Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Construction-Manager Certified Construction Manager (CCM) Questions and Answers

Questions 4

While conducting an inspection of the work in progress for a design-bid-build project, a CM notices that some of the completed work does not conform to the construction documents. The FIRST thing the CM should do is

Options:

A.

document the non-conforming work and distribute the documentation to the contractor, design professional, and client.

B.

discuss the concerns with the owner.

C.

direct the contractor to correct the non-conforming work.

D.

schedule a meeting with the design professionals and the client to discuss the issues.

Buy Now
Questions 5

Which of the following is a key element of a safety culture?

Options:

A.

Time is of the essence

B.

Maximizing profit

C.

Prompt accident notification

D.

Ownership and management buy-in

Buy Now
Questions 6

The chief estimator for a construction company is asked to provide an estimate based on known project characteristics, such as square footage and unit prices. The estimator will MOST likely be employing which technique?

Options:

A.

Conceptual Estimating

B.

Parametric Estimating

C.

Bottom Up Estimating

D.

Analogous Estimating

Buy Now
Questions 7

As the owner's rep, a CM is providing on-site construction management services to a municipality for their new design-build city mall project.

The state requires a 40-hour value engineering workshop for all projects over $10 million. What are the key talking points about the VE process that the CM will highlight to the city's director of public works?

Options:

A.

Life cycle and maintenance costs should not be considered.

B.

A multi-discipline review on functions and alternate solutions.

C.

Scope reduction will reduce overall project budget.

D.

Interface with the design-build team is not needed at this time.

Buy Now
Questions 8

An agency CM is overseeing the construction of a large, complex multi-story, high security building in a remote area. The building had a specialized spire installed at the top, which serves as an encrypted signal transmitter. Construction is complete and the contractor has de-mobilized, but then it is discovered that the signal transmitter is not transmitting the signal. The owner's QC plan required testing for the functionality of the transmitter, but the contractor has not shown test results reflecting adequate performance. Who is responsible for the cost of remobilization?

Options:

A.

Designer of record

B.

Agency CM

C.

Contractor

D.

Owner

Buy Now
Questions 9

During the design phase of a project, the owner had requested the design team develop mitigating strategies due to expected budget concerns. During the procurement process, the agency CM should advise the owner consider

Options:

A.

incorporating Time and Material Alternates into the bid documents.

B.

incorporating Add/Deduct Alternates into the bid documents.

C.

evaluating Phase Alternates in the bid documents.

D.

evaluating Schedule Alternates in the bid documents.

Buy Now
Questions 10

A relatively new general contractor has executed three projects. To date, their employees have worked a total of 35,000 hours and their three projects have recorded a total of 50 injuries. What is their recordable case rate?

Options:

A.

0.0014

B.

150

C.

286

D.

700

Buy Now
Questions 11

Under the Brooks Act, professional services of architects and engineers on federal projects must be

Options:

A.

funded by public dollars.

B.

audited every six months.

C.

qualification-based rather than bid.

D.

contracted before GC services.

Buy Now
Questions 12

Which of the following would MOST likely help provide benchmarking for a sustainable project?

Options:

A.

Environmental Protection Agency

B.

Department of Transportation

C.

Energy Star program

D.

Housing and Urban Development

Buy Now
Questions 13

If it can be proven that there was discrimination based on gender during the hiring process, someone may lose their CCM credential due to a violation of the

Options:

A.

owner's diversity requirements.

B.

owner's contract requirements.

C.

CMAA Code of Professional Conduct.

D.

CMAA Standards of Practice.

Buy Now
Questions 14

A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month 10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million.

Which statement most accurately portrays program status?

Options:

A.

On schedule, pay application accurately reflects percentage complete.

B.

Behind schedule, pay application exceeds percentage complete.

C.

Behind schedule, pay application accurately reflects percentage complete.

D.

On schedule, pay application exceeds percentage complete.

Buy Now
Questions 15

A construction manager is responsible for the bid review and evaluation of an $85 million high school project. All bids must be submitted in person at the clients Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?

Options:

A.

Put the contractor's unopened bid in tight security until the bid opening has been completed.

B.

Send the bid back to the contractor and apologize for the mishap.

C.

Include the unopened bid. since it clearly was an oversight.

D.

Inform the Owner and review the instructions to bidders for guidance on how to proceed.

Buy Now
Questions 16

Float, date, and duration are examples of

Options:

A.

schedule elements.

B.

schedule parameters.

C.

constraints.

D.

logic elements.

Buy Now
Questions 17

Lifecycle analysis of a project will provide the greatest impact during which of the following phases?

Options:

A.

Pre-Design

B.

Design

C.

Construction

D.

Procurement

Buy Now
Questions 18

The contract documents normally require which party/parties to coordinate the transfer of spare parts and warranties to the owner?

Options:

A.

CM

B.

Regulatory agencies

C.

CxA

D.

Designer

Buy Now
Questions 19

A construction manager is responsible for the bid review and evaluation of an $85 million high school project. All bids must be submitted in person at the client's Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?

Options:

A.

Put the contractor's unopened bid in tight security until the bid opening has been completed.

B.

Send the bid back to the contractor and apologize for the mishap.

C.

Include the unopened bid. since it clearly was an oversight.

D.

Inform the Owner and review the instructions to bidders for guidance on how to proceed.

Buy Now
Exam Name: Certified Construction Manager (CCM)
Last Update: Oct 17, 2025
Questions: 65

PDF + Testing Engine

$63.52  $181.49

Testing Engine

$50.57  $144.49
buy now Construction-Manager testing engine

PDF (Q&A)

$43.57  $124.49
buy now Construction-Manager pdf