Questions 4

A company uses separate finished good item numbers for size variations of the same product.

The company wants to minimize the number of variously-sized items that are created.

You need to perform the setup to allow variants in size to the product master.

Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

MB-320 Question 4

Options:

Buy Now
Questions 5

You need to set up the system to calculate the overhead rates automatically for production.

Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

MB-320 Question 5

Options:

Buy Now
Questions 6

You need to configure each item for plastic manufacturing.

Which production types should you use? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.

MB-320 Question 6

Options:

Buy Now
Questions 7

A company produces and distributes seafood to supermarkets. During the manufacturing process, raw seafood is purchased, cleaned, and packaged into various-sized boxes. Each box may have a different weight.

Product is sold by the box and priced by the pound.

You need to ensure that you can perform transactions at the box level and record the net weight of goods shipped to a customer.

Solution: Set up a unit sequence group on the item for both pounds and boxes, then set a standard unit conversion for the product from box to pounds.

Does the solution meet the goal?

Options:

A.

Yes

B.

No

Buy Now
Questions 8

You need to configure the system for plastic operations.

Which two parts should be manually reported as finished? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Options:

A.

unmachined plastic pieces

B.

mold tooling

C.

machined plastic pieces

D.

excess plastic

Buy Now
Questions 9

You need to set up the metal production route and BOM.

Which three actions should you perform? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Set the operation route type as Standard.

B.

Set the input warehouse on the resource to the vendor warehouse.

C.

Set the operation route type as Vendor.

D.

Set all BOM lines warehouse to the production warehouse.

E.

Set all the BOM lines to resource consumption.

Buy Now
Questions 10

You need to modify the production order defaults for the manufacturing execution production order Start process.

What should you do? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

MB-320 Question 10

Options:

Buy Now
Questions 11

You need to configure system attributes.

Which attribute types should you use? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

MB-320 Question 11

Options:

Buy Now
Questions 12

You need to set up the configuration model to price the motorcycles correctly. What should you do?

Options:

A.

Set Order type in price model to Sales Order and Pricing method in Version to Attribute based

B.

Set Order type in price model to Sales Order and Pricing method in Version to Cost based.

C.

Set Order type in price model to Sales Quotation and Pricing method in Version to Attribute based.

D.

Set Order type in price model to Sales Quotation and Pricing method in Version to Cost based

Buy Now
Questions 13

A customer produces light projection toys for holiday decorations throughout the year. Vendors have

negotiated rebate agreements as a condition of their contact. The contract also contains the visual templates

required for the customer to use in a season.

Vendor rebate agreements must only be applied if the following requirements are met:

Units of measure for deliverables are the same unit of measure as on the agreement

The agreement is valid as of the date a purchase order is generated

You need to configure the vendor rebate agreements.

What should you do?

Options:

A.

Set the Rebate line break type field value to Amount

B.

Set the Rebate line break type field value to Quantity

C.

Set the Cumulative purchase by field value to the beginning of the season date

D.

Set the Unit of measure rebate option field value to Exact match

Buy Now
Questions 14

You need to configure scheduling for each production area.

Which scheduling options should you use? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.

MB-320 Question 14

Options:

Buy Now
Questions 15

You need to set up the correct production solution for the assembly area. Which solution should you implement?

Options:

A.

Standard warehousing with Manufacturing execution

B.

Standard warehousing for all transactions

C.

Advanced warehousing for all transactions

D.

Advanced warehousing with Manufacturing execution

Buy Now
Questions 16

You need to set up the state control for sales of motorcycles.

Which two actions should you perform? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Create an inclusive restricted product list for United States. Do not add the motorcycle part to the list.

B.

Create an inclusive restricted product list for United States and add the motorcycle part to the list.

C.

Create an exclusive restricted product list for California and add the motorcycle part to the list.

D.

Create an exclusive restricted product list for Missouri and add the motorcycle part to the list.

Buy Now
Questions 17

You need to create the constraint for the ML seat selection.

Which expression constraint should you use?

Options:

A.

Implies[Trim==Legend,Seat==ML]

B.

Seat!=ML

C.

[Trim==Legend|Seat==ML]

D.

Implies[Seat==ML,Trim==Legend]

Buy Now
Questions 18

You need to set up the chocolate items.

Which values should you select? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

MB-320 Question 18

Options:

Buy Now
Questions 19

You need to resolve the issue for UserG.

What should you do? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

MB-320 Question 19

Options:

Buy Now
Questions 20

You need to calculate estimated consumption of ingredients for liquid cleaning solution.

What is the consumption? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.

MB-320 Question 20

Options:

Buy Now
Questions 21

You need to resolve the production manager issue.

How should you configure manufacturing execution? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.

MB-320 Question 21

Options:

Buy Now
Questions 22

You need to configure production control parameters for liquid cleaning solution manufacturing.

What are two possible ways to achieve this goal? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Require an electronic signature when the formula is approved.

B.

Select Block editing and approve the formula.

C.

Select the Block removal of approval option for the formula

D.

Select the Block editing option only.

D18912E1457D5D1DDCBD40AB3BF70D5D

Buy Now
Questions 23

You need to configure costing for raw materials used to manufacture unscented cleaning solution.

Which form should you use?

Options:

A.

Cost basis type

B.

Quantity and margin template

C.

