L5M8 Project and Change Management Questions and Answers

Questions 4

Which of the following is aninternational standard for Social Responsibility?

Options:

A.

ISO 26000

B.

ISO 27000

C.

Social Value Act

D.

Ethical Trading Initiative

Buy Now
Questions 5

Zumaya is a Procurement Manager and has recently introduced a new e-sourcing tool. She is evaluating the change against the metrics identified at the start and will continue monitoring as staff use the system. What type of evaluation is this?

Options:

A.

return on investment evaluation

B.

procurement evaluation

C.

process evaluation

D.

summative evaluation

Buy Now
Questions 6

In a large construction project with many stakeholders, which groups would you expect to see represented on theProject Board?Select TWO

Options:

A.

Senior Employees

B.

Senior Users

C.

Senior Suppliers

D.

Senior Buyers

Buy Now
Questions 7

What is meant by “resource levelling”?

Options:

A.

employing the same number of people on each concurrent project

B.

employing a set number of people on a project from start to finish

C.

back-loading resources to a project

D.

adjusting project resources based on demand and supply

Buy Now
Questions 8

A project is comprised of multiple programmes and encapsulates broad organisational and technical objectives. Is this sentence TRUE?

Options:

A.

yes – the project manager is focused on the delivery of specific project goals

B.

yes – project managers have specialised skills

C.

no – programmes are composed of multiple projects

D.

no – project managers have a more holistic view than programme managers

Buy Now
Questions 9

Michael is the head of the Steering Committee at ABC Consultancy and must allocate resources to several projects. One project is suffering delays due to lack of staff. Should Michael reallocate resources to this project?

Options:

A.

yes – resources should always be allocated depending on timescales

B.

yes – all resources should be diverted to this project until it is complete

C.

no – this may increase competition and animosity between project teams

D.

no – delays are always unavoidable in project management

Buy Now
Questions 10

Which of the following is a benefit for an organisation of joining a consortium?Select TWO

Options:

A.

it creates a new legal entity, thus reducing risk for the organisation

B.

it requires no capital outlay

C.

members are able to win bigger contracts that wouldn’t otherwise have been available

D.

it may result in additional risk of exposure to liability

Buy Now
Questions 11

A florist is introducing a new electronic ordering system that will reduce staff numbers. The Managing Director is anticipating staff reactions. Which of the following stages of theChange Cyclewill staff likely experience first?Select TWO

Options:

A.

acceptance

B.

discovery

C.

loss

D.

discomfort

E.

doubt

Buy Now
Questions 12

Which of the following is a type ofProject Responsibility Chart?

Options:

A.

SWOT

B.

Gantt Chart

C.

PRINCE2

D.

RACI

Buy Now
Questions 13

Which of the following is an example of an exogenous disruption that stimulates the requirement for change within an organisation?

Options:

A.

company restructure

B.

pressure to increase revenue

C.

increase in tax rate

D.

change of management

Buy Now
Questions 14

At Playground Incorporated there is a particular project management structure in which a traditional hierarchical structure is used. When a project requires multiple departments, each department completes its aspect and then passes it along to the next. There is no need for an overarching Project Manager. What type of structure is this?

Options:

A.

functional

B.

projectized

C.

matrix

D.

downstream

Buy Now
Questions 15

Three companies have joined together to create anew legal entityto explore a new opportunity outside of their core businesses. What is the name given to this type of arrangement?

Options:

A.

joint venture

B.

partnership

C.

consortium

D.

collaboration

Buy Now
Questions 16

What information does aCritical Path scheduleprovide to the project team?Select TWO

Options:

A.

where the project is up to in terms of delivery

B.

a realistic duration of the project

C.

the longest and shortest possible durations of the project

D.

why the project is delayed

Buy Now
Questions 17

Which of the following is arisk in the supply chainwhich could affect the delivery of a project?

Options:

A.

project exceeds budget

B.

late delivery of items leading to delays

C.

vital project team members leave the organisation

D.

project scope increase

Buy Now
Questions 18

The objectives of an organisation are the top-level “wants” of an organisation and are usually non-tangible and long term. Is this correct?

Options:

A.

yes – objectives are set at the business strategy level of an organisation

B.

yes – objectives are set by each department within an organisation

C.

no – objectives are short term, specific and define what a project or department needs to achieve its goals

D.

no – objectives are a wish list of things to be achieved

Buy Now
Questions 19

Ibrahim is planning to implement a new project at his company. He is at the strategy phase and has decided to use aForce Field Analysisto determine whether the planned long-term change he wishes to implement is viable. What is identified within the Force Field Analysis?

Options:

A.

risks and opportunities

B.

pros and cons for completing the project

C.

stakeholders who are for and against the project

D.

different ways of implementing the project

Buy Now
Questions 20

When completing arisk assessment, which TWO characteristics of a risk should bequantitativelyexamined?

Options:

A.

likelihood of risk

B.

type of risk

C.

risk owner

D.

severity of risk

Buy Now
Questions 21

In what way is a Work Breakdown Structure (WBS) useful to a Project Manager?

Options:

A.

controls costs

B.

identifies relevant stakeholders

C.

ensures the project sticks to timelines

D.

defines what the project will accomplish

Buy Now
Questions 22

In Lewin's 3 stage Change Model, which is the first stage?

Options:

A.

unfreeze

B.

loss

C.

denial

D.

disrupt

Buy Now
Questions 23

Lucy has just been told about a change at her company that will affect the way she conducts her job. She is currently feeling sceptical about whether this change is a good idea. According to theChange Cycle, which of the following stages will Lucy experience next?

Options:

A.

denial

B.

depression

C.

discomfort

D.

discovery

Buy Now
Questions 24

Which of the following characteristics of a stakeholder should be considered when conducting a stakeholder analysis for a project?Select THREE

Options:

A.

Interest

B.

Impact

C.

Needs

D.

Money

E.

Status

Buy Now
Questions 25

In aGantt chart, a project is broken down into what?

Options:

A.

activities and who is responsible for each

B.

project risks and mitigations

C.

time periods and what activity is completed when

D.

budgets and budget owners

Buy Now
Questions 26

Yes Ltd is a consultancy organisation running many projects simultaneously. Fiona, the CEO, claims that all projects should use project management software. Is this correct?

Options:

A.

yes – software will ensure projects are delivered to timescales and budgets

B.

yes – all projects require the use of software to track data

C.

no – the use of software may not be required for smaller projects

D.

no – software should never be used as a project management tool

Buy Now
Exam Code: L5M8
Exam Name: Project and Change Management
Last Update: Dec 8, 2025
Questions: 88

PDF + Testing Engine

$63.52  $181.49

Testing Engine

$50.57  $144.49
buy now L5M8 testing engine

PDF (Q&A)

$43.57  $124.49
buy now L5M8 pdf