If you created a project yesterday and want to assign it today to a program, you ...
When creating a Route, if Approve is selected in the Action field, the task assignee must:
When viewing a dashboard and the slip date is 0 to 4 days later than the estimated end date, the slip date will be:
If the “Requires Owner Review” option is chosen for a task in a route, then an email will be sent to the:
The WBS for a Project template is similar to the WBS for a Project EXCEPT a template WBS has no:
When you click on the Program Name link in the search window, you will view a list of all the:
Which dependency code do you assign if the selected task CANNOT start until the current task starts?
If you are a Program Manager and have hundreds of programs that you are managing, what feature would you use to organize your projects into a more manageable display?
Looking at the below image, when would you expect to work on the Create Instructor Guide task (WBS 2.4) by looking at the Dependency column?