Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

CPCM Certified Professional Contract Manager Questions and Answers

Questions 4

A contractor that has present or planned interests that either directly or indirectly relate to the work to be performed under a contract, and may result in an unfair competitive advantage, may have a(n) __________.

Options:

A.

organizational conflict of interest

B.

conflict of employment

C.

personal conflict of interest

D.

procurement integrity conflict

Buy Now
Questions 5

Which domains are identified in the Post-Award Life Cycle Phase?

Options:

A.

Administer Contract and Close Out Contract

B.

Administer Contract and Close Contract

C.

Perform Contract and Close Contract

D.

Administer Contract, Ensure Quality, Manage Subcontracts, and Manage Changes

Buy Now
Questions 6

Scenario 4.0: 2 — “The Requirements of a Requirements Contract”

In 2019, the buyer awarded National Concrete Supply (NCS) the first of three consecutive contracts for concrete placement, asphalt surface treatments, and pavement markings at one of its facilities. The first one-year contract had an option to extend performance through April 30, 2022. The 2020 contract was a “requirements type contract to be ordered on individual delivery orders.” The scope of the contract required NCS to furnish all labor, materials, equipment, transportation, traffic control, and supervision for construction and repair services. The contract provided that services for concrete work would “include, but not be limited to” base course restoration, crack repair, joint repair, concrete headwalls, complete restoration, concrete curb and gutter, concrete porches, steps, and patios, slab jacking, concrete sidewalks, rapid-set concrete repair, culverts and drainage structures, repair or construction of roads, airfield surfaces, walkways, retaining walls, parking lots, and concrete footings.

The buyer reserved the right “to have work falling within the scope of the contract performed by in-house personnel, job order contracting, or by another contract where concrete placement, asphalt surface treatment, or pavement marking is incidental to other work.”

The 2020 contract also included clauses stating, among other things, that this was a requirements contract and that the estimated quantities were not the buyer’s total requirements, but only estimates of requirements exceeding quantities the buyer might furnish within its own capabilities.

CPCM Question 6

Following expiration of the 2020 contract, the buyer entered into additional one-year contracts in 2022 and 2023. Based on the comparison table provided, the key changes were:

    2022: Added revisions to site work associated with the placement of concrete or asphalt; added a definition of “incident” as work in, on, and up to a perimeter of 5 feet around the structure or item to complete work if its origin is within that 5-foot perimeter; no change to contract description; no change to the clause stating the contract was a requirements-type contract.

    2023: Added items NCS would furnish, including engineering/layout, preparing subgrade to receive compacted crushed stone base, and clear and grubbing; deleted the line reserving the buyer’s right to have certain work performed by in-house personnel, job order contracting, or another contract where concrete placement, asphalt surface treatment, or pavement marking was incidental to other work; updated the contract description to state the contract was a “requirements type contract for construction/repair of asphalt pavement, concrete pavement, pavement markings, and site preparation”; and replaced the clause with one stating that the estimated quantities set forth in the 2023 contract, and the buyer’s obligation to order under the 2023 contract, excluded work that the buyer itself would perform.

NCS claimed that during performance of the 2020, 2022, and 2023 contracts, the buyer diverted substantial portions of work within the scope sections to other contractors and claimed lost profits under each contract.

Question:

The buyer agreed that the 2020 contract was a requirements-type contract. However, the buyer and seller disagreed about whether the 2022 and 2023 contracts were requirements-type contracts. Were these contracts requirements-type contracts?

Options:

A.

Yes, because the terms of the contract are consistent with the exclusivity characteristic of a requirements contract.

B.

Yes, because the description of the contract stated that they were “requirements-type” contracts.

C.

No, because the buyer did not intend to enter into a requirements-type contract.

D.

No, because the buyer reserved the right to perform work “incidental to other work” using in-house labor or other contractors.

Buy Now
Questions 7

A bilateral modification would be used for which of the following?

Options:

A.

Making negotiated equitable adjustments resulting from the issuance of a change order

B.

Making administrative changes

C.

Issuing termination notices

D.

