Which of the following participants is involved in the Integrated Project Delivery (IPD) method?
Authority having jurisdiction
Commissioning agent
Contractor
Inspector
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
Integrated Project Delivery (IPD), as described in CSI’s project delivery materials, is a collaborative project delivery method that:
Involves key project participants early in the project,
Uses shared risk and reward, and
Promotes integration of people, systems, business structures, and practices into a process that optimizes project results.
CSI’s discussion of IPD identifies the core IPD team as typically including:
The Owner
The Architect/Engineer (Design Professional)
The Contractor (often a general contractor or construction manager at risk)
In IPD, the contractor is deliberately brought into the project early, often during conceptual or schematic design, to:
Provide constructability input
Contribute cost estimating and scheduling
Help optimize means and methods and coordinate with major trades
Among the choices given, the participant that is clearly recognized as a primary IPD participant in CSI-oriented explanation of IPD is the:
C. Contractor
Why the other options are not the best answer:
A. Authority having jurisdiction (AHJ)The AHJ (e.g., building department, fire marshal) is always involved in permitting and inspections, regardless of delivery method. However, they are not part of the project’s contractual IPD team, nor do they share in IPD contractual risk/reward structures.
B. Commissioning agentA commissioning agent (or authority) may participate in IPD projects, but is not a mandatory or defining core party. Commissioning can be part of many delivery methods (Design-Bid-Build, CM at Risk, Design-Build, IPD). CSI’s general description of IPD focuses on owner–designer–contractor integration.
D. InspectorInspectors (code inspectors, special inspectors) are similar to the AHJ functions—important to the project but external to the project’s contractual structure and not specific to IPD. They serve regulatory and quality verification roles across all delivery methods.
Thus, in the context of CSI’s explanation of Integrated Project Delivery, the clearly correct answer is Option C – Contractor.
Key CSI-Related References (titles only):
CSI Project Delivery Practice Guide – chapters on Project Delivery Methods and Integrated Project Delivery.
CSI CDT Study Materials – comparisons of Design-Bid-Build, CM at Risk, Design-Build, and IPD, including team composition.
CSI presentations and educational modules on collaborative and integrated delivery methods.
Which of the following is an example of quality assurance?
Performing compaction testing
Field observations
Validating quantities for payment
Scheduling and sequencing of the work
In CSI / CDT usage, quality assurance (QA) and quality control (QC) are distinct concepts:
Quality Assurance (QA) focuses on planning, processes, and preventive actions put in place before and during the work to help ensure the required quality will be achieved. It is about systems and procedures.
Quality Control (QC) focuses on inspection, testing, and verification to determine whether the constructed work conforms to the requirements of the Contract Documents.
Typical examples:
QA examples (process-oriented):
Developing and following a project-specific quality plan.
Coordinating scheduling and sequencing of the work so trades do not interfere with one another and work is done under appropriate conditions.
Prequalification of contractors, subcontractors, and testing agencies.
Establishing and enforcing submittal procedures and preinstallation meetings.
QC examples (inspection/testing):
Field testing (e.g., concrete cylinder tests, soil compaction tests).
Visual inspection of installed work.
Checking that installed products match submittals and specifications.
Looking at the options:
A. Performing compaction testing – This is a field test used to verify densities and is clearly quality control, not QA.
B. Field observations – These are performed by the A/E or others to observe and verify that work appears to be in general conformance; this is quality control.
C. Validating quantities for payment – This is a contract administration / cost control activity, not primarily a quality activity.
D. Scheduling and sequencing of the work – This is planning and coordination done in advance so the project can proceed efficiently, correctly, and without damaging completed work. Because it is a procedure-based, preventive activity, CSI places this type of planning under quality assurance.
Therefore, the example of quality assurance is “Scheduling and sequencing of the work” (Option D).
Relevant CSI / CDT References (titles only, no links):
CSI Project Delivery Practice Guide – sections on “Quality in Project Delivery” and distinctions between QA and QC.
CSI Construction Specifications Practice Guide – discussions of quality requirements, testing, and inspection.
CDT Body of Knowledge – domain on “Construction Phase: Quality Assurance and Quality Control.”
Which documents are commonly included as procurement documents?
Project record documents
Contract documents
Consensus documents
Bidding documents
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
CSI uses the term “Procurement Documents” to describe the documents used to solicit and obtain offers (bids or proposals) from prospective contractors. In CSI and CDT terminology, these are more commonly referred to in everyday practice as “Bidding Documents.”
Per CSI’s Project Delivery Practice Guide:
Procurement (bidding) documents usually include:
Solicitation / invitation to bid or request for proposals,
Instructions to bidders,
Bid forms,
Procurement requirements, and
Often copies of the proposed Contract Documents (conditions, drawings, specifications) for information and pricing.
When CSI exam and study materials ask what is “commonly included as procurement documents,” they treat “bidding documents” as the proper term among choices like these. So the best answer is:
D. Bidding documents
Why the other options are not correct by themselves:
A. Project record documents – These are post-construction documents (record drawings, record specifications, record submittals) used for operations and maintenance, not for procurement.
B. Contract documents – While proposed contract documents are often included within the procurement package for pricing and review, the broader category name for the documents used in procurement is still “bidding (procurement) documents.”
C. Consensus documents – This refers to standard-form agreements produced by organizations (e.g., consensus-documents families), not the general CSI term for the set of documents used in the procurement phase.
Relevant CSI references (paraphrased):
CSI Project Delivery Practice Guide – chapters on Procurement Phase and “Procurement Documents (Bidding Documents).”
CSI CDT Study Materials – topics on document families used in procurement and contracting.
What is the primary purpose of MasterFormat®?
To create a master list of Level 3 and Level 4 section titles
To organize cost estimates by major project element
To establish an order of information within specification sections
To provide a uniform system for the organization of information in project manuals
CSI’s MasterFormat® is the standard for organizing work results–based information for building projects. In CDT study materials and CSI practice guides, its primary purpose is described as providing a uniform, consistent structure for organizing and retrieving information in:
Project manuals (specifications)
Related documents such as cost information, product literature, and some facility management data
MasterFormat does this by dividing the work into Divisions and Sections with standardized titles and numbers so that everyone (owner, A/E, contractor, suppliers) can find information in the same place across different projects. That is exactly what Option D states.
Why the others are incorrect:
A. Master list of Level 3 and Level 4 section titles – MasterFormat includes level 3 and level 4 titles, but listing those is a means to the end, not the primary purpose.
B. Organize cost estimates by major project element – That is closer to the stated use of UniFormat®, which organizes by systems and assemblies rather than work results.
C. Establish order of information within specification sections – That is the role of SectionFormat™ and PageFormat™, not MasterFormat.
Relevant CSI references (no links):
CSI MasterFormat® Introduction and User Guide – purpose and scope statements.
CSI Construction Specifications Practice Guide – chapter on organizing specifications with MasterFormat, SectionFormat, and PageFormat.
CSI CDT Study Materials – section on “Organizing Project Manuals.”
What does Divisions 02-49 of the construction project manual address?
Procurement instructions
Distinct work results areas
Temporary facilities and controls
Life cycle activities
In CSI’s MasterFormat® system, the project manual’s specifications are organized into Divisions 00–49:
Division 00 – Procurement and Contracting Requirements (instructions to bidders, bid forms, owner–contractor agreement, etc.)
Division 01 – General Requirements (administrative and procedural requirements applicable to the whole project, including items like temporary facilities and controls, submittals, project meetings, etc.)
Divisions 02–49 – Technical Specifications
CSI defines Divisions 02–49 as the technical divisions, each of which is organized around a specific work results area (sitework, concrete, masonry, metals, finishes, mechanical, electrical, etc.). Within those divisions, each specification section describes the materials, products, and execution requirements for that particular work result.
