PgMP Program Management Professional (PgMP) Questions and Answers

Questions 4

A large international manufacturing company is centralizing its IT which is currently spread over 16 countries. The transition means physically regrouping the infrastructure and aligning processes and organizations. The high-level scope of this transformation encompasses three main areas:

1. The technology area--assessing which technology/tooling should be retained for the target data center.

2. The policies and procedure area--aimed at establishing a common set of processes supporting the new way of delivering services.

3. The HR area--assuring the new organization best fits the diversity of the countries and functional domains, while offering equivalent compensations for comparable functions.

You have selected your team and you are preparing the business case to support 1) the team selections you made and 2) your recommendation to proceed to the program ' s next phase.

Which document should be present in your business case?

Options:

A.

A detailed plan showing dependencies among the constituent projects

B.

A comprehensive analysis of the different compensation packages offered in the 16 countries

C.

An inventory detailing all physical and logical components in place and the employees in scope

D.

A cost/benefit analysis of the different scenarios, presenting their respective contributions

Buy Now
Questions 5

Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team. This requirement for four licensed electricians is an example of which one of the following terms?

Options:

A.

Screening system

B.

Scoring model

C.

Vendor analysis requirements

D.

Evaluation criteria

Buy Now
Questions 6

A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change

request, as it would extend the program schedule and require a scope change. To whom should the change request be presented?

Options:

A.

The program governance board

B.

The program customer

C.

The program management office (PMO)

D.

The project governance board

Buy Now
Questions 7

During program execution, a program manager receives feedback from an executive sponsor that some program stakeholders may not understand the intended benefits of the program.

Which will provide the greatest value to clarify stakeholder perceptions?

Options:

A.

Performing a stakeholder analysis

B.

Updating the stakeholder communications requirements

C.

Redistributing the benefits management plan

D.

Redistributing the program charter

Buy Now
Questions 8

A wild life protection organization opposes your program, which involves the cutting of around 200 trees to make way for the construction of a building. Which of the following correctly defines the organization in program management terminology?

Options:

A.

Negative stakeholder

B.

Positive stakeholder

C.

Key stakeholder

D.

Hurdle stakeholder

Buy Now
Questions 9

You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you ' re about to perform some schedule control activities. Which one of the following will not help you as you perform schedule control?

Options:

A.

Change requests

B.

Performance reports

C.

Forecasts

D.

Earned value management

Buy Now
Questions 10

In your program you must adhere to Six Sigma as part of your organization ' s enterprise environmental factors. There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?

Options:

A.

Quality control

B.

Process improvement

C.

Scope verification

D.

Quality assurance

Buy Now
Questions 11

Which of the following contract types is described in the statement below?

" The seller is reimbursed for all allowable costs for performing the contract work, and receives a fixed payment calculated as a percentage for the initial estimated project costs. "

Options:

A.

Cost Plus Fixed Fee Contracts (CPFF)

B.

Fixed Price Incentive Fee Contracts (FPIF)

C.

Firm Fixed Price Contracts (FFP)

D.

Cost Plus Incentive Fee Contracts (CPIF)

Buy Now
Questions 12

Which of the following represents the duration of activities against a calendar?

Options:

A.

Pie chart

B.

Scatter chart

C.

Gantt chart

D.

Pareto chart

Buy Now
Questions 13

When a change enters your program requirements you must update all of the following documents except for which one?

Options:

A.

Program work breakdown structure

B.

Program activity list

C.

Program charter

D.

Program scope

Buy Now
Questions 14

A large infrastructure development program involves three road construction projects, two sewage line construction projects, and one project to lay underground electric cables. During a program meeting, the project manager of a road construction project communicates that a project risk related to the interdependency with a sewage line project has crossed its risk threshold.

What should the program manager do next?

Options:

A.

Modify the program schedule to accommodate the risk.

B.

Incorporate the project risk into the program risk response strategy.

C.

Instruct the project manager to escalate the risk to the program sponsor.

D.

Ask the road construction project manager to manage the risk at the project level.

Buy Now
Questions 15

A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?

Options:

A.

$978,445

B.

$919,325

C.

$991,667

D.

$987,544

Buy Now
Questions 16

A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.

Which of the following deliverables captures these items?

Options:

A.

Program scope management plan

B.

Program governance plan

C.

Program scope statement

D.

Program work breakdown structure

Buy Now
Questions 17

The program manager plans to address a negative cost variance generating a red flag in the program management status report.

What should the program manager do?

Options:

A.

Contact the project sponsors to present the details, impacts, and possible corrective actions regarding the negative cost variance.

B.

Gather all the details, analyze impacts, determine corrective actions and present the findings to the governance board for direction.

C.

Work with program sponsor to compile impact analysis data to obtain additional funding for the program.

D.

Ask the program team to compile all details, analyze impacts, determine corrective actions and present to the governance board for direction.

Buy Now
Questions 18

Which of the following is used to build consensus through rounds of anonymous surveys?

Options:

A.

The Pareto chart

B.

The Delphi technique

C.

The Monte Carlo simulation

D.

The Gantt chart

Buy Now
Questions 19

In your organization there are rules and procedures that the program manager must follow and abide by before the program can begin and must continue to follow once the program is in execution. What term is assigned to the enforcement of these program management rules and procedures?

Options:

A.

Program governance

B.

Organizational process assets

C.

Program standards

D.

Process analysis

Buy Now
Questions 20

Several issues are identified on one component project in a program. During a meeting with that component’s project manager, the program manager offers several suggested resolutions. Two weeks later, they meet again to review progress. The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule.

What should the program manager do?

Options:

A.

Join project-level issue resolution meetings to accelerate the decision-making process.

B.

Initiate discussions with the program governance board about assigning a more experienced project manager to the project.

C.

Emphasize that the project manager needs to address the issues and follow up at the next scheduled meeting.

D.

Develop an immediate corrective action plan with the project manager and coach them on decision-making responsibilities.

Buy Now
Questions 21

What duration compression technique typically adds risk when it ' s used during a program?