Issuing change orders

Buy Now
Questions 8

In addition to the receipt and acceptance of all goods and services, which of the following is typically part of the contract closeout process?

Options:

A.

Acceptance Testing

B.

Sign Non-Disclosure Agreements

C.

Post-Award Meeting

D.

Return or disposal of buyer furnished property

Buy Now
Questions 9

The contract closeout process should begin when the ____________.

Options:

A.

contract is physically completed

B.

seller delivers the last shipment

C.

buyer has inspected the last shipment

D.

buyer has inspected and accepted the last shipment

Buy Now
Questions 10

__________ include such notions as principle and agency, types of authority, essential elements of a contract, market research, competition, fair and reasonable prices, and ethics.

Options:

A.

General contracting concepts

B.

Standards of Conduct

C.

Guiding Principles

D.

Terms and conditions to address specific contract matters

Buy Now
Questions 11

Contract management is the actions of contract managers to __________.

Options:

A.

develop solicitations, conduct negotiations, form contracts, perform contracts, and close contracts

B.

develop solicitations, develop offers, form contracts, perform contracts, and close contracts

C.

develop solicitations, develop offers, conduct negotiations, perform contracts, and close contracts

D.

develop solicitations, develop offers, form contracts, perform contracts, and conduct negotiations

Buy Now
Questions 12

Knowing how to capture, document, and share knowledge is an example of _________.

Options:

A.

Situational Assessment

B.

Regulatory Compliance

C.

Roles and Responsibilities

D.

Contract Principles

Buy Now
Questions 13

__________ is the most important step in the negotiation process.

Options:

A.

Documentation

B.

Collaboration

C.

Forming the team

D.

Preparation

Buy Now
Questions 14

Certain items need control of work operations, in-process controls, and inspection to meet technical requirements. In such a situation, buyers and sellers may use higher-level quality standards. Which of the following is a higher-level quality standard?

Options:

A.

Association for Testing and Materials (ASTM) certification

B.

International Standards Organization (ISO) certification

C.

Contract Quality Assurance (CQA) certification

D.

National Institute for Standards and Technology (NIST) certification

Buy Now
Questions 15

Scenario 6.0: 2

ABC Corporation (ABC) entered into a firm-fixed-price, indefinite-delivery/indefinite-quantity (IDIQ) contract with a Federal buyer for the purchase of various “Soviet-style” parts. The contract language allowed for changes to:

o Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the buyer;

o The method of shipment or packing; and

o Place of delivery.

The contract also specified that:

If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the buyer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.

ABC was unable to obtain a particular part required to fulfill a delivery order under the contract, and missed the deadline for delivery. Two years after the deadline passed, with no delivery, the failure provided cause for termination for default under the conditions outlined in the contract. To avoid default, ABC entered into Bilateral Modification 4 with the buyer. The modification required ABC to provide additional parts as consideration for late delivery. The modification also stated that a new delivery date for the original delivery would be determined in another modification.

ABC remained unable to purchase the parts to fulfill the original order. A new modification, Bilateral Modification 7 , provided that ABC would deliver “new production” models of the parts in question, rather than the “new surplus” parts specified in the original delivery order. The idea to deliver new production models of the parts had originated with ABC and was accepted by the buyer. ABC did not attempt to negotiate any changes in price, no discussions of price were held, and no price adjustment was included in this modification.

ABC completed delivery of these parts on time. However, the new production models cost significantly more than the new surplus parts originally ordered.

Approximately four months later, ABC submitted a request for equitable adjustment (REA) to the buyer. In the REA, ABC requested $1,369,377.47 , which represented the difference in price between the parts called for by the original delivery order and the parts ABC ultimately delivered. The buyer rejected the request.

Question:

Which factor contributed most to the risk assumed by the contractor for this contract?

Options:

A.

The contractor had to rely on foreign governments to provide the required materials.

B.

The contract type provides no adjustment for actual cost to perform.

C.

The contract allowed the buyer to change the scope of the contract.

D.

The contract type required an indefinite quantity of materials to be delivered.

