MSP-Practitioner MSP Practitioner, 5th edition Exam Questions and Answers

Questions 4

Who produces Business Case?

Options:

A.

Sponsoring Group

B.

SRO

C.

Programme Manager

D.

BCM

Buy Now
Questions 5

The programme is in the ‘embed the outcomes’ process at the end of Tranche 2. As part of the adopt the capabilities activity, the BCM is concerned that many of the sales staff are continuing to use the old sales system alongside the new systems and processes. This is impacting on cost reductions and increased sales. The BCM has confirmed that the new system has all the functionality required.

As part of the ‘adopt the capabilities ' activity what should the BCM do to resolve this situation?

Options:

A.

Start reporting on the reduced costs and increased sales compared to the baselines

B.

Confirm that the sales staff have transitioned successfully to the new sales system as It is being used by all staff

C.

Encourage those staff members who are using the new system effectively to share their knowledge and experiences

D.

Ensure that access to the old sales system is removed and provide support in the new ways of working

Buy Now
Questions 6

Which of the following statements is FALSE?

Options:

A.

The SRO must have enough seniority to take on accountability for the programme delivery.

B.

The SRO is likely to be a peer of the Sponsoring Group.

C.

The SRO is appointed by the Sponsoring Group.

D.

The SRO acts as the Project Executive on all the Project Boards.

Buy Now
Questions 7

Which of following best defines Outcomes?

Options:

A.

Deliverable of a project

B.

Completed set of project outputs

C.

Measurable improvement resulting from outcomes perceived as advantage

D.

New operational state achieved after transition of capability in live operations

Buy Now
Questions 8

The programme is in Tranche 2 and has been progressing according to plan. However, there have been difficulties transitioning to the new ways of working at the end of Tranche 1 and UU has had some customer complaints as a result. Therefore, the SRO asked the programme manager to replan the programme so that all remaining capabilities are transitioned at the end of the programme, instead of at the end of the tranche.

Is this an appropriate application of the ' structure ' theme, and why?

Options:

A.

Yes, because applying the ‘lead with purpose’ principle requires delivery to be planned to realize outcomes of benefit

B.

Yes, because applying the ' collaborate across boundaries ' principle requires effective use of programme resources

C.

No, because applying the ‘realize measurable benefits’ principle requires outcomes of benefit to be embedded at intermediate landing points

D.

No, because applying the ‘align with priorities ' principle requires the content of the tranches to be changed, rather than delaying transition

Buy Now
Questions 9

MSP is best suited for which programme?

Options:

A.

Technically complex but with defined outputs

B.

Simple programme with defined outcomes and strong governance in place

C.

Programme for long term societal change

D.

Launching new products

Buy Now
Questions 10

Which document is prepared with a purpose to share with stakeholders?

Options:

A.

Programme Plan

B.

Vision

C.

Business Case

D.

Blueprint

Buy Now
Questions 11

The programme is in the ‘close the programme ' process. All the projects have been successfully completed, and the capabilities have been delivered. However, some of the new sales roles are still to be recruited in order to deliver increased sales. The programme manager has passed the management of this remaining work to the HR Director.

Is this an appropriate action for the programme manager to take, and why?

Options:

A.

Yes, because the remaining recruitment should be handed to the HR Director to ensure that the benefits are realized

B.

Yes, because the impact of closure on the HR Director needs to be understood and managed well

C.

No, because programme information should be up-to-date and archived before the programme can be formally closed

D.

No, because the SRO should be responsible for disbanding the programme team and closing the programme

Buy Now
Questions 12

In which document would you expect to find the levels of confidentiality to be applied in the programme?

Options:

A.

The Information Management Strategy

B.

The Quality Management Strategy

C.

The Resource Management Strategy

D.

The Benefits Management Strategy

Buy Now
Questions 13

Which of below sentences describes Project Brief?

Options:

A.

List of all projects that will be part of programme

B.

Control framework for programme

C.

Control framework for projects

D.

Describes purpose, cost, time, performance requirements and constraints of a project

Buy Now
Questions 14

The programme is in the middle of Tranche 2. A new SRO has been appointed. To understand the current status of the programme, the SRO has asked for a health check to be carried out. The programme office lead has recruited an external consultant to carry out the health check.

Which assurance success factor does this demonstrate?

Options:

A.

Independence

B.

Accountability

C.

Coordination

D.

Risk appetite

Buy Now
Questions 15

Which individual is MOST LIKELY to be appointed as the SRO?

Options:

A.

