DCDC-003.1 BICSI Data Center Design Consultant - DCDC Questions and Answers

Questions 4

What is the recommended headroom for overhead cable tray?

Options:

A.

3 "

B.

6 "

C.

9 "

D.

12 "

Buy Now
Questions 5

What is the distance from the bottom of the access floor to the bottom of the cable tray?

Options:

A.

6 inches

B.

7 inches

C.

8 inches

D.

9 inches

E.

10 inches

Buy Now
Questions 6

what additional fuel filtering is required for generators in class F3 and F4 facilities

Options:

A.

two-stage, spin-on-type fuel filters

B.

four stage, paper-type fuel filters

C.

five stage, mesh type fuel filters

D.

three stage, spin-on-type fuel filters

Buy Now
Questions 7

What is the ASHRAE min and max dew point

Options:

A.

30F and 59F

B.

42F and 65F

C.

40F and 55F

D.

-10°F to +85°F

Buy Now
Questions 8

what is the ASHRAE recommended operational temperature.

Options:

A.

Minimum =54 degrees[F]/12 degrees[C]

Maximum=88 degrees [F]/31degrees[C]

B.

Minimum =64 degrees[F]/18 degrees[C]

Maximum=80 .6degrees [26 .9] < 30 del= ' ' > [C]

C.

Minimum < =50 degree[A]

Maximum = > 200Degrees[B]

D.

Maximum < =33 Degree[XEIYCPJZDKLTWGBNMFUAHSRQV][/33] [64]= ' ' >

Minimum > =18Degree[KOVBYPZXWMFGUTANLHQSRDCJE] < /18 >

Buy Now
Questions 9

What is the recommended range for the high temperature in a data center according to NEB?

Options:

A.

80 degrees

B.

75 degrees

C.

85 degrees

D.

70 degrees

E.

90 degrees

Buy Now
Questions 10

What is the recommended level of redundancy for a critical power system in a Tier III data center?

Options:

A.

N

B.

N+1

C.

2N

D.

2N+1

E.

3N

Buy Now
Questions 11

What is the high temperature that must be maintained in a data center according to TIA-942?

Options:

A.

70 degrees

B.

75 degrees

C.

77 degrees

D.

80 degrees

E.

85 degrees

Buy Now
Questions 12

What IBC occupancy category are data centers placed in if they don ' t have to operate after an earthquake?

Options:

A.

Category1

B.

Category2

C.

Category3

D.

Category 4

Buy Now
Questions 13

What is the recommended placement of electrical distribution sub systems

Options:

A.

install in dedicated electrical rooms, or, locate outside the computer room with fire rated wall

B.

install within the computer room space on raised floor

C.

install within server racks

D.

none of the above

Buy Now
Questions 14

What Enhanced Fujita Scale level is commonly used in wind loading calculations?

Options:

A.

EF1,73-112 mph

B.

EF2,113-157mph

C.

EF3,158-206mph

D.

EF4,207-260 mph

Buy Now
Questions 15

According to NEB, what is the recommended rate of temperature change per hour in a data center?

Options:

A.

36 degrees

B.

45 degrees

C.

54 degrees

D.

63 degrees

E.

72 degrees

Buy Now
Questions 16

what is the second preference regarding utility service

Options:

A.

At least four circuits each from different distribution stations but fed via common feeders B. Two balanced feeds with different voltages derived from a single distribution station

B.

One balanced feeder coordinated with upstream backup feed D. At least One Circuit from two Separate Substations and Different Voltage Levels

Buy Now
Questions 17

What types of electrical equipment is typically located inside the computer room

Options:

A.

power distribution units, not power distribution equipment, remote power panels, and power strips

B.

transformers only

C.

Uninterrupted Power Supply (UPS) only

D.

Circuit Breakers only

Buy Now
Questions 18

According to TIA-942, what is the low temperature that must be maintained in a data center?

Options:

A.

60 degrees

B.

65 degrees

C.

68 degrees

D.

70 degrees

E.

75 degrees

Buy Now
Questions 19

What is the United States Average Power Utility Outage Annually And What Is The Average Repair Time?

Options:

A.

2.5 outages annually, with average repair time of approximately 7 hours

B.

1 outage annually, with average repair time of approximately eight hours

C.

1.86 outages annually, with average repair time of four hours

D.

Three outages annually, with an unknown average repair time

Buy Now
Questions 20

What is the highest allowable elevation for a data center site?

Options:

A.

2,500 ft

B.

5,000 ft

C.

7,500 ft

D.

10,000 ft

E.

12,500 ft

Buy Now
Questions 21

What is the minimum aisle width?

Options:

A.

3 feet

B.

The width shouldn ' t exceed more than half room length

C.

Arm span distance between technicians

D.

Twice server cabinet depth

Buy Now
Questions 22

What is the recommended range for the high temperature in a data center according to ASHRAE?

Options:

A.

80.6 degrees

B.

75 degrees

C.

85 degrees

D.

70 degrees

E.

90 degrees

Buy Now
Questions 23

what is the recommended height, of the support room pathway

Options:

A.

9 ft

B.

8ft

C.

7ft

D.

6ft

Buy Now
Questions 24

What is the recommended amount of fuel supply needing to be available to a class F3 data center?

Options:

A.

24 hours

B.

48 hours

C.

72 hours

D.

96 hours

Buy Now
Questions 25

What are the 3 different methods for grounding racks in a computer room?

Options:

A.

Ground bus, direct connections, bond to rack

B.

Ground conductor, surge protection, equipment rack

C.

Copper cable, conduit, flexible connector

D.

AC power, DC power, Ethernet

Buy Now
Questions 26

Why do larger data centers require more H DAs?