Buy Now
Questions 16

The formula for measuring productivity is __________.

Options:

A.

productivity = risk + reward

B.

productivity = risk/reward

C.

productivity = output/input

D.

productivity = output + input

Buy Now
Questions 17

Scenario 5.0: 1

Offeror C contested the exclusion of its proposal from the competitive range under a request for proposals (RFP) issued by the buyer for “aircraft logistics, integration, configuration management, and engineering” (ALICE) services. The seller would provide personnel to work at a buyer’s location, and the buyer would direct all work and “establish work hours consistent with meeting the mission at each contract location.” The RFP provided an estimated level of effort, and offerors completed a pricing model spreadsheet.

Proposals were to be evaluated on mission suitability, past performance, and cost/price. The mission suitability and past performance factors were approximately equal in importance, and each was more important than cost/price. The purpose of the mission suitability factor was to determine the offeror’s ability to provide the required personnel at the required work hours to fulfill the contract need. It included several subfactors: management approach, overall management approach, staffing approach, and contract phase-in approach.

Offeror C argued that the buyer unfairly assessed a management approach weakness for failing to show a plan for complying with required work schedules and break times, failing to consider that the buyer establishes work hours consistent with mission needs, and failing to consider the buyer’s intention to have night shift work on Sundays. Offeror C’s proposal had discussed its approach to managing scheduling and breaks and stated that it would comply with collective bargaining agreement requirements. The buyer nevertheless judged the approach inadequate because it did not explain how Offeror C would enforce worker compliance, comparing the plan to a highway speed-limit sign that does not ensure motorists will not speed. GAO found that the RFP required offerors to explain their approaches to ensuring flexible scheduling and required breaks, but did not reasonably disclose that offerors also had to propose an enforcement mechanism.

Question:

Should Offeror B, whose cost was the lowest of the three offerors, have been awarded the contract?

Options:

A.

Yes, because the low cost justifies the deficiencies in “mission suitability” and “past performance.”

B.

Not necessarily, because “cost/price” was not weighted as heavily as “mission suitability” and “past performance” in the evaluation.

C.

Not necessarily, because “cost” is not considered an evaluation factor unless the difference between each offer is determined to be “significant.”

D.

Yes, because the lowest-cost proposal should always be accepted when using negotiated source selection.

Buy Now
Questions 18

__________ is the preferred method of determining a fair and reasonable price if adequate comparative data are available to the buyer.

Options:

A.

Negotiation

B.

Cost Analysis

C.

Catalog Pricing

D.

Price Analysis

Buy Now
Questions 19

Fee is the __________.

Options:

A.

amount left after collecting revenues and paying direct labor costs

B.

amount negotiated in excess of allowable costs

C.

amount left after collecting revenues and paying all expenses, allowable and unallowable

D.

amount negotiated in excess of all costs, allowable and unallowable

Buy Now
Questions 20

A __________ incentive is included when receiving the goods or services faster is important to the buyer.

Options:

A.

performance

B.

quality

C.

delivery

D.

cost

Buy Now
Questions 21

The field of information science is concerned with __________ recorded data.

Options:

A.

planning, collecting, directing, and controlling

B.

collecting, producing, storing, distributing, and protecting

C.

planning, producing, pricing, and placing

D.

collecting, organizing, storing, retrieving, and protecting

Buy Now
Questions 22

From a marketing perspective, to determine the right price, it is important to understand __________.

Options:

A.

promotion, line of business, and market share

B.

supply, demand, and competition

C.

competition, products/services, and organized exchange

D.

costs, target market, and authority to make a purchase

Buy Now
Questions 23

__________ is the process of ensuring all performance has been accomplished, final contractor performance has been evaluated, final payment has been made, and the contract has been reconciled.

Options:

A.

Close Out Contract

B.

Accept Performance

C.

Terminate Contract

D.

Audit Contract

Buy Now
Questions 24

Scenario 6.0: 1 — “When is a Commitment Not a Commitment?”

