RCDDv14 BICSI Registered Communications Distribution Designer – RCDDv14 Questions and Answers
The marketing department of a firm has tasked the organization to design a structured cabling system allowing them to support either 10G6aseT or HDBASE-T. The budget requires that only one cable type be installed and that it be MINIMUM compliant. Of the following choices, what is the choice with the MINIMUM solution/solutions for the client?
One interior TTY must be provided at locations defined as public accommodations with ________ or more pay telephones.
A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase Tracking and reporting of actual benefits realized is one part of the review
What is the other part of the review " ?
A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.
Which of the following deliverables captures these items?
An ICT distribution designer is reviewing a client ' s site information (spaces and pathways) to determine network technology and equipment selection. This is referred to as a___________design process
A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list During the final review of the RFPs the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company policies, the program manager is concerned about a conflict of interest.
What should the program manager do?
In which of the following design phases does the ICT distribution designer perform coordination with stakeholders and other disciplines (e.g.. mechanical, architectural, electrical) to ensure that the design is constructive and that any conflicts are resolved early in the process?
One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set, if the tolerance range is too narrow on a program what effect will multiple minor changes have on the program?
After new private equity owners acquire an enterprise, they want to improve its value by reducing costs A new program will restructure the enterprise, including an aging headquarters campus where the main data center is housed A strategic component project presents significant risk to organizational objectives due to Its complexity and dependencies on external parties. After a series of board meetings, the enterprise ' s investment committee approves a budget to Implement this component project, which will move the old data center from the aging headquarters campus into a new colocation facility Implementation of this component project may now begin, but is already one month behind schedule The program manager now perceives significantly more risk to the larger program due to this delay.
What should the program manager do to address this risk with the program sponsor and governance board?
The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B.
This is an example of which of the following?
A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project which could impact other components if delays occur. The program manager ' s attempts to reach the stakeholder via email also fail.
What should the program manager do next?
The options for termination an unshielded twisted pair cable for a video surveillance camera at the camera end are an 8-pin 8 conductor outlet and
Which two of the following are ADVANTAGES of aerial pathways? (Select two options.)
A program receives initial approval from the selection committee to proceed with the program development. What should the program manager do next " ?
Communicating a project ' s design and technical specifications to the client and stakeholders is part of the ___________of the project.
A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete The program manager can select a design-build option to optimize the construction schedule to 1 5 years However heavy demand for steel is causing price increases and delivery delays. II this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1 25 years
What is the expected time of delivery?
Which of the following is the process of limiting fire and smoke using fire-resistive barriers?
In preparation for the development and submission of the program master schedule to a client, the program manager meets with (he component project manager and master program scheduler to discuss the work breakdown structure (WBS) During the meeting, the master scheduler indicates that the master program schedule should include which of the following?
A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared. During stakeholder engagement planning the program manager should consider which of the following stakeholder aspects?
Which two of the following documents MUST be submitted by the communication ' s project contractor for review and approval? {Select two options.)
An organization must accelerate a product to market. The program manager completes the preliminary program slaps and holds a kick-off meeting Project managers submit their preliminary schedules for review
What should the program manager do next?
A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity ' ?
When estimating an ICT distribution designer project timeline schedule based on the scope of work which two scheduling methods use network diagrams lo integrate logical activities and identify critical paths on the project? (Select two options.)
A program is near completion and the benefits will be delivered shortly. The program manager prepares to initiate program closeout activities to release the program resources.
Before initiating closeout and releasing the resources, what should the program manager do?
A company initiates a program to reorganize its sales and production departments. Three production departments are located at the three production plants next to the company ' s headquarters Five regional sales departments are located at different locations around the world.
At this stage of the program, what is the first step?
The program manager must define the program and understand the organization ' s target market and customer needs. What should the program manager do first?
Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?
The program manager takes over a poorly performing program After a review of the documentation and interviews with the program sponsor, stakeholders and program constituents, the program manager realizes that the program is not aligned with the corporate/organizational goals. The program manager must realign the constituent protects and components to meet the program ' s needs
What action should the program manager take to realign the program?