Pricing calculation

D.

Pricing template

Buy Now
Questions 24

You need to resolve the shop supervisor’s issue.

Which options should you use? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.

MB-320 Question 24

Options:

Buy Now
Questions 25

You need to create the production orders for standard model bicycles.

Which method should you use?

Options:

A.

Sales order line

B.

Master planning execution

C.

Supply schedule form

D.

Released item

E.

All production orders form

Buy Now
Questions 26

You need to configure the bicycles’ production resource.

Which option should you use?

Options:

A.

Exclusive capacity set to yes and enter a Batch capacity.

B.

Exclusive capacity set to no and infinite capacity.

C.

Exclusive capacity set to yes and infinite capacity.

D.

Exclusive capacity set to no and enter a Batch capacity.

Buy Now
Questions 27

You need to create the new summer limited edition bicycle in Dynamics 365 in preparation for taking orders.

Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

MB-320 Question 27

Options:

Buy Now
Questions 28

You need to determine the sales price for a new limited-edition bicycle for the summer season.

What should you do?

Options:

A.

Run inventory close for the BOM items for the limited-edition bicycle.

B.

Create the production order for the limited-edition bicycle and click estimate.

C.

Run the category price rules for the limited-edition bicycle using a cost-plus calculation.

D.

Run the pricing simulator for the limited-edition bicycle for a quantity of one.

Buy Now
Questions 29

A company produces homeopathic lotions for pain relief and uses Dynamics 365 for Finance and Operations.

Several components used in the production of the pain-relieving lotion and oils have special government-mandated reporting requirements.

You need to ensure the company can provide the appropriate reporting and tracking for these components.

Which parameters should you use? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

MB-320 Question 29

Options:

Buy Now
Questions 30

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A client subcontracts production work to a vendor for production operations.

You need to model subcontracting of route operations in production orders.

Solution: Ensure that the service product is stocked and is part of the Bill of Materials.

Does the solution meet the goal?

Options:

A.

Yes

B.

No

Buy Now
Questions 31

Note: This question is part of series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.

The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. IngredientA is the primary active ingredient in the lotion. IngredientB is used as a compensating ingredient.

You need to ensure that the system is set up to support the manufacturing process.

Solution: Configure the catch weight of IngridientA to allow for the variances of the concentrations received from the different vendors.

Does the solution meet the goal?

Options:

A.

Yes

B.

No

Buy Now
Questions 32

A company uses Discreet manufacturing concepts to produce cables. The company’s production scheduler uses internal documents to track issues on in-process production orders.

The production scheduler must group all in-process production orders according to issues. The scheduler must be able to easily determine issues with production orders.

You need to implement a method to easily identify production orders with issues.

Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

MB-320 Question 32

Options:

Buy Now
Questions 33

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A company implements Dynamics 365 for Finance and Operations for their Lean manufacturing environment.

There has been an engineering change to a fixed quantity product that is in production. This change will add an additional processing step as the second step. The existing version must be phased out and replaced by the new version.

You need to ensure that the engineering change takes affect at the end of the month.

Solution:

• Create an activity for the new process step and add it to the existing production flow. Set the expiration date to the end of the month.

• Create a Kanban rule that incorporates the new activity with an effective date of end of the month.

• Edit the existing Kanban rule. Set the expiration date to the end of the month.

• Activate the new production flow.

Does the solution meet the goal?

Options:

A.

Yes

B.

No

Buy Now
Questions 34

You need to meet the substitution requirements for User4 and User5.

What must you configure? To answer, drag the appropriate configurations to the correct substitution requirements. Each configuration may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

NOTE: Each correct selection is worth one point.

MB-320 Question 34

Options:

Buy Now
Questions 35

You need to meet the needs for the large teakwood furniture order.

What must you configure? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

MB-320 Question 35

Options:

Buy Now
Questions 36

You need to configure the requirements for metal fabrication equipment maintenance. What must you configure? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

MB-320 Question 36

Options:

Buy Now
Questions 37

You must ensure that the firepit product is available for sale. How should the product be released?

Options:

A.

Release the engineering product version and then assign the route.

B.

Connect the BOM to an engineering product version before release.

C.

Connect a route to an engineering version before release.

D.

Release the engineering product version and then assign BOM.

Buy Now
Questions 38

You need to meet the requirements for User2.

What should you configure?

Options:

A.

Process over/under transactions.

B.

Create a transfer journal.

C.

Cancel the product receipt.

D.

Correct the product receipt.

E.

Create a movement journal.

Buy Now
Questions 39

You need to enable the features and configuration keys for the firepits.

Which two features should you enable? Each answer presents part of the solution.

NOTE: Each correct selection is worth one point

Options:

A.

Engineering attributes

B.

Change management for process manufacturing

C.

Engineering product variants

D.

Engineering change management

E.

Production floor execution management

Buy Now
Questions 40

You need to address the ignition switch issue.

Which three actions should you perform? Each answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Options:

A.

Set product readiness to manual,

B.

Copy link and products.

C.

Define business impact.

D.

Change product lifecycle state.

E.

Set product readiness to automatic.

Buy Now
Exam Code: MB-320
Exam Name: Microsoft Dynamics 365 Supply Chain Management Manufacturing
Last Update: Dec 11, 2023
Questions: 207