Options:

A.

Lead time generation

B.

Fast tracking

C.

Resource leveling heuristics

D.

Crashing

Buy Now
Questions 22

Which of the following is described in the statement given below?

" It serves as the primary input for the Plan Program Stakeholder Management process, as well as for the distribution of program reports and other communication. "

Options:

A.

Stakeholder register

B.

Program scope statement

C.

Governance plan

D.

Organizational chart

Buy Now
Questions 23

You are the program manager for your organization. One of the projects within your program is to install 15,000 light fixtures throughout your organization ' s corporate campus. The new fixtures will save on electrical costs. Which one of the following choices is an ideal approach to quality assurance and the installation of the light fixtures for this project team?

Options:

A.

The cost and time of each installation should go down because of the learning curve.

B.

The project manager should work with the project team to understand how each fixture is to be installed.

C.

The project team members should develop their own system for installation of the fixtures.

D.

Use a checklist for the installation because it is repeatable work.

Buy Now
Questions 24

Which of the following statements is most accurate about the critical path?

Options:

A.

The critical path is always one path that shows the project duration.

B.

The critical path has no float.

C.

The critical path is the longest path because it has the most activities.

D.

The critical path reveals which path has the most risk of failure.

Buy Now
Questions 25

A program manager recognizes that a successful resource being used in project A could also be used in project B.

What should the program manager do first to leverage the utilization of this resource?

Options:

A.

Assign project A ' s resource to project B.

B.

Reassign the resource to project B after project A ends.

C.

Prioritize the resource to optimize their use across both projects A and B.

D.

Mitigate risk by leveraging other resources in project A.

Buy Now
Questions 26

A program manager initiates a developmental program. Significant resources and funding are required for early activities until the program cost and budget estimates are complete.

What should the program manager do to understand the financial environment?

Options:

A.

Map costs to the expected benefits realization.

B.

Establish intermediate budget based on historical information.

C.

Establish program financial framework.

D.

Obtain intermediate funding from the executive sponsor.

Buy Now
Questions 27

You are the project manager for your organization and are working with the project stakeholders and the business analyst to define all of the deliverables the project is to create. The stakeholders would like the option of adding more deliverables later in the project and keeping the requirements somewhat open for changes. You explain to the business analyst that you need a set of requirements that define exactly what needs to be delivered for the project. What document are you trying to create in this early stage of the project?

Options:

A.

Requirements technical documentation

B.

Project scope statement

C.

Project charter

D.

Detail design document

Buy Now
Questions 28

A municipal agency manages a city ' s water and wastewater infrastructure. Its six-year capital improvement program (CIP) is approximately US$4 billion, and is used for such things as improving aging infrastructure, addressing regulatory requirements, and upgrading facilities. The mayor and key stakeholders are concerned because of yearly rate increases for residents. After receiving proposals from program managers for this key program, which is half of the current CIP, a program management team is hired and receives an approved business case.

What should the project manager do next?

Options:

A.

Discuss the program change and its challenges.

B.

Create a program management plan.

C.

Conduct a program performance analysis.

D.

Develop a program charter.

Buy Now
Questions 29

You are the program manager for your organization and are working with your program team to create the

program scope. Based on the program requirements you have identified the major deliverables of each phase in your program scope. Management has requested that you plan for cost estimating to happen at each phase of the program before continuing the work. Management may elect to cancel the program at the end of each phase based on past performance of the program. What are the reviews of management called at each phase?

Options:

A.

Phase gate estimates

B.

Murder board

C.

Portfolio review sessions

D.

Kill points

Buy Now
Questions 30

You are the program manager for your organization and are about to execute your procurement management plan. You need to procure materials for your program and you want only the vendor to provide you with a price for the goods you need to procure. What type of a document should you provide to the vendor in this

scenario?

Options:

A.

Statement of work

B.

Request for quote

C.

Proposal

D.

Program charter

Buy Now
Questions 31

You have identified several issues in your program and have assigned issue owners. What component of program management oversees issue resolution?

Options:

A.

Program governance

B.

Program risk management

C.

Quality assurance

D.

Issue owner management

Buy Now
Questions 32

A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue.

What should the program manager do NEXT?

Options:

A.

Consider the option to close out the key project

B.

Evaluate the program and re-baseline the objectives

C.

Assess the benefits and impact to the program

D.

Amend the risk register with the key project changes

Buy Now
Questions 33

You are the program manager for your organization. You have created a program that will create things for the organization throughout the program not only at program closure. All of the following are elements that you may transfer to the organization throughout the program ' s life cycle except for which one?

Options:

A.

Benefits

B.

Risk management outcomes

C.

Program personnel

D.

Outputs from team development

Buy Now
Questions 34

A program manager needs to establish direction and identify the essential aspects of a program. In addition, they must ensure that the context and framework of the program are properly defined, assessed, and documented.

Which document will be created to support this activity?

Options:

A.

Program resource management plan

B.

Program management plan

C.

Program master schedule

D.

Program scope statement

Buy Now
Questions 35

An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits sustainment plan starts, the program manager discovers the program may be shut down due to lack of funding.

To ensure continued funding for the program, what should the program manager do next?

Options:

A.

Complete the benefits sustainment plan and update the benefits register

B.

Present a revised ROI to the program sponsors based on the remaining investment

C.

Conduct a cost-benefit analysis to ensure the program sponsors understand the program’s long-term benefits

D.

Review the program business case and the program’s strategic alignment and long-term benefits with the program governance board

Buy Now
Questions 36

You are the program manager for your organization. Your program team has 43 people that all need to be monitored and controlled. You would like to create a standardized report that you can use to monitor, control, and record the performance of each staff member in your program. What type of report can you create that will help you track your staff and their performance?

Options:

A.

Performance reports

B.

Staff variance reports

C.

Exceptions report

D.

Lessons learned

Buy Now
Questions 37

Near the completion of a transformation program, the operations manager is concerned that their department failed to be notified in advance of the new service being transitioned into operations. They claim that their

department did not approve this service, and is now unprepared and untrained to support the transformation. What should the program manager have done first to prevent this?