Chief Finance Officer

B.

Human Resources Director

C.

Chief Technology Officer

D.

Chief Engineering Officer

Buy Now
Questions 16

Which of following is input for ' managing the tranches ' ?

Options:

A.

Programme preparation plan

B.

Programme Brief

C.

Approval to proceed

D.

Assurance review reports

Buy Now
Questions 17

Which of following is not responsibility of Programme Office?

Options:

A.

Repository of programme information

B.

Providing regular updates on progress to SRO

C.

Risk and Issue tracking

D.

Ensuring the control and management frameworks are effectively implemented

Buy Now
Questions 18

Which of the following is Management document?

Options:

A.

Programme brief

B.

Project Dossier

C.

Issue Register

D.

Programme Mandate

Buy Now
Questions 19

Which type of cost is associated in training, moving and supporting an operational unit?

Options:

A.

Programme management cost

B.

Capital cost

C.

Business change and transition cost

D.

Benefits realization cost

Buy Now
Questions 20

The programme is in the ‘design the outcomes’ process for the first time. The Research and Development Project team has recommended that UU sources an imported next generation smart meter. This is an alternative to the development of the smart meter internally. The imported meter can be fully implemented before the CEO retires in three years ' time. However, there is a possibility that this meter could lead to future information security risks.

Is this recommendation an appropriate application of the ‘decisions ' theme, and why?

Options:

A.

Yes, because the proposed option should gain the CEO’s full support

B.

Yes, because providing a clear recommendation should bring pace and value

C.

No, because there are security risks identified with the option proposed

D.

No, because a ‘do-nothing’ option and at least two others should be provided

Buy Now
Questions 21

The programme is in the ‘plan progressive delivery ' process. The programme manager has recommended that the funds for the HR Work should come from a different source to the funding for the project work.

During which activity is the SRO responsible for providing formal approval for this recommendation?

Options:

A.

Continue to develop and validate programme plans

B.

Confirm business case

C.

Prepare for the next process

D.

Agree to proceed (or close)

Buy Now
Questions 22

The programme is now in the ‘close the programme’ process. All the planned training from the Training Project has been completed. However, it is too early to tell how much impact the training will have on service to customers. This will need to be monitored during normal business operation.

Which theme is MOST relevant to this situation?

Options:

A.

Design

B.

Knowledge

C.

Organization

D.

Structure

Buy Now
Questions 23

The programme manager has analysed the costs of using an expert external company to work on the Research and Development Project. Although using the external experts is likely to produce a higher quality solution which would lead to increased organizational adoption, the SRO has insisted that the project only uses internal staff to minimize costs.

Is the SRO ' s response an appropriate application of the ‘deploy diverse skills ' principle, and why?

Options:

A.

Yes, because the programme should minimize its reliance on external suppliers to minimize costs

B.

Yes, because it is important to build internal skills for the future during the programme

C.

No, because the sponsoring group should approve decisions on how the programme will be resourced

D.

No, because programme delivery should use the right mix of skills to achieve the outcomes of benefit

Buy Now
Questions 24

UU has partnered with a supplier who has expertise in training and change management. The supplier will provide a virtual change office function, helping staff in the business prepare for the significant transformation ahead and ensuring that the benefits will be realized. However, these change management services are very costly.

Is this an appropriate application of the ‘justification’ theme, and why?

Options:

A.

Yes, because the costs are justified by the support provided to staff members and the benefits to be delivered

B.

Yes, because the money saved by having a single call centre will provide contingency to pay for the change office

C.

No, because the BCM should use a network of internal change agents to support the changes in order to save money

D.

No, because defining the need for additional supporting offices is part of tailoring the ’organization’ theme

Buy Now
Questions 25

Which of below sentences best defines programme management?

Options:

A.

Coordinating projects under a common umbrella

B.

Executing dependent projects with aim of realizing benefits

C.

Management of set of activities with dependencies and deadlines with aim of realizing benefits

D.

Action of carrying out coordinated organization, direction and implementation of project dossier and transformation activities to realize benefits of strategic importance

Buy Now
Questions 26

Which of following is NOT part of delivering the capability?

Options:

A.

Start Projects

B.

Governance: Manage and control delivery

C.

Align projects with benefits realization

D.

Gateway reviews

Buy Now
Questions 27

During Tranche 1, the Call Centre Manager had played an active role in the programme as a BCM. However, at the end of the tranche, it was decided that they were not required during Tranche 2. In addition, the CTO was appointed as a new BCM for Tranche 2.