The program manager has a global program with live component projects. The program sponsor wants the management plans, processes/procedures and technology to be uniform across the program. The requirements will create issues and result in increased costs. The program sponsor is new and has imposed these new requirements six months into a three-year program.
What should the program manager do next?
An ICT distribution designer is representing a client during a project execution. What is the designer ' s role in the Vendor and Contractor Coordination?
A software development program will launch iterative versions of new software called Alpha over two years Following that, a program will be released to the program team and developers to create new software called Beta While the program manager prepares the program closure plan tor Alpha, the program sponsor expresses concern about its support after program closure.
What should the program manager do as part of Alpha ' s program closure plan?
A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting. What should the program manager do to ensure that the key stakeholder is familiar with the program ' s benefits and supports the program ' ?
A company ' s marketing department Tails an internal compliance audit To comply with the auditor ' s remediation plan the legal department mandates that a content management system (CMS) be implemented After initiating the program for CMS implementation the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.
What should the program manager do to ensure the success of the program?
Which two of the following items MUST be included in a detailed SoW? (Select two options.)
During the program execution stage the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours. What should the program manager do?
AI the beginning of the second year of a five-year strategic cycle, the program management team attends a checkpoint session to review the state of the company ' s strategy During the previous year, the company needed to comply with new government regulations that impacted this strategy.
Based on this information, what should the program manager do?
Who prepares the submittals that are reviewed and approved to ensure that the clients design criteria is met in regards to material selection?
What would prevent a program manager from completing program closure once a program has been completed?
A program manager building the world ' s largest cruise ship is resolving the conflict between the two main sponsors who cannot agree on the number of food and beverage outlets to have onboard. What should the program manager do?
A program is developing a next-gene ration product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet
What activity should the program manager perform next?
A regional finance program is impacted by a new currency regulation issued by a country in the region. The new regulation requires changes to the financial statements of that country ' s branches by the end of the fiscal year Failing to comply with the regulation may result in fines and/or closure of the branches. A branch general manager immediately meets with the program manager to select and secure a local fiscal expert to support the regulation as these types of resources are in high demand. There is a high risk that the changes will not be completed on time if the resource is not secured
What should the program manager do to address the risk?
In the last year, all program phase gate reviews received excellent feedback and exceeded stakeholder expectations recently, the customer decides that there is no need to continue phase gate reviews.
What should the program manager do next?
During program execution, a program manager receives feedback from an executive sponsor (hat some program stakeholders may not understand the intended benefits of the program. Which will provide the greatest value to clarify stakeholder perceptions?
A program manager initiates a developmental program. Significant resources and funding are required (or early activities until the program cost and budget estimates are complete
What should the program manager do to understand the financial environment?
Coupling with electrical circuits can create inductive interference to telecommunications facilities. Which of the following can decrease the coupling effect?
An Ethernet passive optical network (EPON) uses an aggregation device called an optical line terminal (OLT). An OLT can support a MINIMUM of______subscribers per port using a passive optical splitter
The chief executive officer reminds a program manager that a program must deliver a 30% reduction in customer complaints by the end of the year. Where is this expectation documented1?
After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.
What should the program manager do next?
Close out documentation is initially discussed in which of the following meetings?
A company is building a global monitoring network in 40 countries. The program completes the planning phase and a review is conducted of the program components ' strategic alignment with the intended program and company goals. The review identifies issues that should be resolved to improve program progress. One of the issues identified is the lack of incorporation of both software and configuration management tools
Which of the following must be addressed?
The program selection committee presents several programs for approval:

Which program was selected based solely on a three-year return on investment?
The program manager defines the program objectives, requirements and develops a high-level road map. To ensure program alignment with the enterprise strategic plan the program manager should work with which of the following?
For the MAXIMUM flexibility of a cabling system in a hierarchical star topology, ALL backbone cables and links to FR ' s should be terminated at the
A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues.
What tool should be used to trigger a planned response when receiving lower than expected results ' ?
Key performance indicators
B. Benefits management plan
C. Communications management plan
D. Ishikawa diagram
A multiyear program is ready to conclude. It has achieved all business objectives and is delivering its intended benefits. However the program sponsor is not willing to sign the formal program closure acceptance document and the program continues to incur operational costs.
