You need to configure the warehouse manager's ModelA subassembly production requirements. Which setting should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.
The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. IngredientA is the primary active ingredient in the lotion. IngredientB is used as a compensating ingredient
You need to ensure that the system is set up to support the manufacturing process.
Solution: Set up the IngredientB formula line as a phantom BOM.
Does the solution meet the goal?
You need to configure the production requirements for the QA team. What should you configure?
You need to configure the two lift kit subassembly cost requirements for production.
Which methods should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You need to configure the solution for the two issues the production manager reported.
How should you complete the configurations? To answer, move the appropriate configurations to the correct issues. You may use each configuration once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
You need to configure the production requirements of the controller.
What should you configure? To answer, move the appropriate configurations to the correct requirements. You may use each configuration once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
A company uses Dynamics 365 Supply Cham Management.
Several production orders are in the started status.
An issue with equipment causes a rollback in the production status tor some of the orders.
Some orders must be reset once the equipment is repaired, based on which products were being manufactured.
You need to reset the production orders based on the requirements
Which status should you use for each requirement? To answer, drag the appropriate statuses to the correct requirements. Each status may be used once, more than once, or not at all.
You may need to drag the split bar between panes or scroll to view content.
You need to plan scheduling for Customer1’s order of unscented solution.
What are two possible ways to achieve the goal? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
You need to configure the system to meet the order requirements for unscented cleaning solution. Which three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to resolve the ModelT issue reported by the golf course manager.
Which two features should you configure? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to configure costing for raw materials used to manufacture unscented cleaning solution.
Which form should you use?
You need to configure production operations for the pine and orange scent solutions.
Which three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to resolve the production manager issue.
How should you configure manufacturing execution? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.
You need to implement the scheduled Kanban requirements.
Which rules should you use? To answer, drag the appropriate rules to the correct requirements. Each rule may be used once, more than once, or not at all. You may need to drag the spirt bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
You need to configure lot number control for inventory. Which option should you use?
A discrete manufacturer uses Dynamics 365 Supply Cham Management for time and attendance registrations on the shop floor.
Production worker A and production worker 8 clock in at 7 AM. They clock out at different times. Their work schedules are shown in the following table.
You need to determine how the current configuration will book the time.
What is logged in the system for each worker? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You are a manufacturer using Druitt 365 Supply Cham Management
A new series of orders is authorized for production.
You need to identify which documents to use for the released production order.
Which document should you use tor each requirement? to answer drag the appropriate documents to the correct requirements. Each document nay be used once more than once. or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
A customer produces light projection toys for holiday decorations throughout the year.
You must implement Bills of material (BOMs) for the product lifecycle. The solution must meet the following requirements:
You need to create a BOM for each phase.
Which BOM types should you use? To answer, select the appropriate configuration options in the answer area
NOTE: Each correct selection is worth one point.
A company overstates on-hand raw materials due to the time it takes to post raw materials as consumed when production orders are processed.
All items used to manufacture finished goods must be consumed when a finished good is reported as finished. You must not change all bill of materials lines to use the option of flushing principal.
You need to ensure that all production orders consume raw materials at Report as finished.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
You need to determine the sales price for a new limited-edition bicycle for the summer season.
What should you do?
You need to create the new summer limited edition bicycle in Dynamics 365 in preparation for taking orders.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
You need to configure the system to meet the requirements.
What should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You need to configure the manufacturing groups for the standard model bicycle and the new limited-edition bicycle for the summer season.
Which object should you use?
You need to report newly manufactured bicycles as finished products.
Which three options can you use? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
You need to create the production orders for standard model bicycles.
Which method should you use?
You need to configure the options for the new limited-edition bicycle for the summer season. Which configurations should you use? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.
You need to configure the bicycles’ production resource.
Which option should you use?
You need to configure the options for the new limited-edition bicycle for the summer season. Which configurations should you use? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.
You need to configure scheduling for each production area.
Which scheduling options should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.
You need to create production orders for the new summer limited-edition bicycles.
How should they be created? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You need to meet the substitution requirements for User4 and User5.
What must you configure? To answer, drag the appropriate configurations to the correct substitution requirements. Each configuration may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
You need to address the ignition switch issue.
Which three actions should you perform? Each answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to enable the features and configuration keys for the firepits.
Which two features should you enable? Each answer presents part of the solution.
NOTE: Each correct selection is worth one point
You need to meet the needs for the large teakwood furniture order.
What must you configure? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
You must ensure that the firepit product is available for sale. How should the product be released?
You need to configure the requirements for metal fabrication equipment maintenance. What must you configure? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.