While conducting an inspection of the work in progress for a design-bid-build project, a CM notices that some of the completed work does not conform to the construction documents. The FIRST thing the CM should do is
The chief estimator for a construction company is asked to provide an estimate based on known project characteristics, such as square footage and unit prices. The estimator will MOST likely be employing which technique?
As the owner's rep, a CM is providing on-site construction management services to a municipality for their new design-build city mall project.
The state requires a 40-hour value engineering workshop for all projects over $10 million. What are the key talking points about the VE process that the CM will highlight to the city's director of public works?
An agency CM is overseeing the construction of a large, complex multi-story, high security building in a remote area. The building had a specialized spire installed at the top, which serves as an encrypted signal transmitter. Construction is complete and the contractor has de-mobilized, but then it is discovered that the signal transmitter is not transmitting the signal. The owner's QC plan required testing for the functionality of the transmitter, but the contractor has not shown test results reflecting adequate performance. Who is responsible for the cost of remobilization?
During the design phase of a project, the owner had requested the design team develop mitigating strategies due to expected budget concerns. During the procurement process, the agency CM should advise the owner consider
A relatively new general contractor has executed three projects. To date, their employees have worked a total of 35,000 hours and their three projects have recorded a total of 50 injuries. What is their recordable case rate?
Under the Brooks Act, professional services of architects and engineers on federal projects must be
Which of the following would MOST likely help provide benchmarking for a sustainable project?
If it can be proven that there was discrimination based on gender during the hiring process, someone may lose their CCM credential due to a violation of the
A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month 10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million.
Which statement most accurately portrays program status?
A construction manager is responsible for the bid review and evaluation of an $85 million high school project. All bids must be submitted in person at the clients Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?
Lifecycle analysis of a project will provide the greatest impact during which of the following phases?
The contract documents normally require which party/parties to coordinate the transfer of spare parts and warranties to the owner?
A construction manager is responsible for the bid review and evaluation of an $85 million high school project. All bids must be submitted in person at the client's Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?