Options:

A.

Added the operations manager as a key stakeholder

B.

Created a transition plan during the planning phase for the impacted operational area

C.

Ensured there was a communications management plan that included the transition to operations

D.

Drafted a training plan with assistance from the program management office (PMO) or human resource department before transitioning it to operations

Buy Now
Questions 38

A program manager is working with the sponsor, stakeholders, and steering committee to formulate a program’s benefits sustainment and transition plan. What should the program manager do to create this plan?

Options:

A.

Identify key measures to compare expected benefits in the benefits management plan with actual performance once benefits sustainment and program transition starts.

B.

Assign creation of the benefits sustainment plan to the organization responsible for monitoring and controlling the sustainment period.

C.

Interview stakeholders, and revise the benefits management plan to provide new insight into the program’s execution and benefits sustainment period.

D.

Update the benefits management plan, and provide a copy to the organization responsible for measuring the sustainment period.

Buy Now
Questions 39

Gina is the program manager for her organization and is reviewing the results of quality control. She would like to create a chart that shows the categories of defects within the program so that she and the program team can address the largest categories in descending order. Which one of the following is the best chart for Gina in this situation?

Options:

A.

Cause and effect chart

B.

Pareto chart

C.

Control chart

D.

Ishikawa chart

Buy Now
Questions 40

Which of the following directs the improvement efforts to those areas that will have the biggest impact?

Options:

A.

Gantt chart

B.

Flowchart

C.

Pareto diagram

D.

User Documentation

Buy Now
Questions 41

The program manager must define the program and understand the organization’s target market and customer needs.

What should the program manager do first?

Options:

A.

Brainstorm with the program team to decide on the definitions of the target market.

B.

Meet with peers to identify the company’s competitors in the target market.

C.

Meet with the project managers to identify the target market.

D.

Work with the program sponsor to assess the needs of the target market.

Buy Now
Questions 42

A new program is comprised of four component projects. The program manager must assign project managers to each of the four projects. There are eight potential project managers to consider.

What should the program manager do before assigning the project managers?

Options:

A.

Determine budgetary constraints related to the project managers’ salaries

B.

Request performance feedback from the project managers’ line managers

C.

Evaluate the project managers’ skills and match them to the needs of the projects

D.

Interview each project manager to determine their career aspirations

Buy Now
Questions 43

Who owns the program?

Options:

A.

Program manager

B.

Project manager

C.

Program director

D.

Program sponsor

Buy Now
Questions 44

A program manager has four projects pending approval. Senior management asks the program manager to identify a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision:

PgMP Question 44

Which project should the program manager select to be cancelled?

Options:

A.

Project A

B.

Project B

C.

Project C

D.

Project D

Buy Now
Questions 45

Which of the following documents contain a list of all problems, unfavorable events, or situations that occurred so far in the program?

Options:

A.

Program charter

B.

Program risk register

C.

Program issue register

D.

Program scope statement

Buy Now
Questions 46

The program manager has a global program with five component projects. The program sponsor wants the management plans, processes/procedures, and technology to be uniform across the program. The requirements will create issues and result in increased costs The program sponsor is new and has imposed these new requirements six months into a three-year program.

What should the program manager do next?

Options:

A.

Accept what the program sponsor requires and implement the changes.

B.

Discuss the proposed changes with the stakeholders and project managers, and give the program sponsor the best option.

C.

Respond to the program sponsor if the program sponsor asks about it a second time.

D.

Present the risks and benefits of the changes to the program sponsor.

Buy Now
Questions 47

A component project of a multiyear program delivers all expected products and services as anticipated. The component project manager obtains approvals from the stakeholders and transitions the benefits to operations.

What should the program manager do next?

Options:

A.

Reassign the component project manager to another component project or activity

B.

Verify that the benefits were delivered and authorize component project closure

C.

Conduct a program audit to confirm that the component project is complete

D.

Keep the component project open until the program benefits are realized

Buy Now
Questions 48

You are the project manager for your organization. Your project team has finished the second phase of a seven-phase project. At the end of each phase, management must review the work your project team has completed and determine if the project should be allowed to continue. What name describes this type of end- of-phase review management is completing on your project?

Options:

A.

Quality control

B.

Kill point

C.

Phase review

D.

Audit

Buy Now
Questions 49

What would prevent a program manager from completing program closure once a program has been completed?

Options:

A.

Failure to update the financial management plan

B.

Failure to update the benefits register

C.

Incomplete realization of all program benefits

D.

Failure to obtain program steering committee approval

Buy Now
Questions 50

The chief executive officer reminds a program manager that a program must deliver a 30% reduction in customer complaints by the end of the year.

Where is this expectation documented?

Options:

A.

Program quality standards

B.

Customer management plan

C.

Benefits management plan

D.

Benefits sustainment plan

Buy Now
Questions 51

The program manager wants to ensure that a program contributes to shareholder value.

The program manager should verify alignment with which of the following?

Options:

A.

Program charter

B.

Organizational structures and policies

C.

Organizational strategic objectives

D.

Program governance plan

Buy Now
Questions 52

A key stakeholder’s requirement contradicts the organization’s strategic objectives. The program manager meets with the stakeholder, but is unable to reach a compromise on the requirement.

What should the program manager do first?

Options:

A.

Meet with the program management office to update the benefits management plan

B.

Meet with organization’s strategic planning committee to obtain clarification

C.

Meet with the program sponsor to address the issue

D.

Meet the customer to determine if the stakeholder’s requirement is valid

Buy Now
Questions 53

The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality, and schedule objectives have been met, but costs and resource utilization are higher than expected. The program can no longer deliver the planned return-on- investment within an acceptable level and the intended benefits have not yet been realized.

After further analysis of the performance indicators, the program manager should do which of the following?

Options:

A.

Extend the schedule to reduce costs and resource utilization.

B.