The buyer entered into a contract to lease 20,240 square feet of office space from Office Leasing Company (OLC). This space consisted of 8,545 square feet in Suite 1100 and 11,695 square feet in Suite 1106. The lease was for five years and provided the buyer with a renewal option as follows:

The buyer shall have the right to one renewal option for a five-year term. The renewal option shall become effective provided notice is given in writing to the lessor of the buyer’s intent to exercise such option at least 270 days before the end of the original lease term; all other terms and conditions of this lease shall remain the same during any renewal term. Said notice shall be computed commencing with the day after the date of mailing.

The buyer also entered into Supplemental Lease Agreement Number 1 (SLA 1) , which stated it was being issued to reflect an expansion of 6,431 square feet in Suite 300. SLA 1 amended the original lease to encompass the additional space, changing the space from 20,240 square feet to approximately 26,671 square feet, and increased the annual rent to $1,098,790.70. SLA 1 also amended the renewal option text to reflect the new annual rent of $1,156,935.80.

The lease, as amended by SLA 1, also contained a buyer clause regarding authority to make changes to the lease. As stated in the clause, the buyer’s authorized agent may, by written order, make changes within the general scope of this lease to the amount of space, provided the lessor consents to the change.

The first lease was set to end on December 31, 2021. On February 28, 2020, the buyer’s contract specialist sent an email to OLC stating the buyer “hereby exercises its renewal option … for a period of five years.” The buyer’s contract specialist noted that the email was “official notification that the buyer exercises its renewal option right as provided under this lease,” and indicated that “this action will be followed up with a supplemental lease agreement in the near future.” The email also stated that “per SLA 1, [the buyer] would not like to renew the expansion space portion of the lease.” At that time, the buyer was planning to vacate a good portion of its leased inventory and requested that OLC allow the buyer to terminate the Suite 300 portion of the lease effective March 1, 2021.

On March 1, 2020, OLC agreed to accept the long renewal of Suites 1100 and 1106 per the renewal option if the buyer agreed to renew the third-floor space for two weeks, from January 1, 2021, to January 15, 2021. If OLC found a new tenant for a term extending beyond January 15, 2021, it would waive any further liability for the third-floor space as of the date of the replacement lease. After discussion, the buyer agreed over the phone to a two-week extension of Suite 300 at no rent.

On August 2, 2020, OLC emailed the buyer’s contract specialist to ask when the SLA would be prepared. The buyer’s contract specialist did not respond. Several weeks later, on August 24, the buyer determined that it no longer needed to rent any of the suites under the lease and requested to be released at lease termination. On September 10, OLC once again emailed the buyer’s contract specialist to follow up on the preparation of the SLA. This time, the buyer’s contract specialist responded, apologized for the delay, and stated that he would try to get the SLA to OLC in the next couple of weeks.

However, on October 26, the buyer’s contract specialist informed OLC that the buyer no longer intended to pursue the renewal option, reflecting the buyer’s August 24 determination that it no longer required any of the suites under the lease. The following day, on October 27, OLC responded that the buyer had already exercised the renewal option and that it intended to hold the buyer to that agreement.

On June 21, 2021, the buyer notified OLC that its renewal option would not be exercised and that the buyer would not be responsible for any rent payments after the lease expiration date of December 31, 2021. Following a final decision from the buyer’s authorized agent, which rejected the claims that the buyer had exercised the renewal option, OLC filed a claim.

In order to properly exercise an option:

o The option must be accepted;

o Such acceptance may not change, add to, or qualify the terms of the offer; and

o The buyer’s acceptance has to be unconditional and in exact accord with the terms of the contract being renewed.

Question:

Based on these criteria, did the buyer exercise the lease renewal option?

Options:

A.

Yes, because the offer was accepted after discussions with the seller.

B.

Yes, because exercising an option is a unilateral change that can be executed by the buyer.

C.

No, because the buyer’s contract specialist did not have the authority to exercise the renewal option.

D.

No, because the buyer attempted to change the terms of the contract when indicating that the agency planned to exercise the option.

