Which activity contributes MOST to achieving the ‘bring pace and value’ principle?
Identify the missing word(s) in the following sentence:
The definition of [?] is a control point, following delivery of a step-change in capability and benefits realization (tranche), at which a programme can be re-directed or closed.
Identify the missing word in the following sentence:
A programme risk is defined as an uncertain event that, if it occurs, will have an effect on the achievement of programme [?].
Which document, produced during the ‘identify the programme’ process, describes high-level costs, benefits and risks?
Which is a COMMON challenge encountered by organizations that MSP is designed to address?
Which process ensures that all facts are available when they are required by the programme board?
Which document identifies activities to give confidence to stakeholders about how programme risks are managed?
Which principle is the ‘decisions’ theme applying when both the best and worst outcome of a decision is analysed?
Which TWO are objectives of the ‘deliver the capabilities’ process?
To ensure benefits start to be realized and measured.
To ensure corrective action is taken where necessary.
To ensure programme progress is monitored and reported.
To ensure controls are put in place to ensure benefit realization continues in BAU.
Which is a structured set of programme activities that define the sequence of actions, and their inputs and outputs, to achieve a specific objective?
Which is a result of the ‘assurance’ theme applying the principle ‘collaborate across boundaries’?
Which contributes MOST to achieving the ‘collaborate across boundaries’ principle?
Identify the missing word in the following sentence:
A dis-benefit is defined as a measurable decline resulting from an outcome perceived as negative by the investing organization(s) and which detracts from one or more organizational [?].
Which TWO are objectives of the ‘deliver the capabilities’ process?
To ensure that stakeholders adopt new ways of working.
To ensure that controls are put in place so that benefit realization continues in BAU.
To ensure that projects are started and closed in a controlled manner.
To ensure that risks and issues are kept under control.
Which TWO are objectives of the ‘identify the programme’ process?
To ensure that key decision-making roles have been identified and appointed.
To ensure that the tranches of delivery and intermediate landing points are defined.
To ensure that the delivery approach and ways of working are defined.
To ensure that major risks to the high-level benefits have been identified.