Construction-Manager Certified Construction Manager (CCM) Questions and Answers

Questions 4

BIM best assists the CM with

Options:

A.

managing time, safety, quality, and facility operations.

B.

planning, coordination, and control of the project.

C.

developing drawings and facility management.

D.

gathering energy, cost, facility maintenance, safety, and spatial data.

Buy Now
Questions 5

Under the Brooks Act, professional services of architects and engineers on federal projects must be

Options:

A.

funded by public dollars.

B.

audited every six months.

C.

qualification-based rather than bid.

D.

contracted before GC services.

Buy Now
Questions 6

A dispute arises during construction after the contractor encounters what they feel is unsuitable material. The CM is not notified about the areas of concern, and the contractor hauls 10.000 cy of material offsite. Three months later, the contractor submits a claim for additional cost to haul the material off. The CM should advise the owner that

Options:

A.

the owner should pay for the haul.

B.

the claim is not valid because the contractor failed to provide timely notice.

C.

the owner should pay the claim due to lack of owner information.

D.

the owner should pay 50% of the haul since the contractor did not notify the CM first.

Buy Now
Questions 7

An inexperienced client on a design-bid-build project states that they do not want the designer to assist in the review of submittals, respond to Requests for Information (RFIs). or conduct any site inspections during the construction phase. How should the CM respond to the client's request?

Options:

A.

Review the Project Procedures Manual (PPM) and then discuss with the client why their approach may add more risk to the project.

B.

Ignore the client and continue coordinating with the design professional to provide these necessary services as part of their contract.

C.

Agree with the client that this will save the project from unnecessary costs and report that the design documents should be error-free.

D.

Review the Project Management Plan (PMP) and proceed accordingly.

Buy Now
Questions 8

While conducting an inspection of the work in progress for a design-bid-build project, a CM notices that some of the completed work does not conform to the construction documents. The FIRST thing the CM should do is

Options:

A.

document the non-conforming work and distribute the documentation to the contractor, design professional, and client.

B.

discuss the concerns with the owner.

C.

direct the contractor to correct the non-conforming work.

D.

schedule a meeting with the design professionals and the client to discuss the issues.

Buy Now
Questions 9

An agency CM is assigned to a new construction project using the CMAA A-2 Standard Form of Agreement between owner and contractor. The project is experiencing concurrent critical path delays caused by the contractor and the architect. What is the BEST guidance the agency CM could give the owner for dealing with these events?

Options:

A.

The owner should plan for delayed completion.

B.

Direct both the architect and GC to mitigate each delay and have the agency CM perform a schedule impact analysis to allocate delay responsibility.

C.

The architect and GC should be directed to add resources to mitigate each of their delays at no additional cost to the owner.

D.

The owner should charge the contractor daily liquidated damages.

Buy Now
Questions 10

A program management function that promotes the efficient use of completed projects and/or parts of completed projects to maximize the owner's return on investment is called

Options:

A.

resource-leveling.

B.

contract packaging.

C.

project phasing.

D.

project financing.

Buy Now
Questions 11

Which of the following addresses the administrative and reporting requirements for a Construction Manager during execution of a project?

Options:

A.

Project Administration Guidelines

B.

Standards of Practice

C.

Construction Administration Guidelines

D.

Contract Administration Guidelines

Buy Now
Questions 12

During the design review process for a rehabilitation of a corporate office headquarters, the CM should routinely review the designers' submissions, and the reviews will include

Options:

A.

budget, schedule, and value engineering reviews.

B.

scope, constructability, and biddability reviews.

C.

constructability, biddability, and operability reviews.

D.

constructability, schedule, and maintenance reviews.

Buy Now
Questions 13

A construction manager is responsible for the bid review and evaluation of an $85 million high school project. All bids must be submitted in person at the clients Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?

Options:

A.

Put the contractor's unopened bid in tight security until the bid opening has been completed.

B.

Send the bid back to the contractor and apologize for the mishap.

C.

Include the unopened bid. since it clearly was an oversight.

D.

Inform the Owner and review the instructions to bidders for guidance on how to proceed.

Buy Now
Questions 14

Which of the following contract types limits the potential incentive to increase profit through increasing contract costs?

Options:

A.

Time and materials

B.

Unit price

C.

Cost plus fixed fee

D.

Cost plus a percentage of cost

Buy Now
Questions 15

The chief estimator for a construction company is asked to provide an estimate based on known project characteristics, such as square footage and unit prices. The estimator will MOST likely be employing which technique?

Options:

A.

Conceptual Estimating

B.

Parametric Estimating

C.

Bottom Up Estimating

D.

Analogous Estimating

Buy Now
Questions 16

Who owns the float in a typical project critical path schedule?

Options:

A.

Construction manager

B.

Owner

C.

Project

D.

Contractor

Buy Now
Questions 17

A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month 10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million.

Which statement most accurately portrays program status?

Options:

A.

On schedule, pay application accurately reflects percentage complete.

B.

Behind schedule, pay application exceeds percentage complete.

C.

Behind schedule, pay application accurately reflects percentage complete.

D.

On schedule, pay application exceeds percentage complete.

Buy Now
Questions 18

A CM's responsibility for safety on the jobsite includes

Options:

A.

no obligation for safety as it is the contractor's responsibility.

B.

a professional obligation shared with others.

C.

certifying subcontractor compliance.

D.

drafting the contractor's safety plan.

Buy Now
Questions 19

The general contractor on a $1.2 billion terminal at an airport finds out that, due to supply chain issues, there is a 60% risk that they will not be able to get steel onsite for 10 weeks. The late start date of steel installation is four weeks away. Such a delay would cost the owner $75,000 per week to recover. What is the expected monetary value of risk?

Options:

A.

$270,000

B.

$450,000

C.

$1.2 million

D.

$2.7 million

Buy Now
Exam Name: Certified Construction Manager (CCM)
Last Update: May 31, 2026
Questions: 65

PDF + Testing Engine

$64.99   $185.69

Testing Engine

$49.99   $142.83

PDF (Q&A)

$54.99   $157.11