Buy Now
Questions 25

__________ states that only what is written in the contract is applicable and all previous verbal or written statements are not applicable.

Options:

A.

The Contra Proferentem Rule

B.

The Parol Evidence Rule

C.

Extrinsic Evidence

D.

Order of Precedence

Buy Now
Questions 26

To reach a consensus, the evaluation team should evaluate proposals __________.

Options:

A.

individually and then discuss their individual ratings as a team

B.

individually and then average their ratings

C.

as a team and select the highest-rated proposal

D.

as a team and then discuss each proposal’s strengths and weaknesses

Buy Now
Questions 27

While preparing a negotiation objective, a way to ensure flexibility is to adopt which of these positions?

Options:

A.

The average of prior sales or purchases.

B.

The high and the low.

C.

A minimum, the objective, and a maximum.

D.

The best price the market will bear.

Buy Now
Questions 28

Scenario 6.0: 2

ABC Corporation (ABC) entered into a firm-fixed-price, indefinite-delivery/indefinite-quantity (IDIQ) contract with a Federal buyer for the purchase of various “Soviet-style” parts. The contract language allowed for changes to:

o Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the buyer;

o The method of shipment or packing; and

o Place of delivery.

The contract also specified that:

If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the buyer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.

ABC was unable to obtain a particular part required to fulfill a delivery order under the contract, and missed the deadline for delivery. Two years after the deadline passed, with no delivery, the failure provided cause for termination for default under the conditions outlined in the contract. To avoid default, ABC entered into Bilateral Modification 4 with the buyer. The modification required ABC to provide additional parts as consideration for late delivery. The modification also stated that a new delivery date for the original delivery would be determined in another modification.

ABC remained unable to purchase the parts to fulfill the original order. A new modification, Bilateral Modification 7 , provided that ABC would deliver “new production” models of the parts in question, rather than the “new surplus” parts specified in the original delivery order. The idea to deliver new production models of the parts had originated with ABC and was accepted by the buyer. ABC did not attempt to negotiate any changes in price, no discussions of price were held, and no price adjustment was included in this modification.

ABC completed delivery of these parts on time. However, the new production models cost significantly more than the new surplus parts originally ordered.

Approximately four months later, ABC submitted a request for equitable adjustment (REA) to the buyer. In the REA, ABC requested $1,369,377.47 , which represented the difference in price between the parts called for by the original delivery order and the parts ABC ultimately delivered. The buyer rejected the request.

Question:

Based on the contract language that specified how the contract would handle changes, was ABC entitled to an equitable adjustment?

Options:

A.

No, because the change was made in a bilateral modification based on a substitute product offered by the contractor.

B.

Yes, because a change was made to the contract that increased the price.

C.

No, because no change was made to the specifications, design, or place of delivery.

D.

Yes, because the buyer agreed to accept “new production” weapons rather than “new surplus” weapons.

Buy Now
Questions 29

Contract management competency is a direct measurement of the manager’s ability to continuously learn and apply leadership, management, and technical competencies as __________.

Options:

A.

processes that are optional but encouraged

B.

a single, integrated process

C.

individual processes

D.

situational processes

Buy Now
Questions 30

The value added by the __________ process is in mitigating or eliminating contract performance risk by selecting the best source and negotiating prices and terms and conditions.

Options:

A.

Form Contract

B.

Select Source

C.

Price Analysis

D.

Compliance

Buy Now
Questions 31

A contract management team should __________.

Options:

A.

work independently to achieve individual goals

B.

understand each team member’s motives

C.

avoid organizational or workforce changes

D.

only use electronic forms of communication

Buy Now
Questions 32

Scenario 6.0: 2

ABC Corporation (ABC) entered into a firm-fixed-price, indefinite-delivery/indefinite-quantity (IDIQ) contract with a Federal buyer for the purchase of various “Soviet-style” parts. The contract language allowed for changes to:

o Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the buyer;

o The method of shipment or packing; and

o Place of delivery.

The contract also specified that:

If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the buyer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.