Therefore:
A. Procurement instructions – belong in Division 00, not Divisions 02–49.
C. Temporary facilities and controls – are addressed under Division 01 – General Requirements, not Divisions 02–49.
D. Life cycle activities – are not how CSI defines the scope of Divisions 02–49.
The only accurate description of Divisions 02–49 is that they address distinct work results areas, which is Option B.
CSI references (by name only, no links):
CSI MasterFormat® – Numbers and Titles (Introduction and Use)
CSI Construction Specifications Practice Guide, chapters explaining organization of the project manual into Divisions 00–49
Which member of the project team initiates the project, assumes the risk, controls and manages the design and construction process, and provides the funding?
Contractor
Designer
Supplier
Owner
CSI’s description of project roles is very clear about the owner’s role in project delivery:
The owner is the party that:
Identifies the need or opportunity and therefore initiates the project.
Provides the funding for design and construction.
Retains the design and construction teams and selects the project delivery method.
Ultimately assumes the primary financial and project risk, because the owner is the one investing in and depending on the completed facility.
In contrast:
The designer (architect/engineer) is responsible for planning and design, preparing construction documents, and administering the construction contract on the owner’s behalf, but does not typically initiate the project or provide funding.
The contractor is responsible for constructing the project in accordance with the contract documents; the contractor bears construction execution risk, but not the basic project-initiative and funding role.
Suppliers provide materials/equipment and have no overarching control over the project delivery process.
The question lists all of the characteristics that CSI attributes to the owner:
“initiates the project, assumes the risk, controls and manages the design and construction process, and provides the funding.”
Thus, the correct answer is Option D – Owner.
CSI references (by name only, no links):
CSI Project Delivery Practice Guide – “Participants in Project Delivery” (owner, designer, constructor, suppliers)
CDT Body of Knowledge – descriptions of owner responsibilities and risk
An architect/engineer (A/E) is reviewing a claim from a contractor asking for more money and time on the project. The A/E plans to reject this claim based on documentation supplied by the contractor indicating what reason?
There was active interference by the owner.
There were conditions beyond the control of the contractor or owner.
The A/E modified the contract documents.
There is defective work needing repair.
Under the typical CSI-aligned project delivery framework, additional time and money are generally justified when:
The owner (or A/E as owner’s agent) changes the work or otherwise causes delay (e.g., active interference, late decisions, design changes).
There are unforeseen conditions beyond the control of both owner and contractor, where the contract documents anticipated “normal” conditions instead.
Other compensable events defined in the Conditions of the Contract occur (e.g., certain force majeure events, if provided for).
However, the contractor is responsible for correcting defective or nonconforming work at no increase in contract sum or time (except where the defect is caused by others). CSI-based guidance on construction phase services and contract administration explains that:
Defective work (work not in accordance with the contract documents) must be removed, replaced, or corrected by the contractor at the contractor’s expense.
Any extra time and cost arising from correcting such defective work is not a valid basis for a change order or a claim for increased compensation or time extension.
If the contractor’s own documentation shows that the extra cost and time are due to defective work needing repair, the A/E has a clear basis—consistent with the Conditions of the Contract—to reject the claim. That aligns directly with Option D.
Why the other options do not support rejecting the claim:
A. Active interference by the owner – Owner-caused interference is typically a valid ground for a time and possibly cost adjustment, not grounds for rejection.
B. Conditions beyond the control of the contractor or owner – Unforeseen conditions are exactly the type of situation that may justify a claim, depending on the contract language.
C. The A/E modified the contract documents – A/E-issued changes (such as change orders or certain clarifications) often result in compensable changes if they add work or cause delay.
CSI-aligned references (no URLs):
CSI Project Delivery Practice Guide – Construction Phase and Claims/Changes discussions.
CSI Construction Specifications Practice Guide – responsibilities for defective work and changes.
CSI CDT Body of Knowledge – construction phase administration and evaluation of claims.
When the specifications allow controlled substitutions, a substitution may be approved during the bidding period only if what?
An addendum is issued to all the bidders
The proposer of the substitution is notified in writing
The architect/engineer accepts the substitution during the pre-bid meeting
Specifications are revised and reissued to include the substitution
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
CSI emphasizes fairness, clarity, and equal information for all bidders. When controlled substitutions are permitted during bidding, the procedure typically described in Division 01 and the Instructions to Bidders is:
A bidder or manufacturer may propose a substitution for a specified product within a defined time before bid date.
The architect/engineer reviews the proposed substitution and may accept or reject it.
If the substitution is accepted, it must be communicated to all prospective bidders in a formal way so that every bidder is pricing the same requirements.
The correct formal mechanism during the bid period for changing procurement documents is an addendum. Therefore:
A substitution may be approved during bidding only if its approval is issued by an addendum to all bidders.
This maintains a level playing field and prevents one bidder from having a private advantage or a different scope basis than others.
Why the other options are not sufficient or correct alone:
B. The proposer of the substitution is notified in writingNotifying only the proposer does not put all bidders on the same basis. CSI stresses that changes affecting price, scope, or products must be distributed to all bidders via addenda during the procurement phase.
C. The architect/engineer accepts the substitution during the pre-bid meetingEven if verbally accepted in a pre-bid meeting, it must be officially documented by an addendum. Pre-bid meeting minutes alone are not a proper modification of the procurement documents unless they are explicitly issued as part of an addendum.
D. Specifications are revised and reissued to include the substitutionCompletely revising and reissuing specifications is not the usual or efficient method during a normal bid period. Instead, CSI practice is to use addenda to modify the existing specifications. On larger changes, an addendum may include revised pages, but the key formal instrument remains the addendum.
Therefore, in CSI-aligned bidding procedures, a substitution can be approved during bidding only when it is issued to all bidders as an addendum, making Option A the correct answer.
Key CSI-Related References (titles only, no links):
CSI Project Delivery Practice Guide – procurement process, bidder communications, and substitutions.
CSI Construction Specifications Practice Guide – Division 01 sections on Substitution Procedures and Instructions to Bidders regarding substitutions.
CSI CDT Study Materials – controlled substitutions during bidding and the role of addenda.
Which of the following statements is correct?
Contract documents are complementary
Requirement of one of the contract documents may be superseded by others
Specifications take precedence over drawings
The architect/engineer may require the contractor to perform at a higher level than the contract documents require
In CSI-based project delivery and typical general conditions (such as those coordinated with CSI practices), contract documents are described as “complementary”. This means the drawings, specifications, and other contract documents are intended to be read together as a unified whole, and requirements shown or stated in one document are binding as if they appeared in all.
CSI’s CDT body of knowledge and practice guides explain that:
The project manual (including the specifications and conditions of the contract) and the drawings together form the contract documents used to describe the work.
These documents are interrelated and mutually supportive; no single document is intended to stand alone.
The concept of “complementary” means that if a requirement is found in any contract document, it applies, unless it has been consciously modified by a change in the contract (e.g., via addenda, change order, or supplementary conditions).
Therefore, statement A. Contract documents are complementary reflects the core CSI teaching on how contract documents function together.
Why the other options are incorrect (from a CSI/CDT perspective):
B. Requirement of one of the contract documents may be superseded by othersCSI teaches that the contract documents should be coordinated, not competing. While modifications can be made through proper instruments (addenda, change orders, supplementary conditions), the baseline rule is not that any document “supersedes” another by default. Instead, the emphasis is on coordination and consistency across the entire set of documents. Precedence is only established where explicitly written into the conditions or supplementary conditions, and even then it is a last resort, not a standard operating principle.
C. Specifications take precedence over drawingsCSI specifically cautions against blanket “order of precedence” clauses (such as “specifications govern over drawings”), because they encourage sloppy coordination and can lead to disputes rather than preventing them. CSI promotes the idea that both drawings and specifications must be coordinated so they do not conflict. While some owners or agencies may include precedence clauses in their own conditions, this is not a CSI best practice and is not the general rule taught in CDT-preparation materials.
