Based on the diagram below, what is the percentage slope between D1 and C2 if the grid is 10 m × 10 m?
For granular material, what is the typical optimum moisture content for dry densities ranging from 2100 kg/m³ to 2200 kg/m³?
In an oil and gas project, the location of a pile is offset by 78 mm north and 54 mm east of the key location plan. The location was stamped and issued for construction by a consulting engineering company. The statement on the drawings says, “Offset more than 75 mm is not accepted.” Which of the following is the best approach for the civil engineering technologist to take?
Which of the following can a civil engineering technologist request from a concrete supplier to verify that concrete falls within municipal specifications?
The graph below is used for tracking progress and costs of a project for a client. What can be concluded about the project at week 10?
An engineered wooden “I” floor joist has a hole that was cut at the bearing location. What is the best way to verify that the structural integrity of the joist has not been compromised?
Which of the following situations would cause the most serious delay on a project?
Which of the following should be performed to determine the cumulative effect of a land development project on land, air, and water?
What must an employer do if an employee could be exposed to hazardous materials on a work site?
What personal protective equipment is most important when surveying near active traffic?
A road to be filled is 6 m wide with 3:1 side slopes and a maximum of 6 m fill at the road centre line. The cut and fill are symmetrical, as shown in the image below. The cost of moving material is $4.00 per m³ per km haul length. What is the minimum cost to fill in the road?
A site inspection reveals a beam that does not conform to Issued for Construction (IFC) drawings. What should be done?
What is the most important information a civil engineering technologist should be familiar with before stepping onsite during site inspection?
In the middle of the project, the client proposed an additional scope of work that requires a change order to the contract. Which statement applies to the contractor’s percentage fee (i.e., mark-up) that should be added to the total amount in the change order?
Which of the following tests would most likely be used to determine if engineered fill was placed to meet contract specifications?
A civil engineering technologist works for a contractor. An engineer notifies him that the depth of concrete pilings needs to be increased. What is the first thing the civil engineering technologist should do?
What information is provided by a 5-point Proctor density test on a soil sample?
Which of the following statements best describes thefor piling loads in the diagram below?
When calculating the total cost for a multi-year project, which of the following parameters should be considered?
A geotechnical report indicates the presence of a peat layer in several boreholes. The peat layer ranges in thickness from 450 mm to 1200 mm and is found at a depth of 1.5 m below the existing grade. How should this be addressed in the project specifications that are being prepared?
The k-value in a vertical curve design defines the horizontal distance required to make a 1% change in the gradient. Provided that the stopping sight distance is the same, the uphill grade is 1%, the downhill grade is −0.5%, and the design speed is 90 km/h, what is the length of the vertical curve?
EXCERPT FROM MUNICIPAL BYLAW 1234 – ZONING
Section 3: Single family zone
3.1 All dwellings shall house one family.
3.2 All dwellings shall have a minimum main floor area of 120 m².
3.3 All dwellings shall be constructed a minimum of 10.0 m from the front property line, 15.0 m from the rear property line, and 1.5 m from the side property lines.
3.4 An application that does not fulfill the above requirements shall be referred to Council.
A soil sample has a porosity of 40%, and the specific gravity of solids is 2.60. What would be the approximate value of dry density of the soil if the soil is completely saturated?