Expand the scope and continue the program until return-on-investment objectives can be met.

C.

Recommend cancellation of the program based on performance metrics.

D.

Transition the existing program results to the appropriate operational area.

Buy Now
Questions 54

A program sponsor is concerned about the status of high-priority risks and budget variances.

The program manager should refer to which of the following?

Options:

A.

Program status dashboard

B.

Program management plan

C.

Program performance report

D.

Program management information system (PMIS)

Buy Now
Questions 55

A company CEO issues a mandate to automate a new-client onboarding process to replace manual and paper-based procedures. After the program sponsor and program manager obtain formal acceptance of the program charter, what should be done next?

Options:

A.

Deploy a team to develop the program management plan.

B.

Develop estimates for scope, resources, and cost.

C.

Identify the program management components, and develop the resource management plan.

D.

Review and update the benefits management plan and link it to program outcomes.

Buy Now
Questions 56

A multiyear program is ready to conclude. It has achieved all business objectives and is delivering its intended benefits. However, the program sponsor is not willing to sign the formal program closure acceptance document and the program continues to incur operational costs.

What should the program manager do next?

Options:

A.

Ask the finance department to increase the program budget

B.

Escalate the issue to the program governance board

C.

Ask key stakeholders to influence the program sponsor

D.

Direct component project managers to archive all relevant project documents

Buy Now
Questions 57

What does CPI value less than 1.0 indicates?

Options:

A.

Cost overrun for work completed

B.

Scheduled performance is great

C.

Cost underrun of performance to date

D.

Cost for completed work is as per estimate

Buy Now
Questions 58

A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity?

Options:

A.

Program risk register

B.

Program scope management plan

C.

Program risk management plan

D.

Component project risk register

Buy Now
Questions 59

A program manager initiates a new global program to create a higher level of protection for a company ' s intellectual property. The company exhibits a relaxed culture and environment, and is intolerant of processes to the point of being considered process-adverse. However, the company ' s culture is tolerant of long-term program activities, provided there is continuous progress on improving the protection of its intellectual property. Expectations for rapid progress are low.

What should the program manager do next?

Options:

A.

Tailor program sponsor and stakeholder engagement and communications activities to meet the company ' s expectations

B.

Insist on maintaining a set of tightly controlled stakeholder register and engagement plan documents to meet expectations

C.

Provide detailed information to the most influential program sponsors and stakeholders

D.

Ensure that the component stakeholders have the appropriate level of communications required to meet their needs

Buy Now
Questions 60

After taking over a program, a program manager reviews the program’s status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs. The program manager establishes earned value (EV) metrics and determines that the program has a budget of US$2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000.

Based on this information, the program manager determines which of the following?

Options:

A.

The schedule is US$30,000 under budget

B.

The cost is US$20,000 under budget

C.

The schedule is US$10,000 over budget

D.

The cost is US$20,000 over budget

Buy Now
Questions 61

What is the formula to determine earned value (EV) for a program?

Options:

A.

Percent complete times percent remaining in the program

B.

Percent completes time the program cost estimate

C.

Percent complete times the program budget at completion

D.

Percent complete times the program cost of labor and materials

Buy Now
Questions 62

A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?

Options:

A.

Reactionary risks

B.

Chain risks

C.

Secondary risks

D.

In flux risks

Buy Now
Questions 63

Which of the following documents is described in the statement below?

" It is a type of procurement document used to request proposals from prospective sellers of products or services. "

Options:

A.

Request for information

B.

Request for quote

C.

Request for proposal

D.

Request for bid

Buy Now
Questions 64

You are the program manager for your organization and are planning the roles and responsibilities in your program. You would like to create a RACI chart for the program work. What does RACI mean?

Options:

A.

It is a roles and responsibilities chart that uses responsible, accountable, consult, and inform responsibilities as the chart legend.

B.

It is a roles and responsibilities chart that uses responsible, action, consult, and interest responsibilities as the chart legend.

C.

It is a roles and responsibilities chart that uses resource, action, contribute, inform responsibilities as the chart legend.

D.

It is a roles and responsibilities chart that uses responsible, accountable, contribute, and inform responsibilities as the chart legend.

Buy Now
Questions 65

A program manager joins a team during its preparation phase.

What should the program manager do to obtain formal sponsor approval to begin the benefits delivery phase?

Options:

A.

Develop the program management plan based on the organization ' s strategic plan.

B.

Write the program charter, including the program mission statement and stakeholder engagement plan.

C.

Define a high-level program roadmap of milestones and schedules supported by a preliminary estimate.

D.

Identify and document the anticipated program benefits in the benefits management plan.

Buy Now
Questions 66

What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

Options:

A.

Project Management Information System

B.

Integrated Change Control

C.

Scope Verification

D.

Configuration Management System

Buy Now
Questions 67

A program manager is identifying and verifying risks as outlined in the risk management plan.

The results will be recorded in which of the following?

Options:

A.

Risk register

B.

Risk monitoring and control

C.

Risk response planning

D.

Risk mitigation strategy

Buy Now
Questions 68

Stakeholders make ad-hoc requests on a routine basis. This causes duplication of reporting and communication gaps that affect the program ' s performance.

To resolve this situation, which of the following must go through critical review and change?

Options:

A.

Program Benefits Management domain

B.

Stakeholder communications requirements

C.

Program communications report

D.

Program communications management plan

Buy Now
Questions 69

After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.

What should the program manager do next?

Options:

A.

Accelerate the projects and components of the program that replace the two legacy systems.

B.

Analyze the impact of accelerating the program, and present the pros and cons to the program sponsor.

C.

Identify the parts of the program that need to be accelerated and, if it is cost effective and increases benefits realization, implement the change.

D.

Create several " what-if " scenarios of alternatives to present to the program sponsor.

Buy Now
Questions 70

A software company ' s program manager is conducting closing procedures for a program. At the last steering

committee meeting, realized benefits were presented to the program governance board. What should the program manager do next?

Options:

A.

Begin transitioning program resources, and update the resource and program management plans to reflect the change in the program ' s status.