Options:

A.

to ensure maximum horizontal cable lengths are not exceeded and to avoid cable congestion

B.

to reduce energy consumption and carbon footprint

C.

to increase server processing speed by minimizing latency

D.

to provide redundancy and failover mechanisms

Buy Now
Questions 27

What level should the battery room be on?

Options:

A.

Grade Level

B.

Upper floor

C.

Lower Floor

D.

None

E.

All

Buy Now
Questions 28

What is the flame index spread rating required for all materials hosted in a containment system?

Options:

A.

0

B.

10

C.

25

D.

50

Buy Now
Questions 29

What IBC occupancy category are data centers placed in?

Options:

A.

Category 3

B.

Category 4

C.

Category5

D.

category6

Buy Now
Questions 30

What room should have its own dedicated air handling system apart from the computer room?

Options:

A.

Electrical Room

B.

Break Room

C.

Printer Room

D.

Storage Room

E.

Telecommunications Room

Buy Now
Questions 31

where should printers be located

Options:

A.

beside high traffic areas

B.

near equipment that has active air flow to cool them down

C.

in a dedicated print room with dedicated air handling system

D.

placed outdoor, away from building facilities

Buy Now
Questions 32

What is the minimum raised floor height?

Options:

A.

6 "

B.

12 "

C.

18 "

D.

24 "

Buy Now
Questions 33

What is an automatic static transfer switch used for?

Options:

A.

Switching between multiple utility power sources

B.

Switching between utility and generator power sources

C.

Switching between different generator power sources

D.

Switching between AC and DC power sources

Buy Now
Questions 34

What is the smoke development rating required for all materials hosted in a containment system?

Options:

A.

150

B.

300

C.

450

D.

600

Buy Now
Questions 35

what are 2 typical printer manufacturer environmental criteria?

Options:

A.

humidity and temperature

B.

lighting and sound level

C.

radioactivity measurement and electromagnetic interference

D.

electrical conductivity and soil contamination

Buy Now
Questions 36

what is minimum recommended space for secured storage area?

Options:

A.

100 square feet

B 240 square feet

B.

250 square feet

C.

280 square feet

D.

None of above

Buy Now
Questions 37

what is the minimum thickness of an elevated floor topping over metal flutes?

Options:

A.

2 inchmhes

B, 3 Inches

B.

4 Inches

C.

1,5Inchessa.i:sab#v=onepage & q & f=.htm & ebrary= & qp=end+user+bicsi+f2590b67561c7dcea431ec3e26ae44ef+07000000+dcdc & s.cvsr=sidx%3D45 & pgreso ' & page=29

Buy Now
Questions 38

what is typical entrance room power requirement?

Options:

A.

500, to 1500 watts per access provider

B.

More than 2000 KW

C.

exactly or less than 300KW

D.

More than about Million watts

Buy Now
Questions 39

What is the typical air delivery temperature from a CRAC unit?

Options:

A.

20-25 degrees Celsius

B.

15-18 degrees Celsius

C.

10-13 degrees Celsius

D.

13-16 degrees Celsius

Buy Now
Questions 40

What are two functions of telecommunications entrance room?

Options:

A.

to provide a secure area where access provider outdoor cable can be converted, to indoor cable, and, house access provider owned equipment

B.

to house all company-wide communication devices

C.

to store backup telecommunication devices

D.

none of these

Buy Now
Questions 41

What is the acceptable rate of temperature change per hour in a data center according to TIA-942?

Options:

A.

5 degrees

B.

7 degrees

C.

9 degrees

D.

12 degrees

E.

15 degrees

Buy Now
Questions 42

What is the recommended floor loading capacity for a data center?

Options:

A.

1000 lbs per sq. ft.

B.

1250 lbs per sq. ft.

C.

1500 lbs per sq. ft.

D.

1750 lbs per sq. ft.

E.

2000 lbs per sq. ft.

Buy Now
Questions 43

What is the third preference regarding electricity supply?

Options:

A.

At Least Two Circuits From Same Power Grid But Different Substations And Separate Paths

B.

One Balanced Feeder Coordinated With Upstream Backup Feed

C.

One Circuit From Single Sub Station Fed Via Additional Path from Alternate Power Grid

D.

Two Balanced Feeds With Same Voltage Derived From A Single Distribution Station

Buy Now
Questions 44

What is the minimum access floor to ceiling height recommended?

Options:

A.

8 feet minimum

B.

9 feet minimum

C.

10 feet minimum

D.

11ft minimum

Buy Now
Questions 45

What are the minimum separation distances for electrical and telecom services pathways to maintain from their primary and redundant feeds?

Options:

A.

5 meters (16 feet)

B.

10 meters (33 feet)

C.

15 meters (49 feet)

D.

20 meters (66 feet)

Buy Now
Questions 46

What are the recommended computer room delivery pathway dimensions

Options:

A.

10 feet long by 4 feet deep by 8 feet high

B.

20 feet long by 6 feet deep by 10 feet high

C.

15 feet long by 5 feet deep by7feet high

D.

14 feet long and has a depth dependent on rack layout.

Buy Now
Questions 47

What is the preferred location of the power distribution unit?

Options:

A.

a service gallery outside the computer room, if the A H J and feeder distances allow

B.

under each server rack

C.

in an unused area of another floor

D.

inside a ventilation duct

Buy Now
Exam Code: DCDC-003.1
Exam Name: BICSI Data Center Design Consultant - DCDC
Last Update: Apr 30, 2026
Questions: 158

PDF + Testing Engine

$63.52  $181.49

Testing Engine

$50.57  $144.49
buy now DCDC-003.1 testing engine

PDF (Q&A)

$43.57  $124.49
buy now DCDC-003.1 pdf