ABC was unable to obtain a particular part required to fulfill a delivery order under the contract, and missed the deadline for delivery. Two years after the deadline passed, with no delivery, the failure provided cause for termination for default under the conditions outlined in the contract. To avoid default, ABC entered into Bilateral Modification 4 with the buyer. The modification required ABC to provide additional parts as consideration for late delivery. The modification also stated that a new delivery date for the original delivery would be determined in another modification.

ABC remained unable to purchase the parts to fulfill the original order. A new modification, Bilateral Modification 7 , provided that ABC would deliver “new production” models of the parts in question, rather than the “new surplus” parts specified in the original delivery order. The idea to deliver new production models of the parts had originated with ABC and was accepted by the buyer. ABC did not attempt to negotiate any changes in price, no discussions of price were held, and no price adjustment was included in this modification.

ABC completed delivery of these parts on time. However, the new production models cost significantly more than the new surplus parts originally ordered.

Approximately four months later, ABC submitted a request for equitable adjustment (REA) to the buyer. In the REA, ABC requested $1,369,377.47 , which represented the difference in price between the parts called for by the original delivery order and the parts ABC ultimately delivered. The buyer rejected the request.

Question:

The seller’s difficulty executing this contract was due primarily to a failure in which of the following areas?

Options:

A.

Project management

B.

Supply chain management

C.

Financial management

D.

Business management

Buy Now
Questions 33

__________ provides the oversight required to ensure that both parties comply with the contract requirements.

Options:

A.

Project Management

B.

Contract Closeout

C.

Contract Administration

D.

Financial Management

Buy Now
Questions 34

Avoiding risk by using effective communication skills is an example of __________.

Options:

A.

tacit knowledge

B.

strategic knowledge

C.

procedural knowledge

D.

explicit knowledge

Buy Now
Questions 35

Which of the following financial statements shows the financial position of the business on a particular date?

Options:

A.

Balance sheet

B.

Expense accounts

C.

Income statement

D.

General ledger

Buy Now
Questions 36

A new design for an article of manufacture may be legally protected from use by others using a __________.

Options:

A.

patent

B.

license

C.

nondisclosure agreement

D.

trademark

Buy Now
Questions 37

A bid is __________ when it complies in all material respects with the invitation for bids.

Options:

A.

responsive

B.

responsible

C.

reasonable

D.

realistic

Buy Now
Questions 38

There are four essential laws of supply and demand, assuming that all other factors remain equal, which of the following statements is true?

Options:

A.

If supply decreases and demand doesn’t change, then the price will increase.

B.

If demand decreases and the supply doesn’t change, then the price will increase.

C.

If demand increases and supply doesn’t change, then the price will decrease.

D.

If supply increases and demand doesn’t change, then the price will increase.

Buy Now
Questions 39

__________ competency in contract management integrates and fortifies all other contract management competencies, and increases the depth, breadth, and impact of contract management.

Options:

A.

Knowledge

B.

Management

C.

Leadership

D.

Learn

Buy Now
Questions 40

Scenario 5.0: 1

Offeror C contested the exclusion of its proposal from the competitive range under a request for proposals (RFP) issued by the buyer for “aircraft logistics, integration, configuration management, and engineering” (ALICE) services. The seller would provide personnel to work at a buyer’s location, and the buyer would direct all work and “establish work hours consistent with meeting the mission at each contract location.” The RFP provided an estimated level of effort, and offerors completed a pricing model spreadsheet.

Proposals were to be evaluated on mission suitability, past performance, and cost/price. The mission suitability and past performance factors were approximately equal in importance, and each was more important than cost/price. The purpose of the mission suitability factor was to determine the offeror’s ability to provide the required personnel at the required work hours to fulfill the contract need. It included several subfactors: management approach, overall management approach, staffing approach, and contract phase-in approach.

