MB-335 Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert Questions and Answers
You need to configure the system to meet the order requirements for unscented cleaning solution. Which three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to plan scheduling for Customer1’s order of unscented solution.
What are two possible ways to achieve the goal? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
You need to configure lot number control for inventory. Which option should you use?
You need to configure production control parameters for liquid cleaning solution manufacturing.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
You need to configure the two lift kit subassembly cost requirements for production.
Which methods should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

You need to configure the production requirements for the QA team. What should you configure?
You need to configure costing for raw materials used to manufacture unscented cleaning solution.
Which form should you use?
You need to configure the warehouse manager ' s ModelA subassembly production requirements. Which setting should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

You need to resolve the ModelA charging issue.
Which two configurations should you set on the work order finite capacity? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
A specialty nutritional supplement manufacturer that produces vitamins uses Dynamics 365 Supply Chain Management. The vitamins are configured as a single product but have multiple sellable variations by volume.
Multiple vendors send bulk raw ingredients to the manufacturer on a quarterly basis.
The vendors own the raw ingredients until the manufacturer receives an order from a distributer for a product. The manufacturer then must own the raw ingredients to be able to process the vendor invoice and provide payments for the required amounts of the law ingredients.
Any remaining raw ingredients that are unsold and at the end of their shelf life must be removed from storage and shipped back to the vendors.
You need to configure the raw ingredients to meet the requirements.
Which configuration should you use for each requirement? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

You need to configure each item for plastic manufacturing.
Which production types should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.

You need to resolve the issue reported by Buyer1.
Which two features should you configure? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to set up the correct production solution for the assembly area. Which solution should you implement?
You need to modify the production order defaults for the manufacturing execution production order Start process.
What should you do? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

You are responsible for product and formula maintenance for a paint manufacturer. You create a formula for white paint and add its lines. When the formula size increases or an ingredient changes, the quantity of the pigment ingredient must be adjusted proportionately. You need to set up the formula line for the pigment. Which formula feature should you use?
You need to create the constraint for the ML seat selection.
Which expression constraint should you use?
You need to resolve the ModelT issue reported by the golf course manager.
Which two features should you configure? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to configure the solution for the two issues the production manager reported.
How should you complete the configurations? To answer, move the appropriate configurations to the correct issues. You may use each configuration once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

You need to configure the reservation methods prototype production order as planned by the engineering team.
How should you configure the prototype production order? To answer, move the appropriate configurations to the correct requirements. You may use each configuration once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP 01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
• Create a vendor warehouse for the subcontracting vendor.
• Create a vendor resource and add it to a new work cell for outsource painting.
• Create a production flow transfer activity and specify the vendor warehouse as The target warehouse.
Does the solution meet the goal?
You need to configure the system to meet the requirements.
What should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

You need to resolve the issue for UserC.
Which two options should you configure? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
You need to configure the controller ' s ModelB asset requirements for the off-season.
What should you do?
You need to configure the system for plastic operations.
Which two parts should be manually reported as finished? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to address the ignition switch issue.
Which three actions should you perform? Each answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to configure scheduling for each production area.
Which scheduling options should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.

You need to set up the configuration model to price the motorcycles correctly. What should you do?
You need to set up the state control for sales of motorcycles.
Which two actions should you perform? Each correct answer presents part of the solution.
NOTE : Each correct selection is worth one point.
You need to set up the metal production route and BOM.
Which three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
You need to meet the substitution requirements for User4 and User5.
What must you configure? To answer, drag the appropriate configurations to the correct substitution requirements. Each configuration may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

You need to configure the requirements for metal fabrication equipment maintenance. What must you configure? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

A company plans to use master planning in Dynamics 365 Supply Chain Management. The company will sell items between legal entities.
The company has several facilities across legal entities that can manufacture the same products. Same products are produced only in some plants. To meet product demand, when one facility is over capacity, another facility is used to fulfill the downstream demand.
The organizational entities are:
• LegalEntityA: Plant 1.2, and 3
• LegalEntityB: Plant4and 5
• LegalEntityC: Plant 6. 7, and 8
The following plants must be planned together:
• Plant 1. Plant 3. and Plant 4
• Plant 2. Plant 6. and Plant 8
• Plant 5 and Plant 7
You need to configure master planning for the facilities.
Which configuration mechanism should you use?
You must ensure that the firepit product is available for sale. How should the product be released?
You need to enable the features and configuration keys for the firepits.
Which two features should you enable? Each answer presents part of the solution.
NOTE: Each correct selection is worth one point
You need to meet the needs for the large teakwood furniture order.
What must you configure? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

You need to determine the sales price for a new limited-edition bicycle for the summer season.
What should you do?
You need to create the new summer limited edition bicycle in Dynamics 365 in preparation for taking orders.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

You are the production scheduler for a manufacturing company. You have run the Resource Group Capacity report as shown in the Resource Group 21 Capacity exhibit. (Click the Resource Group 21 Capacity tab).

After reviewing that report, you run Resource Capacity reports as shown in the Resource 2101 and 2102 Capacity exhibits. (Click the 2101 Capacity and 2102 Capacity tabs.)

You run the Gantt chart report as shown in the Gantt exhibit to determine the production orders scheduled on the resources. (Click the Gantt tab.)

You need to determine the method to schedule the production lines.

For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.

A company uses Process manufacturing for most products and Discrete manufacturing for other products. The company is creating a formula for a new product. The new item will be used to make a name brand product and two generic brand products.
This item has the following requirements:
• Production of the name brand and generic products must use the same formula.
• The company must produce all three items at the same time.
You need to create a produced item that can make two generic items and one main item.
How should you set up the item?
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to It. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
• Create a purchase agreement for the subcontracting vendor and add SP-01 as the painting service.
• Create a vendor resource then create a work cell for outsourced painting and add the resource to the work cell.
• Create a production flow process activity for the painting work cell and add the component to be painted as a picking activity.
• Create a server term to tie the purchase agreement to the activity.
Does the solution meet the goal?
A manufacturing company uses Dynamics 365 Supply Cham Management.
The company identifies a bill of materials (BOM) item that needs to be recalled for a product
The engineering department needs to link customer support incidents and knowledgebase articles related to the product change.
Other items affected by this change must reference the same support incidents and knowledgebase articles.
You need to recommend features to facilitate this business process.
Which features should you recommend? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

You need to calculate estimated consumption of ingredients for liquid cleaning solution.
What is the consumption? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.

You need to resolve the shop supervisor’s issue.
Which options should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.

You need to report newly manufactured bicycles as finished products.
Which three options can you use? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
You need to configure the manufacturing groups for the standard model bicycle and the new limited-edition bicycle for the summer season.
Which object should you use?
You need to configure the options for the new limited-edition bicycle for the summer season. Which configurations should you use? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.

You need to create production orders for the new summer limited-edition bicycles.
How should they be created? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

You need to configure the options for the new limited-edition bicycle for the summer season. Which configurations should you use? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.

You need to configure the bicycles’ production resource.
Which option should you use?
You need to create the production orders for standard model bicycles.
Which method should you use?















A white paper with black text
AI-generated content may be incorrect.
A white background with black text
AI-generated content may be incorrect.