B.

Initiate knowledge transfer with the receiving organization, and establish the program integration management plan.

C.

Update the financial, stakeholder, and contract management plans, and archive them in the program information repository.

D.

Obtain sponsoring organization approval to begin closeout procedures to transition benefits sustainment to the supporting organization.

Buy Now
Questions 71

You are the program manager for your organization. Your program has recently completed its program scope and you ' ve transferred the benefits to the operations of your organization. Before your program is considered closed you must complete some forms and procedures as required by your organization. The requirements to complete the forms and paperwork are also known as what?

Options:

A.

Program administrative closure

B.

Enterprise environmental factors

C.

Closing processes

D.

Organizational process assets

Buy Now
Questions 72

An infrastructure program has 20 projects. The first half of these projects incurred multiple change orders and failed to be completed on time. The program manager meets with the project managers to discuss lessons learned and to understand the challenges. During the meeting, the project managers complain that key risks and a lack of resources resulted in missing deadlines.

What should the program manager do to ensure that the remaining 10 component projects stay on track?

Options:

A.

Rebaseline the remaining component projects.

B.

Develop a change management strategy.

C.

Update the program management plan.

D.

Schedule weekly meetings with the project managers.

Buy Now
Questions 73

Your program exists within a matrix structure. Your program has eight projects that all share resources from around the organization. You are concerned that some of the project team members may be over allocated and want to create a chart that will reflect the utilization of resources. What kind of chart can show the utilization of project team members used in your program?

Options:

A.

Resource network diagram

B.

Resource breakdown structure

C.

Resource histogram

D.

Pareto chart

Buy Now
Questions 74

Which of the following risk identification techniques is described in the statement below?

" It is used to gather information where participants don ' t know each other nor do they have to be present at the same location. "

Options:

A.

Brainstorming

B.

Delphi

C.

SWOT analysis

D.

Assumptions analysis

Buy Now
Questions 75

You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the schedule performance index (SPI) for this program?

Options:

A.

Negative ten percent B. .75

B.

$300,000 D. $225,000

Buy Now
Questions 76

A program manager is leading a program to transform an organization ' s sales and customer service operations by introducing a new customer relationship management (CRM) solution. As the program progresses, the sponsor and other stakeholders are satisfied with the pace of the program ' s performance.

A stakeholder from the sales department now requests a new feature to integrate the CRM platform with another application. The program manager advises that this is out of scope, as it will require analysis and development and be a project on its own. The program manager then requests additional funding via the formal change management process and the new scope is approved.

What should the program manager do next?

Options:

A.

Secure additional approvals from senior stakeholders.

B.

Assign a new project manager to own the delivery of the new project.

C.

Redefine the priorities of the existing program components to ensure optimal resource allocation and management of interdependencies.

D.

Discontinue one of the existing program components, and reallocate all of that component ' s resources to the newly approved project.

Buy Now
Questions 77

Program management has several themes that the program manager must be aware of. Which one of the following is not a program management theme?

Options:

A.

Benefit management

B.

Stakeholder management

C.

Program governance

D.

Organizational planning

Buy Now
Questions 78

A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals. A materials supplier informs the program manager that when this agreement is finalized, it will shorten the product’s delivery time.

What should the program manager update first?

Options:

A.

Procurement management plan

B.

Benefits register

C.

Risk register

D.

Benefits management plan

Buy Now
Questions 79

A project manager in your program is using progress elaboration as part of their planning approach. This approach is also known as what planning methodology?

Options:

A.

Waterfall management

B.

Rolling wave planning

C.

Scope refinements

D.

Incremental planning

Buy Now
Questions 80

A program with six projects has been running for three years. The company’s procurement and contracts department has compiled a qualified seller list. The program manager determines that one of the projects must be outsourced.

The program manager will use the qualified seller list to do which of the following?

Options:

A.

Plan a proposal evaluation system

B.

Prepare the program procurement management plan

C.

Perform the required program budget updates

D.

Issue requests for proposals

Buy Now
Questions 81

A large automaker begins a program to create the next-generation car. As the program team is composed, key stakeholders are identified.

Key stakeholders for the program should include which of the following?

Options:

A.

Potential customers, government regulatory agencies, and competitors

B.

Project management office (PMO), third-party contractors, and agents

C.

Local car dealers, factory workers, and corporate officers

D.

Vice president of logistics, potential customers, and corporate executives

Buy Now
Questions 82

You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them. Which of the following processes are you on?

Options:

A.

Report Program Performance

B.

Monitor and Control Program Scope

C.

Monitor and Control Program Schedule

D.

Monitor and Control Program Performance

Buy Now
Questions 83

The program manager leads a medical billing system integration program for company A, a health services provider. Company A acquires smaller company X, which delivers health services strategically aligned with company A.

Company X uses a different billing approach than company A. Company A ' s chief information officer (CIO) seeks counsel on which solution would be the better option moving forward, requesting the program manager ' s assistance.

How should the program manager respond to the CIO ' s request?

Options:

A.

Document the resources required to implement the recommended solution and demonstrate how this solution will save the company money.

B.

Find similar examples of the preferred approach and ask the project teams to document why the preferred approach is better

C.

Gather the costs and benefits associated with each option and recommend the appropriate solution defining why the selected approach is better.

D.

Conduct a thorough stakeholder analysis and develop a program management plan to implement the appropriate solution for both companies.

Buy Now
Questions 84

Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder ' s opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?

Options:

A.

Resource breakdown structure

B.

Resource management chart

C.

Stakeholder analysis chart

D.

RACI chart

Buy Now
Questions 85

At the beginning of the second year of a five-year strategic cycle, the program management team attends a checkpoint session to review the state of the company’s strategy. During the previous year, the company needed to comply with new government regulations that impacted this strategy.

Based on this information, what should the program manager do?

Options:

A.

Update the program management, benefits management, and risk management plans, and modify priorities and interdependencies.

B.

Meet with stakeholders, and modify the program roadmap to comply with the new regulations and ensure strategic alignment.