D. The architect/engineer may require the contractor to perform at a higher level than the contract documents requireUnder standard contract principles presented in CSI’s practice guides, the architect/engineer (A/E) cannot unilaterally change the contractor’s obligations beyond what the contract documents require, except through properly authorized changes (e.g., change orders) that include appropriate adjustments to cost and/or time if applicable. The A/E administers the contract and interprets the documents but cannot simply demand higher performance than what the contract documents specify without formal change mechanisms.
In summary, the CSI-aligned view is that contract documents are complementary and intended to be interpreted together, which is best represented by Option A.
Which of the following is a component of project design team coordination during the construction documents phase?
Duplication of important information by each discipline
Ensuring drawing note terminology is differentiated from specification terminology
Requiring the owner to hire a third-party to write the Division 01 specifications independently
Quality assurance tasks shared between design and consulting teams
During the construction documents phase, CSI’s guidance emphasizes that coordination between the architect/engineer (A/E) and the various consulting disciplines (structural, mechanical, electrical, etc.) is essential to produce consistent, coordinated, and complete contract documents (drawings, specifications, and project manual). Part of that coordination is a shared quality assurance (QA) effort among the design team members.
In CSI’s practice guides and CDT body of knowledge, the following principles are stressed (paraphrased to respect copyright):
The prime design professional is responsible for overall coordination of the construction documents, but each consultant is responsible for the technical accuracy and coordination of their own portions.
Coordination includes review of cross-references, matching terminology, alignment of requirements between drawings and specifications, and resolving conflicts before bid/issue.
Quality assurance during this phase is not done in isolation; it is a team activity. Consultants and the lead design firm review each other’s work where it interfaces (e.g., architectural and mechanical coordination of ceilings and diffusers; structural and architectural coordination of openings, etc.).
Therefore, “Quality assurance tasks shared between design and consulting teams” (Option D) correctly describes a standard component of project design team coordination during the construction documents phase.
Why the other options are incorrect:
A. Duplication of important information by each disciplineCSI stresses “say it once, in the right place” as a fundamental principle. Information should not be unnecessarily duplicated because duplication increases the risk of conflict and inconsistency (for example, a requirement shown in both drawings and multiple spec sections but updated in only one location). Coordination aims to avoid duplication, not to promote it.
B. Ensuring drawing note terminology is differentiated from specification terminologyCSI emphasizes consistent terminology across drawings, specifications, and other documents. The same items (e.g., “gypsum board,” “reinforcing steel,” “membrane roofing”) should be described using the same terms in both drawings and specifications to reduce ambiguity. Coordination meetings often include checking that terminology is aligned, not intentionally differentiated.
C. Requiring the owner to hire a third-party to write the Division 01 specifications independentlyDivision 01 – General Requirements – is typically prepared or controlled by the lead design professional or specifier, in coordination with the owner. CSI materials do not identify it as a standard or required coordination practice for the owner to hire an independent third party to write Division 01 separately from the design team. That may occur on some projects, but it is not a defined component of team coordination in CSI’s CDT framework.
In summary, CSI-based construction documentation practice defines coordination during the construction documents phase as a shared responsibility among the architect/engineer and all consultants, including joint quality assurance reviews, consistency checks, and cross-discipline coordination. This aligns directly with Option D.
Key CSI References (no links):
CSI Project Delivery Practice Guide – chapters on Design Phase and Construction Documents coordination.
CSI Construction Specifications Practice Guide – sections on coordination between drawings and specifications and the role of Division 01.
CSI CDT Body of Knowledge – topics on roles and responsibilities of the design team and coordination of construction documents.
What is the compositional format for standardizing the presentation of specification information on a printed page in a way that is meant to be easy to read and quick to navigate?
UniFormat®
PPDFormat®
PageFormat®
SectionFormat®
Comprehensive and Detailed Explanation (CSI-aligned, paraphrased)
CSI has several coordinated formats, each with a specific purpose:
UniFormat® – organizes information by building systems and assemblies (e.g., substructure, superstructure, interiors), used for early design and cost models.
PPDFormat® (Preliminary Project Description Format) – organizes preliminary descriptions of the project using a system-based structure for early-phase documentation.
SectionFormat® – organizes the content of each specification section into three parts: Part 1 – General, Part 2 – Products, Part 3 – Execution.
PageFormat® – defines the layout and composition of information on the printed page of specifications, including margins, headers/footers, article arrangement, and typography conventions so that the document is easy to read and navigate quickly.
The question specifically asks for:
“the compositional format for standardizing the presentation of specification information on a printed page… easy to read and quick to navigate.”
That is exactly what PageFormat® is for, so the correct answer is:
C. PageFormat®
Why the others are incorrect in this context:
A. UniFormat® – classification system for systems / assemblies; it does not prescribe how the text is positioned on a printed page.
B. PPDFormat® – used for structuring preliminary project descriptions, not for page layout.
D. SectionFormat® – structures the logical content within a spec section (Part 1–3), but does not itself define margins, columns, headers, or the graphic layout of the printed page—that’s PageFormat’s role.
Key CSI-Related References (titles only):
CSI Construction Specifications Practice Guide – chapters on SectionFormat® and PageFormat®.
CSI MasterFormat / UniFormat / PPDFormat publications – introductions describing each standard’s purpose.
CSI CDT Study Materials – overview of CSI formats and how they interact.
In construction documents, what does the agreement refer to?
The agreement between the owner and the architect/engineer
The general conditions of the contract for construction
The agreement between the owner and the contractor
The agreement between the contractor and the subcontractor
Within CSI’s framework for contract documents, the term “Agreement” (capitalized) has a specific meaning. It refers to the formal written contract for construction between the Owner and the Contractor.
CSI describes the typical structure of the contract documents as including:
The Agreement between Owner and Contractor (such as AIA A101 or similar),
The Conditions of the Contract (General and Supplementary Conditions),
Drawings, Specifications, and Addenda,
And other documents listed in the Agreement.
The Agreement sets out key commercial terms (contract sum, contract time, identification of the work, list of contract documents, progress payments, etc.) and binds the owner and contractor to the Conditions of the Contract and the remainder of the documents.
Why the other options are not correct:
A. Agreement between the owner and the architect/engineer – This is usually a separate professional services agreement (often titled Owner–Architect Agreement or similar) and is not what CSI and AIA mean by “the Agreement” within the construction contract set.
B. The general conditions of the contract for construction – The General Conditions are a separate document; they become part of the contract when they are incorporated by reference in the Agreement, but they are not themselves “the Agreement.”
D. Agreement between the contractor and the subcontractor – This is a separate subcontract document, not part of the owner–contractor contract set defined in the project manual.
CSI’s practice material on contract formation and document relationships consistently identifies “the Agreement” as the contract between the Owner and the Contractor, hence Option C is correct.
A drawing set arranged in the following order is an example of what type of drawing organization?
Cover Sheet, Sheet Index, Life Safety, Demolition, Civil, Landscaping, Architectural, Interiors, Structural, Mechanical, Electrical, Plumbing, Fire Protection
Traditional drawing set organization
Uniform Drawing System
AIA CAD Layer Guidelines
BIM Implementation
CSI, together with other organizations, developed the Uniform Drawing System (UDS) as part of the National CAD Standard. The UDS provides:
Standard sheet identification and discipline designations
A recommended order for drawing disciplines within a set of contract documents
Consistent organization to help all project participants find information efficiently
The UDS discipline order groups drawings by discipline in a typical sequence, for example:
General (G) – often includes Cover Sheet, Sheet Index, Life Safety
Civil (C)
Landscape (L)
Architectural (A)
Interiors (I)
Structural (S)
Mechanical (M)
Electrical (E)
Plumbing (P)
Fire Protection (FP)(and additional disciplines as needed)
The order given in the question:
Cover Sheet, Sheet Index, Life Safety, Demolition, Civil, Landscaping, Architectural, Interiors, Structural, Mechanical, Electrical, Plumbing, Fire Protection
matches the intent of the Uniform Drawing System discipline grouping and ordering:
The initial items (Cover Sheet, Sheet Index, Life Safety, Demolition) fit within the General / Architectural front sections.