Offeror C argued that the buyer unfairly assessed a management approach weakness for failing to show a plan for complying with required work schedules and break times, failing to consider that the buyer establishes work hours consistent with mission needs, and failing to consider the buyer’s intention to have night shift work on Sundays. Offeror C’s proposal had discussed its approach to managing scheduling and breaks and stated that it would comply with collective bargaining agreement requirements. The buyer nevertheless judged the approach inadequate because it did not explain how Offeror C would enforce worker compliance, comparing the plan to a highway speed-limit sign that does not ensure motorists will not speed. GAO found that the RFP required offerors to explain their approaches to ensuring flexible scheduling and required breaks, but did not reasonably disclose that offerors also had to propose an enforcement mechanism.

Question:

In this scenario, how could the buyer have made its evaluation process more defensible to avoid a protest?

Options:

A.

Giving equal weight to all three evaluation factors.

B.

Documenting reasons beyond point values for determining the competitive range.

C.

Notifying Offeror C during the evaluation process that its proposed schedule process was insufficient.

D.

Requiring each member of the evaluation team to perform their initial evaluations of the proposals collaboratively.

Buy Now
Questions 41

Which of the following refers to a method for measuring project performance that compares the amount of work that was planned with what was actually accomplished to determine if cost and schedule performance went as planned?

Options:

A.

Earned Value

B.

Baseline

C.

Estimate at Completion (EAC)

D.

Work Breakdown Structure (WBS)

Buy Now
Questions 42

A(n) __________ contract is created when the parties state their intentions either verbally or in writing.

Options:

A.

guaranteed

B.

express

C.

quasi

D.

requirements

Buy Now
Questions 43

__________ are final documents and do not evolve.

Options:

A.

Archives

B.

Records

C.

Quality Control Plans

D.

Contracts

Buy Now
Questions 44

Reasonable costs are those costs that a prudent seller, under the constraint of competition, would recognize as __________.

Options:

A.

substantial

B.

discounted

C.

profitable

D.

justifiable

Buy Now
Questions 45

Subcontractors do not have a right to file a contract claim directly with the government due to __________.

Options:

A.

conflict of interest

B.

lack of privity of contract

C.

separation of buying and selling

D.

facilitating clauses

Buy Now
Questions 46

What contract type requires the buyer to order and the contractor to furnish at least a stated minimum quantity of supplies?

Options:

A.

Fixed-price redeterminable

B.

Requirements

C.

Firm-fixed-price (FFF)

D.

Indefinite quantity

Buy Now
Questions 47

Which of the following solicitation tools is normally used for two-step sealed bidding?

Options:

A.

Invitation for bids (IFB)

B.

Request for proposal (RFP)

C.

Request for technical proposals (RFTP)

D.

Request for quotations (RFQ)

Buy Now
Questions 48

An essential element of contract administration is establishing and maintaining effective communications. What is the primary method for achieving a clear and mutual understanding of contract requirements and identifying potential problems?

Options:

A.

Conducting a post-award kick-off meeting

B.

Avoiding organizational conflicts of interest (OCIs)

C.

Analyzing the product/service procurement history

D.

Establishing performance standards

Buy Now
Questions 49

__________ are those criteria, usually stated in a contract and/or statement of work, that include deliverables, performance requirements, and essential conditions which must be met to complete project deliverables and be accepted.

Options:

A.

Performance standards

B.

Deliverable milestones

C.

Earned value methods

D.

Acceptance criteria

Buy Now
Questions 50

An __________ contract is one in which the contract terms are stated in either written or spoken words and are assented to by both parties.

Options:

A.

quasi

B.

express

C.

implied

D.

unilateral

Buy Now
Questions 51

The seller is responsible for risk of loss or damage occurring before delivery to the buyer in which of the following?

Options:

A.

Free on board origin (FOB origin)

B.

Report of shipment (REPSHIP)

C.

Government transportation system (GTS)

D.

Free on board destination (FOB destination)

Buy Now
Exam Code: CPCM
Exam Name: Certified Professional Contract Manager
Last Update: Mar 21, 2026
Questions: 180

PDF + Testing Engine

$63.52  $181.49

Testing Engine

$50.57  $144.49
buy now CPCM testing engine

PDF (Q&A)

$43.57  $124.49
buy now CPCM pdf