C.

Obtain stakeholder approval to stop or postpone programs that fail to comply with the new regulations, and modify the program roadmap.

D.

Review resource capacity and capability, program priorities, and interdependencies, and create a change request to modify the program roadmap to ensure strategic alignment.

Buy Now
Questions 86

A sponsor decides that the business environment is unfavorable for continuation of a program. The sponsor asks that the program be closed.

What items should be completed as part of the program’s final report?

Options:

A.

Lessons learned, successes and failures, and financial and performance assessments

B.

Final updates to the benefits register, successes and failures, and resource disposition

C.

Financial and performance assessments, successes and failures, and reason(s) for program closure

D.

Knowledge transition, successes and failures, and reason(s) for program closure

Buy Now
Questions 87

After attending a technology exposition, an influential stakeholder believes that integrating a new technology into the program will increase benefits and help shorten the schedule. The stakeholder asks the program manager to immediately include the new technology into the program.

What should the program manager do next?

Options:

A.

Assess the new technology and discuss the results with the program steering committee to determine next steps.

B.

Start the change management process and submit a change request to integrate the new technology.

C.

Inform the stakeholder that the program will not be changed until proof of concept (PoC) is completed.

D.

Research the new technology and begin its integration during the next development cycle.

Buy Now
Questions 88

A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end. What should be completed first to close all appropriate contracts?

Options:

A.

Certify contract completion

B.

Conduct a procurement audit to review the procurement process

C.

Assess all contracts to ensure all agreed conditions are met

D.

Review contract management plan for completeness

Buy Now
Questions 89

Terri is the program manager for her organization and she ' s working with Alice, a project manager in her program. Alice calls Terri and insists that she add a change to program scope. Terri agrees that the change should be entertained. What must Alice do to move forward with her change request?

Options:

A.

Add the change to the program scope herself, as she is a project manager

B.

Add the change request to the scope and complete integrated change control

C.

Document the change request in a change request form.

D.

Create a change request charter justifying the change request

Buy Now
Questions 90

Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?

Options:

A.

Decompose the program work based upon available resources

B.

Decompose the program to the work package level

C.

Decompose the program to the architecture baseline level

D.

Decompose the program at a level sufficient to achieve control

Buy Now
Questions 91

A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of US$1 million.

Since the shutdown was not anticipated, what should the program manager do first?

Options:

A.

Implement the appropriate risk response plan and inform the stakeholders of the planned actions.

B.

Utilize contingency reserves to hire contractors, which will accelerate the schedule to meet the original milestone.

C.

Evaluate the impact, reassess the program risk, and determine options to be presented to the governance board.

D.

Collaborate with the sponsor to determine options and negotiate a new date for the milestone.

Buy Now
Questions 92

Your program creates a byproduct that you could sell to a client. The cost of the byproduct would offset the cost of the program by nearly $7,500 per month. This is an example of which positive risk response?

Options:

A.

Sharing

B.

Enhance

C.

Exploiting

D.

Accepting

Buy Now
Questions 93

A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict.

What technique could the program manager use to gain more input from this project manager?

Options:

A.

Institute an incentive program to create competition among the team members.

B.

Make the project manager share an office with a more assertive team member.

C.

Solicit ideas from each team member individually, giving each person a chance to express their opinions.

D.

Create an online message board so team members can see and respond to everyone’s ideas.

Buy Now
Questions 94

External resources are required for a program. The program manager receives bids from multiple vendors and

presents the top vendor to the program governance board. One program governance board member asks the program manager to select a vendor that was dismissed early in the selection process because they were not on the approved vendor list. The program manager learns that this program governance board member has a personal connection to this vendor.

What should the program manager do?

Options:

A.

Add the vendor to the approved list

B.

Report an ethics violation

C.

Agree to engage the vendor due to the program governance board member ' s program influence

D.

Initiate a new vendor selection bid process

Buy Now
Questions 95

A component project of a program is completed, and will provide the intended incremental benefits.

How should the program manager proceed with the component transition?

Options:

A.

Update the program stakeholder engagement plan with stakeholders from the transition organization

B.

Define the component project’s business value in the benefits management plan

C.

Update the program roadmap to reflect completion of a key end-point objective

D.

Initiate a program change request to close out the component project

Buy Now
Questions 96

Which of the following can be used to help you or other project managers on future projects?

Options:

A.

Sponsor

B.

Charter

C.

Stakeholder

D.

Documentation

Buy Now
Questions 97

Which earned value management formula can help you determine how likely it is that you ' ll complete the program based on the amount of cash left in the program budget?

Options:

A.

Estimate at completion

B.

Variance at completion

C.

To-complete performance index

D.

Estimate to complete

Buy Now
Questions 98

A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list. During the final review of the RFPs, the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company policies, the program manager is concerned about a conflict of interest.

What should the program manager do?

Options:

A.

Select the best bid from the prequalified vendor list.

B.

Accept the bid from the new vendor and document the decision.

C.

Advise the sponsor of a possible conflict of interest prior to awarding the bid.

D.

Add the new vendor to the prequalified list and replace the project manager.

Buy Now
Questions 99

A team member has made a mistake during the installation of a fixture in your program. You have requested

that the team member should correct the problem so that the fixture is installed properly. Once the team members has corrected the problem what action should be taken next?

Options:

A.

Defect repair validation

B.

Lesson learned documentation

C.

Corrective actions

D.

Preventive actions

Buy Now
Questions 100

Your program has 121 stakeholders that you ' ll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You ' ll also need which one of the following as an input to the information distribution process in your program?

Options:

A.

Change requests

B.

Earned value management results

C.

Stakeholder analysis plan

D.

Performance reports

Buy Now
Questions 101

You are the program manager for your organization. You have proposed a program that will cost $750,000

and will last for four years. Management is concerned with the cost of the program in relation to the return your

program will bring. If the rate of return is six percent what is the minimum value your project should return in four years based on the investment of the program?

Options:

A.