Which principle is being applied by the ‘organization’ theme, and why?

Options:

A.

Lead with purpose, because the new BCM has a more senior role in UU and will be able to lead the work in Tranche 2

B.

Lead with purpose, because the appointment of the new BCM should result in more integrated decisionmaking in Tranche 2

C.

Align with priorities, because the new BCM is able to provide support to operations to deliver the Tranche 2 outcomes

D.

Align with priorities, because the appointment of the new BCM shows senior commitment to Tranche 2

Buy Now
Questions 28

Halfway through Tranche 2, North City local government announced a new incentive programme to support green initiatives that help residents reduce their carbon footprint. UU is applying for this funding, claiming that its water smart meters and leak detection systems qualify as eco-friendly mechanisms aligned to the new government scheme. The cost of the application process will be more than paid for if UU is approved as part of the incentive programme.

Is this an appropriate application of the justification ' theme, and why?

Options:

A.

Yes, because the programme budget should include financial contingency to deal with identified opportunities

B.

Yes, because the sponsoring group should pursue valuable opportunities and make them more likely to occur

C.

No, because the funding approach for this programme should ensure that the programme is self-funded by this point

D.

No, because the programme should consider the ‘do nothing’ option, plus at least two other options, before pursuing the opportunity

Buy Now
Questions 29

Here are three actions to be performed during the Smart Meter Programme. Which role has an area of focus associated with each statement?

MSP-Practitioner Question 29

Options:

Buy Now
Questions 30

Which document identifies appropriate milestones for benefit reviews?

Options:

A.

Benefit realization plan

B.

Quality and assurance plan

C.

Information management plan

D.

Business case

Buy Now
Questions 31

Which of the following statements best defines ' MSP Principles ' ?

Options:

A.

Common factors of success derived from lessons learned in programmes that had both positive and negative results

B.

Allow organizations to put in place right leadership, delivery team, robust organization structures and controls

C.

Provides a route through lifecycle of a from its conception through to delivering new capability

D.

Temporary flexible organization created to coordinate, direct and oversee implementation of set of related projects

Buy Now
Questions 32

Which of following groups can be a stakeholder for building a city programme?

Options:

A.

Employees

B.

Political leadership

C.

People interested in being residents

D.

All of above

Buy Now
Questions 33

Which of following is correct about Benefits Management?

Options:

A.

Ensures programme does right things and is aligned with strategy

B.

Ensures programme is aware of positive and negative impact it might generate

C.

Is tightly aligned to transformational flow processes

D.

All of above

Buy Now
Questions 34

Which of the following is NOT an MSP Governance Theme?

Options:

A.

Leadership and Stakeholder Engagement

B.

Learning from Experience

C.

Quality Management

D.

Organization

Buy Now
Questions 35

Which of the following will not be in Issue register?

Options:

A.

Date issue was raised

B.

Description of issue

C.

How issues will be identified, captured and assessed

D.

Categorization of issue

Buy Now
Questions 36

Which of the following is kind of a vision led programme?

Options:

A.

Programme evolved from concurrent, individual projects with need to ensure compliance to organization strategy

B.

Must do programmes due to change in legislation

C.

Public programme started to fulfil electoral promises

D.

Programme focused on bringing organization in tune with laws of the country of operations

Buy Now
Questions 37

Which of following is output of ' Identifying the programme ' ?

Options:

A.

Programme Mandate

B.

Appointment of programme board and SRO

C.

Business Case

D.

Benefit profiles

Buy Now
Questions 38

In delivering the capability, who is responsible for aligning projects with benefits realization?

Options:

A.

BCM

B.

Programme Manager

C.

Both

D.

None

Buy Now
Questions 39

UU has always used a linear project management methodology in the past with varying degrees of success. During the ‘design the outcomes’ process, UU has decided to trial an agile approach to deliver projects throughout Tranche 1.

Which theme is being applied to the ‘design the outcomes ' process?

Options:

A.

The ‘knowledge ' theme is being applied by making use of lessons from their previous agile projects

B.

The ‘decisions’ theme is being applied by coming to a conclusive decision to use an agile approach for delivery

C.

The ’structure ' theme is being applied by using an agile delivery method to a complex piece of work

D.

The ‘design’ theme is being applied by deliberately designing the work to make use of an iterative approach

Buy Now
Exam Code: MSP-Practitioner
Exam Name: MSP Practitioner, 5th edition Exam
Last Update: May 11, 2026
Questions: 133