Free Practice Questions for the CompTIA Project+ PK0-005 Exam (2026 Updated)
At Marks4sure, we are dedicated to providing IT professionals with the most accurate and reliable preparation materials for the CompTIA PK0-005 exam. To support your certification journey, we have made a selection of our premium 2026 Project+ practice questions and answers available completely free. You can take this practice test as many times as you need. Every question includes a detailed, expertly verified explanation to ensure you fully grasp the core security concepts before test day.
Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?
A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?
Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?
A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?
A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?
Which of the following is the best alternative to allow multiple users to edit a project plan in real time?
After a weekly status meeting, a project manager needs to prepare and distribute a document with a summary of all the topics discussed, agreements, and next steps. Which of the following documents should the project manager prepare?
A project manager is concerned about the performance of a developer who is struggling with the new coding language. Which of the following actions should the project manager take?
While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?
After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?
Which of the following concepts represents multiple resources interfaced to run reports?
A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?
For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?
During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?
A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?
A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the
following has the project manager identified?
During the planning phase, a project manager is mapping out the full scope, calculating task durations, and identifying dependencies. Which of the following is the best tool for the project manager to use?
A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following best describes this technique?
Which of the following best describes the reason a chat messaging service would be used as the primary form of communication for a project team?
A project manager and team are currently in the planning phase of a project. Which of the following should the team do during this phase?
A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?
Which of the following can help identify opportunities for future improvement following the successful closure of a project?
A project manager is receiving reports of the actual project expenditures and, based on this information, is making adjustments to the budget. In which of the following phases does this occur?
A company is adapting its strategy almost every quarter, and the product might be different at the end of the project. Which of the following is the best methodology for the project manager to use?
During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.
INSTRUCTIONS
Review the email with the latest updates sent by the project sponsor and respond in
the following order:
1. Select the best tool for tracking the server migration progress.
2. Select the new critical path.
3. Select the correct number of engineers required for the server migration phase.
If at any time you would like to bring back the initial state of the simulation, please click
the Reset All button.
Select the Appropriate Tool:


Select the new critical path.
Option A
Option B
Option C

A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to
identify the level of engagement among project team members. Which of the following would be the best tool for the project manager to use?
A software development team implemented an approved change but does not obtain the expected results. The team notifies the change control board (CCB) about the failed change. Which of the following control processes is being followed?
A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?
A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?
The sales department accidentally has access to all project files, including employee personal information. Which of the following security concepts is this violating?
A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?
A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?
A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?
A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).
A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?
During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?
An external developer working on a project at an hourly rate provides an invoice at the end of a month for 80 hours spent on a project. The project manager realizes that there were no tasks assigned to this developer last month. Which of the following actions should the project manager take first?
A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?
A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?
As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?
Which of the following can be used to determine whether a sample product is within an acceptable range?
After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?
A web designer is currently verifying that the website data is compliant. Which of the following data types will be protected after confirming that the controls are in place?
During a functional validation exercise, two end users request changes to the product that cannot be implemented without altering the already constrained project budget. The project manager convinces the end users to simplify the change request so it can be accomplished. Which of the following conflict resolution techniques did the project manager use?
A project manager working in a strong matrix organization was selected to manage a new project with trending technologies. During the kickoff meeting, one of the stakeholders mentions that the company has never worked with such technologies. Which of the following should the project manager do next?
Which of the following provides a layered approach to logging in to systems that contain an organization ' s most valuable intellectual property?
As part of a global project, the project manager wants to ensure there is no disruption in the day-to-day performance among project team members around the world Which of the following should the project manager consider doing as part of the project planning?
During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?
Project team members enter their time sheets into a system that also displays incurred project cost. Which of the following systems can perform this task?
Which of the following software programs would be BEST to use lo store information related to business transactions?
A project sponsor requires a system that is capable of providing integrated management of all the business ' s core functions. Which of the following systems is the project sponsor describing?
During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following:

Which of the following was the initial cause of the issue?
An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens ' complaints. Which of the following solutions would be BEST?
A company plans to install new servers. The project manager receives a notification that the manufacturer may be in financial trouble, so the servers will be sourced from another vendor. Which of the following risk management strategies should the project manager use?
A stakeholder called a project manager on the telephone to ask for a status report. Which of the following describe this type of communication? (Select two).
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?
During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?
A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following describes the grouping of the smaller components?
Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?
Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?
A project was selected for an audit years after the project closed. Which of the following is most likely to be needed for the audit?
As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?
Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?
During project initiation, a project manager is drafting a document that includes an outline of the high-level goals, objectives, milestones, and requirements. This document will be modified and finalized as more information becomes available. Which of the following best meets the requirements?
Which of the following best describes the reason a waterfall approach would be used for a project?
An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?
A project manager and team are reviewing a task that is supposed to take 9 days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional 5 days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project ' s timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?
A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?
A project team is reviewing the project plan and related documents and identifies tasks that could be spread into smaller deliverables. Which of the following documents should the team edit first?
A company purchases new software. The project manager needs to present the new software’s features to the stakeholders. Which of the following meeting types should the project manager and stakeholders have?
A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?
A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?
Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?
A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?
Given the following information:
Which of the following represents the critical path of the project?
A project manager is responsible for implementing a large, centralized repository that stores raw information from various sources in a structured and organized way. Which of the following should the project manager implement?
A team found a deficiency in an application and is proposing improvements, but the sponsor requests a business case. Which of the following best describes the intended objective of the business case?
A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?
A team member is not completing deliverables on time or responding to emails while the project manager is on vacation. Which of the following actions should the technical lead take?
Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?
The project manager sends individual messages to team members about what must be accomplished. However, the team communicates confusion about the tasks assigned. Which of the following communication methods would be best to use?
A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?
During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?
Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?
Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?
During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?
A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?
A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?
Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users ' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?
A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?
During project initiation, a project manager needs to establish the communication channel that will be used to deliver weekly presentations to stakeholders who are across the country. Which of the following would be the best communication channel to use?
A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
The PM is concerned with multiple copies of the same file causing confusion. Which of the following would prevent this issue?
Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?
As a result of an unpredicted risk, a project manager is documenting a request in the change control log. Which of the following change control processes should the project manager do last?
Which of the following are primary features provided by a standard laaS solution? (Select two).
A principle states 80% of the issues are the result of 20% of the causes. Which of the following types of diagrams is based on this principle?
A project team is developing an application that will allocate a building ' s parking spaces. The building owner does not agree with using corporate colors in the application and has blocked
the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?
Participant attendance has been poor at the last few weekly meetings. The project manager wants to validate who the participants should be, how often the meetings should occur, and on which day and at what time the meeting should be held. Which of the following is the best place to validate this information?
Which of the following situations would require a project manager to revise the communication plan during a project ' s execution?
A project manager is meeting with stakeholders to identify objectives and success criteria. Which of the following artifacts is the project manager working on?
Given the information in the chart,

which of the following techniques should the project manager use to improve the project schedule in Sprint 1?
Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?
Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).
Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?
A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?
A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?
The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?
A project manager is managing a virtual team across the country. As reported in the retrospective, the team morale has decreased due to additional production issues. Which of the following meeting tools is the best option to record results in the retrospective?
A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?
Which of the following should be the PRIMARY basis for establishing metrics that measure the effectiveness of an information security program?
Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?
A project manager is comparing the documentation attached to invoices from main vendors with the requirements described in the SOW in order to decide if all are correct. Which of the following best describes what is being performed?
Which of the following provides the best justification for undertaking a project?
A project manager makes a list of the smallest activity components in the project. Which of the following is the project manager building?
The executive leadership of an agile company has launched a new strategy. This new strategy impacts new features that are in development with the project team. Which of the following describes what the team should do next?
A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?