$750,000

B.

$795,000

C.

$750,001

D.

$946,857

Buy Now
Questions 102

A project manager in your program has estimated the cost of a program to be $145,000. As the project manager ' s project comes close to completion, the project manager realizes that he has still $27,876 left in his project budget. He decides to add some additional features to the project ' s deliverables in an effort to use the remaining budget. These additions will add value to the project and the project customer is likely to enjoy these new features. This is an example of what term?

Options:

A.

Gold plating

B.

Errors and omissions

C.

Expert judgment by the project manager

D.

Value added change

Buy Now
Questions 103

You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?

Options:

A.

Contract administration

B.

Resource management

C.

Resource control

D.

Procurement management

Buy Now
Questions 104

A program with objectives that impact a large segment of the population receives negative commentary from organizations representing the public interest.

What action should the program manager take first?

Options:

A.

Rework the stakeholder engagement plan to foster better relationships with the affected stakeholder groups.

B.

Review the stakeholder register to determine the ability of the affected stakeholder group(s) to affect program outcomes.

C.

Assess the risk of sustained negative media coverage.

D.

Discuss the issues with the governance board to determine next steps.

Buy Now
Questions 105

In which of the following processes is the program charter created?

Options:

A.

Establish Program Financial Framework

B.

Plan Program Scope

C.

Initiate Program

D.

Develop Program Management Plan

Buy Now
Questions 106

A multi-year complex program will deliver advanced driver assistance system (ADAS) components for autonomous vehicles. Several key stakeholders are concerned because they have not been regularly involved with the program and do not understand the program ' s benefits.

What should the program manager do to address these key stakeholders ' concerns?

Options:

A.

Meet with the stakeholders and update the stakeholder map.

B.

Create a progress report to share with stakeholders after the next status meeting.

C.

Capture stakeholder expectations, and revise the stakeholder engagement plan.

D.

Update the communications management plan after meeting with the program steering committee.

Buy Now
Questions 107

You are the program manager for your organization. When a project in your program is completed, who will need to sign the certificate of completion?

Options:

A.

The project manager

B.

The program customer

C.

The program stakeholders

D.

The project management team

Buy Now
Questions 108

You are a program manager of a program. You are required to compile performance data of your program. These data will be sent to relevant stakeholders. You are reviewing the status reports of all projects including the costs, schedule, scope, risks, and other performance data.

In which of the following processes are you working on?

Options:

A.

Plan Communication

B.

Distribute Information

C.

Report Program Performance

D.

Monitor and Control Program Performance

Buy Now
Questions 109

A rapidly expanding IT company wants to mature its delivery methodology. It creates a benefits management plan that identifies formal program management governance as a key area that would add value.

What benefits would structuring work into programs bring to this organization?

Options:

A.

Delivery of initiatives and objectives through the alignment of portfolios

B.

Bundling of components or work to gain efficiencies unachievable if managed separately

C.

Increasing efficiencies by adhering to defined constraints to achieve specific activities

D.

Coordination of portfolio and project work by linking principles and practices

Buy Now
Questions 110

All of the following are benefits of a program except for which one?

Options:

A.

Projects can operate independently of one another.

B.

Resource management in a program allows resources to be shared across all projects in the program.

C.

The program manager can use the same approach in stakeholder management for all projects in the program.

D.

All projects follow the policies of the program and organization.

Buy Now
Questions 111

Complete the following phrase about quality management: Quality is into a program, not into a program.

Options:

A.

Built, inspected

B.

Planned, inspected

C.

Planned, controlled

D.

Executed, controlled

Buy Now
Questions 112

What document should you provide to the vendors if you ' re only interested for a set fee for their materials?

Options:

A.

IFB

B.

RFP

C.

RFI

D.

SOW

Buy Now
Questions 113

Which of the following is not a template element that is designed to make the project more effective?

Options:

A.

Description of the work packages

B.

Required resources and skills

C.

Required actions to complete the project scope

D.

Contract file

Buy Now
Questions 114

At what point in the project is the risk of failing to achieve the project objectives the greatest?

Options:

A.

During project planning

B.

During the project execution

C.

At the project start

D.

At the end of the project

Buy Now
Questions 115

You are the program manager for a construction program. In this program you are requiring that all workers adhere to the identified safety requirements. Some of the work in the program you ' ve decided is too risky for the program team members so you ' ve hired specialists to manage the dangerous work. The outsourcing of the dangerous work to a specialist is what type of risk response?

Options:

A.

Avoidance

B.

Mitigation

C.

Transference

D.

Enhancing

Buy Now
Questions 116

Hal is the program manager for his organization. He would like your organization to provide his program with 4 tons of pea gravel for a construction project in his program. Hal send you a statement of work and an IFB. What document should you provide to Hal?

Options:

A.

Invoice

B.

Proposal

C.

Bid

D.

Quote

Buy Now
Questions 117

Which of the following is NOT true regarding the program work breakdown structure (WBS)?

Options:

A.

It defines a program and groups the program ' s discrete work elements in a way that helps organize and define the total work scope of the program.

B.

It subdivides the program deliverables to work packages that are linked to the activities within the program.

C.

It defines all the work and only the required work for the program.

D.

It subdivides the program deliverables to work packages that are linked to the activities within the program.

Buy Now
Questions 118

You are the program manager for your project. You are working with the project managers regarding the procurement processes for their projects. You have ruled out one particular contract type because it is considered too risky for the program. Which one of the following contract types is usually considered to be the most dangerous for the buyer?

Options:

A.

Cost plus incentive fee

B.

Cost plus percentage of costs

C.

Time and materials

D.

Fixed fee

Buy Now
Questions 119

You are the program manager for your organization. As your program is being initiated there is some initial concern from the management about the utilization of resources in your program and the need for resources in their day-to-day roles in operations. Management has set a limit on your program that resources may only

work 20 hours per week on the program. What is this limit of resource hours in a time period known as?

Options:

A.

Resource leveling heuristic

B.

Resource requirements

C.

Program risk

D.

