can withhold their prices from the bidder until the final moments before the deadline.

D.

The bidder can ask the subcontractor to reevaluate their prices to find a lower price after the subcontractor has submitted their price.

Buy Now
Questions 26

The general principle to which architects and engineers have a duty to clients and society at large to practice is defined as " taking the same course of action as another reasonable and prudent architect or engineer in the same geographic area would have taken under the same circumstances " is known by what term?

Options:

A.

Professional standard of care

B.

Due diligence

C.

Performance based requirement

D.

Spearin doctrine

Buy Now
Questions 27

Who is responsible for accepting and inspecting for damage of the owner-furnished products delivered to the project site?

Options:

A.

Contractor

B.

Installer

C.

Owner

D.

Subcontractor

Buy Now
Questions 28

In construction documents, what does the agreement refer to?

Options:

A.

The agreement between the owner and the architect/engineer

B.

The general conditions of the contract for construction

C.

The agreement between the owner and the contractor

D.

The agreement between the contractor and the subcontractor

Buy Now
Questions 29

When innovative or unusual design techniques are proposed, it is advised to have what type of review?

Options:

A.

Sustainability

B.

Budget

C.

Constructability

D.

Design

Buy Now
Questions 30

Who has the right to stop the work if hazardous materials are encountered during the construction?

Options:

A.

Architect/engineer

B.

Contractor

C.

Stakeholders

D.

Facility manager

Buy Now
Questions 31

Which term or word is appropriate to use in specification text?

Options:

A.

Any

B.

As per

C.

As required

D.

Work

Buy Now
Questions 32

Which of these is NOT a graphical format used to establish order and organization of construction drawings?

Options:

A.

United States National CAD Standard

B.

American Institute of Architects (AIA) CAD Layer Guidelines

C.

Construction Specifications Institute (CSI) Uniform Drawing System

D.

MasterFormat®

Buy Now
Questions 33

Lump sum, unit price, and cost-plus-fee are examples of what?

Options:

A.

Delivery method

B.

Bonding system

C.

Basis of payment

D.

Cost estimate

Buy Now
Questions 34

What activity helps the owner assess the viability of a project, evaluate financial resources, and understand the project ' s potential impact on the community?

Options:

A.

Schematic programming

B.

Site selection

C.

Due diligence investigation

D.

Master planning

Buy Now
Questions 35

In the AIA A201 General Conditions of the Contract for Construction, whom is responsible for property insurance for a project?

Options:

A.

Surety, on contractor ' s behalf.

B.

Owner, unless assigned to contractor.

C.

Owner and contractor, jointly.

D.

Contractor, unless assigned to owner.

Buy Now
Questions 36

Where can you typically find requirements for temporary toilet facilities?

Options:

A.

Supplementary Conditions

B.

Division 22 – Plumbing

C.

The Owner–Contractor Agreement

D.

Division 01 – General Requirements

Buy Now
Exam Code: CDT
Exam Name: Construction Documents Technologist
Last Update: May 21, 2026
Questions: 120

PDF + Testing Engine

$64.99   $185.69

Testing Engine

$49.99   $142.83

PDF (Q&A)

$54.99   $157.11