Then the disciplines follow in a sequence consistent with UDS recommendations: Civil → Landscape → Architectural → Interiors → Structural → Mechanical → Electrical → Plumbing → Fire Protection.
Therefore, this is an example of UDS-based drawing set organization, which corresponds to Option B – Uniform Drawing System.
Why the other options are incorrect:
A. Traditional drawing set organization“Traditional” is vague and not a CSI-standardized system. The sequence in the question clearly follows a recognized CSI / NCS discipline order, not just an informal tradition.
C. AIA CAD Layer GuidelinesThe AIA CAD Layer Guidelines address layer naming conventions in CAD files, not the order of sheets in a printed / published drawing set.
D. BIM ImplementationBIM is about digital building information models and processes. It does not by itself define a sheet order; the sheet organization is still typically based on CSI / UDS discipline sequence, even on BIM projects.
Relevant CSI / CDT References (titles only, no links):
CSI / National CAD Standard – Uniform Drawing System (UDS) documentation on discipline designators and sheet ordering.
CSI Project Delivery Practice Guide – discussions of drawing organization and coordination with specifications.
mentation
Answer: A
What is MasterFormat® keyword index used for?
Identifying Level 4 sections
Identifying specification format
Locating subject titles and numbers
Specifying correct word usage
The MasterFormat® system, maintained by CSI and CSC, organizes work results into a numbered and titled hierarchical structure (Divisions, Level 2, Level 3, Level 4). Included with MasterFormat is a keyword index.
CSI describes the MasterFormat keyword index as a tool that:
Lists common keywords and subject terms used in construction (e.g., “gypsum board,” “elevators,” “unit masonry”).
Cross-references each keyword to the appropriate MasterFormat section number and title.
Helps specifiers and project team members find where a product, system, or topic belongs when writing or organizing sections.
Therefore, the keyword index is used for:
Locating subject titles and numbers – Option C.
Why the other options are incorrect:
A. Identifying Level 4 sectionsWhile the keyword index may point to Level 4 numbers, its purpose is not specifically to “identify Level 4 sections” but to locate the correct section number and title (at any level) based on subject words.
B. Identifying specification formatSpecification format (such as SectionFormat and PageFormat) is addressed in separate CSI standards, not by the MasterFormat keyword index.
D. Specifying correct word usageThe keyword index is not a language or style guide; it does not prescribe grammar or “correct word usage” in that sense. It is an indexing and locating tool for section numbers and titles.
Relevant CSI-aligned references (no URLs):
CSI / CSC MasterFormat® publication – introduction and explanation of keyword index function.
CSI Construction Specifications Practice Guide – discussion of using MasterFormat and its indexes to organize specifications.
CSI CDT Study materials – overview of MasterFormat and how to use the keyword index to locate topics.
The owner's budget may not be adequate to pay for the entire project. What method is used to allow flexibility in the event that the budget is exceeded by the bids?
Cash allowance
Quantity allowance
Unit pricing
Alternates
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
CSI describes several techniques in the procurement documents to manage cost uncertainty. When the owner is concerned that the project may exceed the budget when bids are received, the most common tool to allow scope flexibility is the use of alternates.
Alternates (often called “bid alternates”):
Are defined variations in the work (additions or deletions) that bidders price separately from the base bid.
Can be additive (additional scope that can be accepted if the budget allows) or deductive (scope that can be removed to reduce cost if needed).
Give the owner the ability, after seeing the base bids, to accept or reject alternates to bring the project within the available budget without redesigning the entire project.
This fits the scenario in the question exactly: the owner anticipates that the budget may be tight and wants a mechanism to adjust the final contract amount if bids come in high.
Why the other options are not the primary CSI method for this budget-flexibility issue:
A. Cash allowanceAn allowance is a set amount included in the contract sum to cover a defined but not fully specified portion of the work (e.g., artwork, specialty items). It helps manage scope uncertainty, but it doesn’t systematically provide a way to reduce overall cost after bids in the same way alternates do.
B. Quantity allowanceThis is a form of allowance tied to a presumed quantity (e.g., rock excavation). It addresses uncertain quantities, not overall budget flexibility in the bidding process.
C. Unit pricingUnit prices provide fixed prices per unit (e.g., per cubic meter, per square meter) for work items whose final quantities are uncertain. They are useful for adjustments after contract award as quantities change, but they are not the primary tool for adjusting total scope to meet the owner’s budget at bid time.
Therefore, the CSI-aligned answer for allowing flexibility when bids may exceed the budget is:
D. Alternates
Key CSI-Related References (titles only, no links):
CSI Project Delivery Practice Guide – procurement and pricing strategies, including alternates and allowances.
CSI Construction Specifications Practice Guide – Division 01 sections on Alternates, Unit Prices, and Allowances.
CSI CDT Study Materials – explanations of bid alternates and their role in controlling project cost.
As a project manager representing a private client, which of the following instances would best benefit from a constructability review meeting?
The client is unfamiliar with this type of project.
The project team consists of multiple new members.
The site presents unusual challenges and constraints.
The contractor is unable to commit to original schedule.
Comprehensive and Detailed Explanation (CSI-aligned, paraphrased)
In CSI’s project delivery guidance, constructability reviews are described as a structured way to have construction-experienced professionals—often contractors, CMs, or experienced field personnel—review the design during planning or design phases to determine:
Whether the design can be built efficiently and safely
How site conditions, constraints, and logistics will affect means and methods
Potential cost, schedule, and sequencing issues arising from unique or complex aspects of the project
Constructability reviews are especially valuable when:
The site is constrained (tight urban sites, limited access, nearby sensitive structures)
There are unusual ground, environmental, or logistical conditions
The work involves complex staging, phasing, or access issues
Option C. The site presents unusual challenges and constraints is therefore the clearest trigger for a constructability review, because it directly ties to the need to evaluate how the physical and logistical realities of the site affect construction feasibility, cost, and sequence.
Why the other options are less appropriate:
A. The client is unfamiliar with this type of project.This calls for more owner education, clearer communication, and perhaps additional planning or programming support—not specifically a constructability review. The core need is understanding, not constructability.
B. The project team consists of multiple new members.That suggests a need for team alignment, clarification of roles, and communication protocols. While new team members may benefit from constructability input, the main justification for a formal constructability review is project/site complexity, not simply team turnover.
D. The contractor is unable to commit to original schedule.This is a procurement or scheduling problem, often addressed through rescheduling, negotiation, or possibly re-bid. Constructability reviews are proactive during design; schedule commitment issues often arise later and are handled with different tools (e.g., schedule analysis, changes, resequencing).
Key CSI-Related References (titles only):
CSI Project Delivery Practice Guide – sections on constructability reviews and preconstruction services.
CSI CDT Study Materials – discussions of preconstruction evaluation, constructability, and risk identification.
What determines the responsibilities of the participants on the project team?
Size of the project
Nature of the project
Cost of construction
Project delivery type
CSI teaches that while project size, nature, and cost all influence the complexity and staffing of a project, the primary determinant of formal roles and responsibilities among owner, design professional, and constructor is the project delivery method.
For example:
In Design-Bid-Build (DBB), the A/E designs under a separate contract with the owner; the contractor is selected later and has no design responsibility (except limited design delegation).
In Design-Build (DB), the design-builder assumes both design and construction responsibilities under a single contract with the owner; the architect is typically under contract to the design-builder.