Resource utilization

Buy Now
Questions 120

Joan is the program manager for her organization. Management has asked her to create a centralized reporting system to capture information on program work, risks, changes, benefits management, and other aspects of the program. What solution can Joan implement to capture, communicate, and record the information management wants?

Options:

A.

Program management information system

B.

Program management integrated change control

C.

Change control systems

D.

Program management plan execution

Buy Now
Questions 121

You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you ' ll transfer the benefits of the program to the operations of your organization. Which program management plan defines this process?

Options:

A.

Operational transfer plan

B.

Program transition plan

C.

Benefits transfer plan

D.

Program closure plan

Buy Now
Questions 122

You are the program manager for your organization. Your program will create a new condominium in your community. There are several concerns about the condos including the timing, the local economy, the environment, and the proposed schedule. You and your team are creating the program management plan to address these concerns along with identifying the constituent projects that will build the structures and deliverables. What group will need to review your program plan to approve the plan before you may proceed in the work?

Options:

A.

The local government

B.

The change control board

C.

The stakeholders

D.

The program board

Buy Now
Questions 123

Which of the following types of floats are available? Each correct answer represents a complete solution. Choose two.

Options:

A.

Half float

B.

Full float

C.

Total float

D.

Free float

Buy Now
Questions 124

You are the program manager for the HQM Program. Your program has sixteen constituent projects around the world. You are requiring that each project manager and project management team use the same forms, software, and templates to create standardization in each project. What term is assigned to the forms, templates, and software that your program will provide for your projects?

Options:

A.

Program governance

B.

Project management assets

C.

Enterprise environmental factors

D.

Organizational process assets

Buy Now
Questions 125

A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase. Tracking and reporting of actual benefits realized is one part of the review.

What is the other part of the review?

Options:

A.

Tracking and reporting on benefits management plan

B.

Identifying factors influencing delivery of benefits

C.

Demonstrating that other stage gate requirements have been met

D.

Gathering additional stakeholders ' requirements

Buy Now
Questions 126

A program with 10 components is in the planning phase. Project managers who oversee the component projects request detailed schedules. These schedules will be merged into one document to create a master schedule.

What should the program manager do to ensure that the overall program life cycle will meet stakeholder needs and deliver planned benefits?

Options:

A.

Establish a quality review for the project schedules to ensure that resource leveling and baselines are followed and component projects are delivered on time

B.

Work with the project managers to decompose their schedules to minimize risk and better understand the dependencies and resource needs

C.

Decompose the component schedules to determine if work can be executed more quickly to deliver value earlier than planned

D.

Create a work breakdown structure (WBS) to align program execution with stakeholder expectations and the benefits management plan

Buy Now
Questions 127

Which of the following shows the ratio between a task ' s budgeted and actual costs?

Options:

A.

To-Complete Performance Index (TCPI)

B.

Schedule Variance (SV)

C.

Schedule Performance Index (SPI)

D.

Cost Performance Index (CPI)

Buy Now
Questions 128

June is the program manager for her organization. Management has asked June to create a visual mapping of the program scope so that all of the key stakeholders can see all of the elements of the program scope. June needs to create what kind of document to show all of the program deliverables based on the program scope?

Options:

A.

Program network diagram

B.

Program benefits mapping chart

C.

Program budget

D.

Program work breakdown structure

Buy Now
Questions 129

A program manager is appointed to manage a new program. The organization ' s leadership has specified a list of benefits that the program should deliver and has requested that the program manager determine when incremental benefits can be realized.

What should the program manager do first?

Options:

A.

Develop the benefits sustainment plan.

B.

Develop the program management plan.

C.

Develop the program roadmap.

D.

Develop the component project schedules.

Buy Now
Questions 130

You are the program manager for your organization and you are trying to determine the possible outcomes of

a risk event. You ' re analyzing the risk event ' s worst case scenario, most likely scenario, and optimistic scenario to simulate the possible affects of the risk on the program ' s cost, time, and scope ramifications. What simulation technique are you using in this situation?

Options:

A.

Monte Carlo simulation

B.

Sensitivity analysis

C.

Force field analysis

D.

Decision tree analysis

Buy Now
Questions 131

is the degree to which a set of inherent characteristics fulfills requirements.

Options:

A.

Scope

B.

Project phase

C.

Regulation

D.

Quality

Buy Now
Questions 132

Holly is the program manager for her program. She is creating with her team a plan that will address how the program team will achieve program goals based on who the program will need to interact with in the program. This plan should define all of the people, groups, and other entities the program needs to interact with in order to move the program forward. On what plan is Holly working?

Options:

A.

Stakeholder management plan

B.

Communications management plan

C.

Human resource management plan

D.

Interface management plan

Buy Now
Questions 133

Where are negative risks recorded?

Options:

A.

Negative risk register

B.

Risk management plan

C.

Risk register

D.

Issues log

Buy Now
Questions 134

You are the program manager for your organization. A new program is about to initiated and Marcy, your assistant, asks you about the themes that all new programs must map to. All of the following are themes that you can discuss with Marcy except for which one is not a program theme?

Options:

A.

Stakeholder management

B.

Requirements analysis

C.

Benefits management

D.

Program governance

Buy Now
Questions 135

Kelly ' s program is slipping on its schedule. Management is worried that the program will be late and this will cost the organization several thousand dollars in fines and penalties. They ' ve asked Kelly to use a schedule duration compression technique that will help the program finish on time. The technique that Kelly can use, however, should not add costs to the program. What duration compression technique should Kelly use in this instance?

Options:

A.

Crash the program

B.

Add lead time to the program

C.

Trim the program scope

D.

Fast track the program

Buy Now
Exam Code: PgMP
Exam Name: Program Management Professional (PgMP)
Last Update: May 14, 2026
Questions: 452

PDF + Testing Engine

$64.99  $185.69

Testing Engine

$49.99  $142.83
buy now PgMP testing engine

PDF (Q&A)

$54.99  $157.11
buy now PgMP pdf