What should the program manager do next?
The type of apparatus housed in TRs varies greatly in size, purpose and function. Which two of the following active equipment is included? (Select two options.)
A program manager has four projects pending approval Senior management asks the program manager to identity a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision.
Which project should the program manager select to be cancelled?

An ICT distribution designer is preparing a price quote for a building design with multiple floors originally sized at 40.000 ft (3716 m2). While the designer is preparing the quote, the structural engineer indicates the building has been increased in size to accommodate an additional 40,000 ft2 (3716 m3) per floor. The designer ' s recommendation to the engineer will be to increase the slot area by_____for each additional 40,000 ft3 (3716 m2)
A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment
Where should the program manager document this?
A program completes all component projects and all identified benefits are being delivered However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters
To ensure the realization of long-term benefits what should the program manager use?
You are designing distribution for a seven unit townhouse with in slab conduits. What is the MINIMUM number of 27 mm (1 in) rigid PVC Type 2 or metallic conduit that is required to satisfy distribution to each unit?
A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated only 60 percent has been achieved
What should the program manager do to ensure benefits realization?
In a RFI, an ICT distribution designer instructs the contractor to test all the fibers In a PON Installation. Which of the following testing requirements does the designer include?
A component is scheduled to close at the end of the week. What should the program manager verity prior to allowing the component to close?
When preparing an upfront cost estimate, the ICT distribution designer MUST consider which two of the following fees? (Select two options.)
Company A recently signed a contract with a strategic business partner, Company B, to jointly roll out a new technology Company B is excited about the joint marketing opportunity Company A ' s component Quality Assurance team has expressed concerns to you the program manager, Ural the product is being rolled out prematurely and has identified potential issues with backend support systems. QA, however, assures you that a manual work around is possible, but not ideal Company B requests an enhancement to the new product. In a meeting with Company B, you determine that additional funding will be required and resources allocated and scheduled
What is your MOST appropriate next step?
A program manager takes over a global program from another program manager. Upon arriving on-site, the program manager immediately sees that stakeholders are upset because of a lack of updates and communications about the program.
What should the program manager do first?
During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized the program manager was asked to transition the program into operations.
At this stage, what is expected during the post-review session organized by the program manager?
In a PTP network using optical fiber, the ________ is responsible for media conversions from the optical fiber to the balanced twisted pair network within the residence.
A non-profit organization launched a program to reduce its dependence on regularly decreasing government funding sources. This program ' s goal was (o raise 50 percent of its operating expenses by selling its services to the for-profit sector. After three years, the goal was reached, deemed complete, and transitioned to operations. Eighteen months later, the organization discovers that its dependence on government funds has now increased to 80 percent, even though its operating budget has largely stayed the same
What should the program manager have done to avoid the issue of program benefits being unrealized after more than a year of implementation?
When planning a telecommunication termination area, what is the estimated space needed to terminate 144 strands of optical fiber?
Which two of the following are ADVANTAGES of underground conduit systems? (Select two options.)
A company is releasing a new product geared toward a specific geographic area. The program manager has received the program objectives and developed the program roadmap which consists of six program components Approval from the program governance board has been obtained.
What is the program manager ' s next step?
A software company ' s program manager is conducting closing procedures for a program. At the last steering committee meeting, realized benefits were presented to the program governance board.
What should the program manager do next?
Which two of the following types of metallic conduit REQUIRE threaded couplings? (Select two options.)
An unforeseen geopolitical risk impacts a program to establish a company ' s operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately what appeared to be a significant risk resulted in a negligible risk.
What should the program manager recommend to stakeholders for future similar situations?
Which of the following two items are examples of items associated with a submittal? (Select two options.)
A program manager assigns project managers lo five component projects and continues to develop the program team. Which of the following represents the program manager ' s strategy?
What category/class of cabling does BICSI recommend for the MINIMUM performance level of horizontal balanced twisted-pair cabling?
Exhibit:

A pay telephone using coins needs to be installed in a public area. In the specifications, it is required that the telephone shall meet the ADA (American with Disabilities Act) requirement for front reach using a wheelchair. What will be the maximum reachable height or the value of " X " ?