In Construction Manager at Risk (CMAR), the CM has both preconstruction services and then a construction contract with a Guaranteed Maximum Price.
In IPD, key participants share responsibilities collaboratively, often under multi-party agreements.
Because contracts and relationships change with the delivery method, the Project delivery type (Option D) is what determines how responsibilities are allocated in a formal, contractual sense.
Why the other options are not the best answer:
A. Size of the project – Larger projects may require more staff or additional roles (e.g., full-time construction administrator), but they do not fundamentally change who is contractually responsible for design, construction, and administration.
B. Nature of the project – A hospital vs. a warehouse may influence technical requirements and consultant types, but not the core allocation of responsibilities if the delivery method is the same.
C. Cost of construction – Budget level affects scope and possibly oversight intensity, but not the basic contractual roles of owner, A/E, and contractor.
Key CSI-Oriented References (titles only, no links):
CSI Project Delivery Practice Guide – chapters on Project Delivery Methods and team responsibilities.
CSI CDT Body of Knowledge – “Project Delivery Methods and Their Impact on Roles and Responsibilities.”
Which of the following elements should be included in Supplementary Conditions?
Requirements for a schedule of values
Claims and dispute resolution requirements
Equal employment opportunity requirements
Termination of the work by owner or contractor
CSI organizes the contract documents into a logical hierarchy:
General Conditions – Standard baseline clauses on rights, responsibilities, procedures (e.g., claims, dispute resolution, termination, payments, schedule of values reference).
Supplementary Conditions – Project-specific modifications or additions to the General Conditions, often driven by laws, funding requirements, or owner policies.
Division 01 – General Requirements – Administrative and procedural requirements specific to the project (submittals, schedule of values procedures, temporary facilities, etc.), coordinated with the Conditions of the Contract.
CSI’s guidance (as used for CDT) explains that Supplementary Conditions are the place to add or modify contract conditions to comply with local laws, regulations, and owner requirements that go beyond or differ from the standard General Conditions. Typical items include:
Project-specific insurance requirements and limits,
Local wage requirements,
Equal Employment Opportunity (EEO) and affirmative action provisions,
Special regulatory or funding-agency conditions.
Therefore, Equal Employment Opportunity requirements belong properly in Supplementary Conditions, making Option C the CSI-consistent answer.
Why the others are incorrect in CSI’s structure:
A. Requirements for a schedule of valuesCSI places the detailed procedures and requirements for the schedule of values in Division 01 – General Requirements, not in the Supplementary Conditions. The General Conditions may mention the schedule of values at a high level, but the “how to” (formats, breakdown, submission procedures) belongs in Division 01, not Supplementary Conditions.
B. Claims and dispute resolution requirementsStandard claims and dispute resolution clauses are part of the General Conditions (for example, notice requirements, initial decision-maker roles, mediation/arbitration steps). Supplementary Conditions may modify certain aspects if needed, but the base provisions themselves are not created there; they originate in the General Conditions.
D. Termination of the work by owner or contractorTermination rights (for cause or for convenience) and their procedures are fundamental contract provisions that belong in the General Conditions. Like claims, they can be adjusted in Supplementary Conditions, but the primary termination clauses are part of the standard General Conditions text, not something you “include” first in Supplementary Conditions.
Key CSI-aligned references (no links):
CSI Construction Specifications Practice Guide – chapters on the Conditions of the Contract and the roles of General and Supplementary Conditions.
CSI CDT Body of Knowledge – organization of the Project Manual and correct placement of Division 01, General Conditions, and Supplementary Conditions content.
Which of these is NOT a graphical format used to establish order and organization of construction drawings?
United States National CAD Standard
American Institute of Architects (AIA) CAD Layer Guidelines
Construction Specifications Institute (CSI) Uniform Drawing System
MasterFormat®
CSI’s various classification and formatting standards serve different purposes, and CDT content draws clear distinctions between them:
The United States National CAD Standard (NCS) and the AIA CAD Layer Guidelines (now part of NCS) define graphic conventions, sheet organization, layering, and symbols for CAD drawings.
The CSI Uniform Drawing System (UDS) (now integrated into the NCS) provides consistent formats and conventions for construction drawings, including sheet organization, drawing set organization, schedules, notation, and symbols.
All three—NCS, AIA CAD Layer Guidelines, and CSI UDS—are associated with graphical and organizational standards for construction drawings.
By contrast:
MasterFormat® is CSI’s specification and work-results classification system, which organizes information primarily into Divisions and Sections for specifications and other written documents, not drawings. CDT materials repeatedly emphasize that MasterFormat is used to organize project manual content and other written construction information, not the graphical content of the drawings.
Therefore, the one item not used as a graphical format for organizing drawings is:
D. MasterFormat®
Why the other options are correct as “graphical” or drawing-related formats:
A. United States National CAD Standard – Provides a nationally coordinated standard for CAD drawing presentation, including layering, symbols, and sheet organization.
B. AIA CAD Layer Guidelines – Define standard layer naming and structure for CAD drawings; these are explicitly about how graphical information is organized in electronic drawings.
C. CSI Uniform Drawing System – Developed to standardize the organization and graphical conventions of drawings, later integrated into NCS.
Thus, from a CSI standpoint, MasterFormat® is the outlier here: it organizes written construction information, not graphical drawing formats, making Option D the correct choice.
What does the Integrated Project Delivery (IPD) process involve?
A collaborative, integrated, and productive team composed of key project participants
Traditional delivery methods and team relationships for improving project performance by understanding the qualifications and attributes of team members
Responsibility silos for greater efficiencies, leading to project success
Segregat knowledge gathered as needed with paper-based communications to team members
Within CSI’s project delivery discussion, Integrated Project Delivery (IPD) is defined as a highly collaborative project delivery approach where key project participants—typically owner, architect/engineer, and contractor (and often major trades and key consultants)—work together as an integrated team from very early in the project.
Core characteristics of IPD in CSI-oriented material include:
Early involvement of key participants in planning, design, and sometimes even programming.
A single, collaborative team structure (rather than traditional silos of responsibility) focusing on shared project goals (cost, schedule, quality, performance).
Shared information and decision-making, often supported by digital tools (such as BIM) so that design, cost, constructability, and operations considerations are integrated.
A focus on joint problem-solving and collective risk and reward, rather than adversarial relationships.
That description aligns directly with Option A: “A collaborative, integrated, and productive team composed of key project participants.”
Why the other options are incorrect:
B. Traditional delivery methods and team relationships…IPD is specifically a departure from traditional team relationships (like those in conventional Design-Bid-Build), which are more linear and segmented. IPD emphasizes integrated rather than traditional or separated relationships.
C. Responsibility silos for greater efficiencies…“Responsibility silos” describe the opposite of IPD. IPD seeks to break down silos, fostering shared responsibility and integrated decision-making.
D. Segregat[ing] knowledge… with paper-based communications…IPD promotes continuous, transparent information sharing, often using digital platforms and models. Segregated, paper-based communications are characteristic of older, more fragmented approaches, not IPD.
Key CSI Reference Titles (no links):
CSI Project Delivery Practice Guide – sections on Integrated Project Delivery and collaborative team structures.
CSI CDT Body of Knowledge – “Project Delivery Methods” and comparison of IPD with traditional methods.
Which document obligates the architect/engineer to review submittals during construction administration?
AIA Document A201, General Conditions of the Contract for Construction
AIA Document B101, Standard Form of Agreement Between Owner and Architect
AIA Document D200, Project Checklist
AIA Document G612, Owners Instructions to the Architect
In CSI/CDT study materials, a key concept is that each party’s legal obligations come from their own agreement:
The owner–contractor relationship is defined in the Owner–Contractor Agreement and its General Conditions (commonly AIA A201).
The owner–architect relationship is defined in the Owner–Architect Agreement (commonly AIA B101).
The architect’s duty to provide construction administration services, including reviewing submittals, is a service owed to the owner and is therefore set out in the Owner–Architect Agreement, not the General Conditions.
In AIA’s standard structure (which CSI uses extensively in CDT):
AIA B101 (Owner–Architect Agreement) lists the architect’s basic services, including:
Construction Phase Services
Review of submittals (shop drawings, product data, samples, etc.)This is what legally obligates the architect to review submittals as part of their contracted services to the owner.
AIA A201 (General Conditions) describes the architect’s role in the context of the construction contract between owner and contractor (e.g., the architect will review submittals in accordance with the Contract Documents), but the architect’s obligation itself arises from B101, which is the contract between owner and architect.
Therefore, the document that actually obligates the architect/engineer (A/E) to perform submittal review as part of construction administration is AIA Document B101 → Option B.
Why the other options are incorrect:
A. AIA Document A201, General Conditions of the Contract for ConstructionA201 is part of the Owner–Contractor contract. It establishes procedures and the architect’s function with respect to the contractor, but it does not itself create the architect’s contractual obligation to the owner; that comes from B101. A201 can describe what the architect will do “as provided in the Owner–Architect Agreement,” but the promise from the architect is in B101.
C. AIA Document D200, Project ChecklistD200 is a non-contractual guide/checklist used for planning and scoping services. It is an aid, not a contract, and does not bind the architect to perform submittal review.
D. AIA Document G612, Owners Instructions to the ArchitectG612 is also a form tool, used for gathering owner’s instructions and information; it is not itself the agreement that defines the architect’s scope of services and obligations.
CSI / CDT-aligned references (no links):
CSI Project Delivery Practice Guide – discussions of standard AIA documents and how responsibilities are allocated between owner, architect, and contractor.
CSI Construction Specifications Practice Guide – sections on relationships between A201 and B101.
CDT Exam references to AIA A201 – General Conditions and AIA B101 – Owner–Architect Agreement in the “Agreements & Conditions of the Contract” domain.
During the bid period, what does the architect issue if it is necessary to modify the procurement documents?
Addenda
Construction change directives
Change order
RFI response
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
CSI distinguishes clearly between procurement-phase modifications and construction-phase changes:
During procurement (bidding/negotiation), the documents used for pricing and proposing work are called procurement documents (instructions to bidders, bid forms, drawings and specifications issued for bid, etc.).
If these need to be clarified, corrected, or modified before bids are received, the architect/engineer issues an addendum.
An addendum:
Is a written or graphic modification to the procurement documents issued before the execution of the contract.
Becomes part of the procurement documents and, once the contract is formed, part of the contract documents.
Must be issued to all known prospective bidders to maintain fairness and keep everyone pricing the same requirements.
By contrast:
Construction Change Directive (CCD) and Change Order are used after the contract is executed, to modify the contract documents during construction (scope, cost, or time).
An RFI response answers a bidder’s or contractor’s question, but if the answer changes the procurement/contract requirements, it must be formalized by addendum (before award) or change order/CCD (after award), not just left as an informal answer.
Therefore, the correct instrument during the bid period to modify procurement documents is:
A. Addenda
Key CSI-Related References (titles only, no links):
CSI Project Delivery Practice Guide – chapters on Procurement, Addenda, and pre-award communications.
CSI Construction Specifications Practice Guide – Division 00 discussions of Instructions to Bidders and Addenda.
CSI CDT Study Materials – definitions of Addenda vs. Change Orders vs. Construction Change Directives.
Which of the following is LEAST important to log when documenting the decision-making process?
Date, time, and location of the meeting
List of attendees and who they represent
Length of time each attendee spent speaking
Action items with responsibilities assigned and date to accomplish
Good documentation of project decisions (typically in meeting minutes) is essential for traceability, accountability, and later dispute avoidance. CSI-oriented project management procedures and your uploaded construction management documents emphasize that minutes should record, at a minimum:
When the meeting occurred – date, time, location.
Who attended and whom they represent (owner, A/E, contractor, etc.).
What was decided and what remains unresolved.
Action items, assigned responsibilities, and due dates.
These elements are repeatedly included in the sample agendas and minutes procedures in your Construction Management Plan and Project Management Manual, which require minutes and action/open-items lists to be prepared and circulated after key meetings.
None of these procedures mention, or require, tracking how long each attendee spoke. That level of granularity does not contribute meaningfully to documenting decisions, responsibilities, or follow-up work. It adds administrative burden without improving clarity or accountability.
Thus:
A (date/time/location) – important context for the record.
B (attendees and representation) – critical to know who agreed to what.
D (action items, responsibilities, dates) – central to the decision-making trail.
C (length of time each attendee spoke) – least important and not standard practice in CSI-based documentation.
So the correct answer is Option C.
CSI-aligned references (no URLs):
CSI Project Delivery Practice Guide – sections on project meetings and documentation.
CSI CDT body of knowledge – “Documenting decisions and maintaining project records.”
The names of the project, owner, architect/engineer and consultants, and the general project data such as a location map are normally included in which of the following?
Sheet index
Cover sheet
General notes
Building code summary
In CSI-based drawing organization, the cover sheet (sometimes called the title sheet) is the primary identification sheet of the drawing set. It typically includes:
Project name and project number
Owner’s name
Architect/engineer’s name and logo
Names of key consultants (structural, mechanical, electrical, etc.)
General project data (site address, legal description, gross area, etc.)
A location map or vicinity map
Sometimes a sheet index, code summary, and other global project information
CSI’s guidance for construction documents describes the cover sheet as the place where the project is formally identified and the major parties are listed so that anyone picking up the drawing set immediately knows what project it is, who the participants are, and where the project is located. This is exactly what the question is asking about.
Why the others are not correct in CSI’s sense:
A. Sheet index – A sheet index is usually a list of drawing sheets (by discipline and sheet number) and may be placed on the cover sheet or on a separate index sheet, but it does not normally carry the full set of project identification data, consultant names, and location map by itself.
C. General notes – General notes are used to provide global instructions or clarifications applicable to the drawings (e.g., dimensional conventions, typical construction requirements). They are not the primary location for listing the owner, A/E, consultants, or site location map.
D. Building code summary – A building code summary focuses on code-related data: occupancy classification, construction type, fire-resistance ratings, egress calculations, etc. While it may appear on the cover sheet or nearby sheets, it is not where CSI expects all of the names and general project data to be grouped.
So, per CSI’s standard organization of construction drawings and project manuals, the cover sheet is the correct answer.
During which stage of a facility's life cycle are operations and maintenance documents presented to the owner?
After the authorities having jurisdiction issues a permit
Closeout phase
Preconstruction phase
Construction phase
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
CSI organizes the facility life cycle into phases such as planning, design, construction, closeout, and operations/occupancy. Within this framework, CSI describes project closeout as the phase where the contractor and design team complete all remaining contractual obligations and formally turn the project over to the owner.
A key part of that turnover is providing the owner with operations and maintenance (O&M) information, often including:
Operating and maintenance manuals for equipment and systems
Warranties and guarantees
Spare parts lists and recommended maintenance procedures
As-built/record documentation and, sometimes, commissioning records and training materials
CSI indicates that these O&M documents are to be delivered as part of the closeout requirements, usually at or near Substantial Completion or Final Completion, so that the owner can properly operate and maintain the facility during the occupancy phase.
Therefore the correct answer is B. Closeout phase.
Why the other options are incorrect:
A. After the authorities having jurisdiction issues a permitPermits are typically issued during design or preconstruction, authorizing the start of work. At this time, the facility is not built and O&M documentation does not yet exist in final form. CSI treats permits as part of regulatory approvals, not the turnover of maintenance information.
C. Preconstruction phasePreconstruction focuses on activities like finalizing construction documents, bidding, procurement planning, and initial mobilization. O&M manuals cannot be finalized because products and systems are not yet fully installed, tested, and accepted.
D. Construction phaseDuring construction, some O&M information may be started or submitted in draft form, but CSI’s guidance is clear that formal delivery of complete O&M documentation is a closeout requirement, not an in-progress construction requirement.
Key CSI-Related References (titles only):
CSI Project Delivery Practice Guide – facility life cycle and project closeout chapters.
CSI Construction Specifications Practice Guide – Division 01 sections (Closeout Submittals, Operation and Maintenance Data).
CSI CDT Study Materials – topics on project closeout, warranties, and O&M documentation.
In the MasterFormat® specification system, which subgroup contains requirements of MEP, fire protection, and telecom systems?
Site and Infrastructure Subgroup (Divisions 30–39)
Facility Services Subgroup (Divisions 20–29)
Facility Construction Subgroup (Divisions 02–19)
Part 2 – Products
CSI’s MasterFormat® (2004 and later editions) organizes work results into five major groups, several of which are broken into subgroups. In CDT and CSI materials, the key subgroups are described as follows:
Facility Construction Subgroup (Divisions 02–19) – Covers sitework and building construction elements, such as existing conditions, concrete, masonry, metals, wood, finishes, openings, specialties, equipment, furnishings, conveying systems, fire suppression, plumbing, HVAC (in early editions), and electrical (in divisions 26–28 pre–2010 structure; in more recent updates MEP is consolidated differently but still under “facility services”).
Facility Services Subgroup (Divisions 20–29) – Specifically established to organize mechanical, electrical, plumbing, fire suppression, communications, and related systems—collectively termed facility services.
Site and Infrastructure Subgroup (Divisions 30–39) – Covers civil, site, utility, and infrastructure work, such as earthwork, site utilities, transportation, and similar site/infrastructure elements.
In the modern MasterFormat framework, CSI defines “Facility Services” as the subgroup including divisions for:
Mechanical systems
Electrical systems
Plumbing
Fire suppression / fire protection
Communications and telecom, security, and related low-voltage systems
Therefore, the subgroup that contains MEP (mechanical, electrical, plumbing), fire protection, and telecom systems is:
B. Facility Services Subgroup (Divisions 20–29)
Why the other options are incorrect or incomplete:
A. Site and Infrastructure Subgroup (Divisions 30–39)This subgroup addresses site and infrastructure work, not building internal MEP or telecom systems. Items like site utilities and transportation infrastructure belong here, not typical building MEP systems.
C. Facility Construction Subgroup (Divisions 02–19)This subgroup deals primarily with building fabric and architectural/structural elements (sitework, concrete, masonry, metals, finishes, openings, specialties, etc.). While historically some mechanical/electrical content appeared in lower-number divisions before the 2004 reorganization, in the current CSI structure, MEP and related systems are grouped under Facility Services (20–29), not under Facility Construction.
D. Part 2 – Products“Part 2 – Products” is a component of SectionFormat™, not MasterFormat’s division/group structure. SectionFormat defines the three-part structure of individual specification sections (Part 1 – General, Part 2 – Products, Part 3 – Execution). It doesn’t define which subgroup MEP/telecom systems belong to.
Thus, consistent with CSI’s MasterFormat organization, Option B is the correct answer.
Which document directly modifies the requirements of the general conditions?
Division 01, General Requirements
Supplementary Conditions
Agreement
Instructions to Bidders
In the standard organization of the contract documents as taught in CSI’s CDT materials and practice guides, the General Conditions establish the baseline contractual rights, responsibilities, and relationships among the owner, contractor, and architect/engineer (A/E).
CSI explains that whenever there is a need to change or add to the standard provisions of the General Conditions (for example, to address project-specific insurance limits, bonding, liquidated damages, or local legal requirements), those changes are made in the Supplementary Conditions. The Supplementary Conditions are expressly written to modify, delete, or add to the printed General Conditions, and they do so by direct reference to specific articles or paragraphs.
The General Conditions set the standard, overall rules of the contract.
The Supplementary Conditions are the only document whose primary purpose is to modify those General Conditions for the specific project.
Other documents (Agreement, Division 01) must be consistent with the Conditions of the Contract but are not the formal instrument intended to “directly modify” the General Conditions.
Why the other options are not correct:
A. Division 01, General Requirements – Division 01 coordinates administrative and procedural requirements for the work and bridges from the Conditions of the Contract to the technical specifications. It may elaborate how procedures are implemented but it is not the document that directly amends the General Conditions.
C. Agreement – The Agreement (e.g., AIA A101) identifies parties, contract sum, contract time, and incorporates the Conditions, drawings, and specifications by reference. It relies on the General and Supplementary Conditions; it does not systematically edit their language.
D. Instructions to Bidders – These govern the procurement phase only (how to submit bids, qualifications, bid security, etc.) and cease to have effect once the Contract is executed. They do not modify the General Conditions of the construction contract.
CSI’s Project Delivery and Construction Specifications Practice Guides describe this hierarchy and emphasize that Supplementary Conditions are the proper instrument for project-specific modifications to the General Conditions, which makes Option B the correct answer.
During design, in a design-build delivery method, what is the design-builder responsible for delivering to the owner?
Submittals
Record documents
Geotechnical reports
Construction documents
In the design-build project delivery method, the design-builder (a single entity or team under one contract) is responsible for both design and construction. Industry guidance consistent with CSI’s CDT framework explains that, unlike Design–Bid–Build (where the architect prepares construction documents and a separate contractor builds), design-build uses a single contract covering both the design and construction phases, with a “design builder” responsible for meeting contract requirements.
During the design phase of a design-build project:
The design-builder leads planning and design and, together with its architectural/engineering team, creates the detailed design needed to build the project.
Once design details are in place, this design is used to set prices and proceed into construction.
In CSI/CDT terms, the output of this design effort is the Construction Documents (drawings and specifications) that define the scope, quality, and requirements for the work and become part of the contract documents for the project.
Why the other options do not match the CDT/CSI role at this stage:
A. Submittals – Submittals (shop drawings, product data, samples) are primarily a construction-phase contractor responsibility, responding to the already-issued construction documents. They are not the primary deliverable of the design phase.
B. Record documents – Record documents (as-built drawings, O&M manuals, etc.) are post-construction deliverables, produced near the end of the project to show what was actually installed.
C. Geotechnical reports – In many project delivery methods, geotechnical investigations are owner-provided information or obtained early by the owner; the design-builder may coordinate or rely on them, but they are not the core design-phase deliverable the question is seeking.
Therefore, in a design-build delivery method, during design, the design-builder is responsible for producing and delivering Construction documents (Option D) to the owner.
Core CSI-aligned references for this question (no URLs):
CSI Project Delivery Practice Guide – sections on Design-Build roles and responsibilities (single point of responsibility for design and construction).
Industry explanations of design-build (single contract; design builder leads design and then construction).
When is decommissioning required for a facility?
When the entire building is going to be demolished
When the facility is no longer needed for operations
When the facility will not be used again in the future
When the building changes owners
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
In CSI’s description of the facility life cycle, the last phase is decommissioning. This phase occurs when a facility is taken out of service because it is no longer needed for its original operations, has reached the end of its useful life, or is being prepared for conversion to a different use. The emphasis is on the facility no longer being required for its intended operations, not strictly on demolition or permanent abandonment.
Decommissioning tasks can include: removing or securing systems, handling hazardous materials, salvaging components, planning for demolition, or preparing the facility for a different use.
Because decommissioning can precede demolition, adaptive reuse, or other end-of-life actions, it is triggered when the facility is no longer needed for operations.
Option B captures this definition accurately.
Options A and C are too narrow: demolition or permanent disuse are possible outcomes of decommissioning but not the only reasons it is required. Option D (change of ownership) does not automatically require decommissioning; a facility can continue operating normally under a new owner.
Relevant CSI references (no links):
CSI Project Delivery Practice Guide – Facility Life Cycle chapter (discussion of operations, maintenance, and decommissioning).
CSI CDT Body of Knowledge – overview of project phases including decommissioning.
Cost classification, data organization, and specifications use which written formats?
OmniClass and UniFormat
UniFormat and MasterFormat
OmniClass and MasterFormat
SectionFormat® and MasterFormat
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
CSI distinguishes among several written formats, each with a specific purpose:
UniFormat – organizes information by systems and assemblies (elements) and is commonly used for:
Cost classification and early cost estimating,
Data organization in the programming, schematic design, and design development stages.
MasterFormat – organizes information by work results (trades/products) and is used for:
Project specifications,
Detailed cost information tied to specification sections,
Organizing procurement and construction information.
CSI’s practice guides clearly connect cost classification and data organization in early design with UniFormat, and detailed specifications and later-stage cost information with MasterFormat. Therefore, the correct pair is:
UniFormat and MasterFormat (Option B)
Why the other options are incorrect:
A. OmniClass and UniFormat – OmniClass is a broader classification system for the built environment, not the primary written format CSI assigns to “specifications.” UniFormat is used for cost and systems, but OmniClass is not the standard format for specs.
C. OmniClass and MasterFormat – Again, OmniClass is overarching; it does not replace UniFormat as the main element-based cost classification tool.
D. SectionFormat and MasterFormat – SectionFormat is the internal three-part structure of a specification section (Parts 1, 2, and 3) and is not the format used for cost classification and data organization; that role is assigned to UniFormat.
Relevant CSI references (paraphrased):
CSI Project Delivery Practice Guide – descriptions of UniFormat use for system-based project descriptions and cost planning, and MasterFormat use for work result organization.
CSI Construction Specifications Practice Guide – chapters on MasterFormat, UniFormat, and their roles in specifications and estimating.
Under SectionFormat®, where would the Article "Manufacturers" be found?
Either Part 1 or Part 2
Part 1 only
Part 2 only
Part 3 only
CSI’s SectionFormat® establishes a standard three-part structure for specification sections:
Part 1 – GeneralAdministrative and procedural requirements specific to that section (scope, related work, references, submittals, quality assurance, delivery/storage, warranties, etc.).
Part 2 – ProductsDescriptions of products, materials, and equipment required: manufacturers, materials, components, fabrication, finishes, performance requirements, and similar.
Part 3 – ExecutionField/application/installation requirements: examination, preparation, installation/application procedures, tolerances, field quality control, adjustment, cleaning, protection, etc.
Within this structure, CSI specifically places “Manufacturers” as an article in Part 2 – Products. This is because Part 2 is where the specifier identifies:
Acceptable manufacturers or manufacturer list
Standard products and models
Performance or quality requirements associated with those manufacturers
Product substitutions (if addressed by article structure)
Placing “Manufacturers” in Part 2 maintains consistency across specs and makes it clear that manufacturer-related information is part of the product requirements, not administrative conditions or execution procedures.
Why the other options do not align with SectionFormat®:
A. Either Part 1 or Part 2Although some poorly structured sections in practice may misplace content, CSI’s recommended SectionFormat® is explicit: manufacturers belong in Part 2 – Products. Allowing Part 1 or Part 2 would blur the distinction between administrative requirements and product requirements.
B. Part 1 onlyPart 1 is not intended for listing manufacturers. It covers general/administrative topics, not the specific products or manufacturers.
D. Part 3 onlyPart 3 deals with execution/installation in the field, not who manufactures the products. Manufacturer listing in Part 3 would conflict with CSI’s structure and make the section harder to interpret and coordinate.
Therefore, under SectionFormat®, the correct location for the “Manufacturers” article is Part 2 only (Option C).
Key CSI References (titles only, no links):
CSI SectionFormat® and PageFormat™ (official CSI format document).
CSI Construction Specifications Practice Guide – chapters explaining the three-part section structure and where to place specific articles such as “Manufacturers.”
CSI MasterFormat®/SectionFormat® training materials used for CDT preparation.
Which of the following is a format that standardizes the way text is arranged in specification pages so that it is best suited for easy reading and rapid reference?
SectionFormat®
PageFormat
MasterFormat®
UniFormat®
CSI defines three major, complementary organizing tools:
MasterFormat® – classifies work results and organizes specification sections into numbered divisions.
SectionFormat® – standardizes the internal arrangement and headings of text within each specification section (e.g., Part 1 – General, Part 2 – Products, Part 3 – Execution), making it easy to read and quickly reference.
UniFormat® – organizes information by systems and assemblies, often used in early design and cost planning rather than final spec sections.
The question specifically asks about a format that standardizes how the text is arranged on specification pages for easy reading and rapid reference. That is exactly the role of SectionFormat®: it defines the structure and order of information inside the section so that users know where to find general requirements, product information, and execution requirements, regardless of the project.
By contrast:
MasterFormat® (Option C) organizes which section information goes into (coding and naming of sections), not the layout of text within the section.
UniFormat® (Option D) structures information by building systems/elements, especially for programming and early design, not for final spec page layout.
PageFormat (Option B) is not one of CSI’s registered, widely recognized branded formats in the way the question is framed.
Therefore, the correct answer is Option A – SectionFormat®.
CSI-aligned references (no URLs):
CSI Construction Specifications Practice Guide – chapters on MasterFormat®, SectionFormat®, and UniFormat®.
CSI SectionFormat® & PageFormat™ standard (CSI publication).
You are working on a project that is subject to regulatory reviews both at the city and at the state level. Both agencies have acknowledged receiving the construction documents. This project has already been awarded to a general contractor, and you are representing the owner who wants to start construction immediately. How would you advise the owner?
Construction may begin immediately as long as a safety manager is present, and the contractor avoids all excavation work until after the permits are issued.
Since the state approval is more critical than the city approval, construction may proceed immediately after the state permits are issued.
Since the city approval is more critical than the state approval, construction may proceed immediately after the city permits are issued.
Construction may begin only after both city and state permits have been issued.
Under CSI’s project delivery and contracting principles, the contract documents are only one part of the legal framework that governs construction. Regulatory approvals and permits are a separate, critical requirement that must be satisfied before construction begins, regardless of contract award or the owner’s desire to proceed.
Key CSI-aligned concepts:
Building codes and other regulations are enforced by authorities having jurisdiction (AHJs)—in this case, both city and state agencies.
The owner, often via the design professional, must obtain the required permits from all AHJs before construction activities are started.
Contract award to a general contractor does not authorize construction to proceed without permits; doing so exposes the owner and contractor to violations, stop-work orders, penalties, and liability.
Therefore, the correct advice in a CSI-consistent framework is:
Construction may begin only after both city and state permits have been issued. (Option D)
Why the other options are incorrect:
A. Construction may begin immediately … if a safety manager is present and excavation is avoided.Safety management and the type of work do not override permit requirements. Work without required permits is typically prohibited regardless of safety measures.
B. Since the state approval is more critical … proceed after the state permits are issued.CSI acknowledges that all applicable jurisdictions must be satisfied. One jurisdiction is not “more critical” such that the other can be ignored. If both city and state approvals are required, the project must have both before construction starts.
C. Since the city approval is more critical … proceed after city permits are issued.Same issue as B. If both city and state have regulatory authority, both sets of permits are required; neither is optional or subordinate in this sense.
CSI-aligned references (no external links):
CSI Project Delivery Practice Guide – sections on regulatory requirements and authorities having jurisdiction.
CSI CDT Study materials – discussions of permits, code compliance, and the relationship between AHJ approvals and the start of construction.
Typical General Conditions of the Contract as discussed in CSI materials – provisions requiring compliance with laws, codes, and permits.
TESTED 23 Nov 2025
