Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PK0-005 CompTIA Project+ Certification (2026) Questions and Answers

Questions 4

Which of the following is the best example of CapEx?

Options:

A.

Taxes

B.

Vehicles

C.

Salaries

D.

Utilities

Buy Now
Questions 5

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Options:

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Buy Now
Questions 6

After a weekly status meeting, a project manager needs to prepare and distribute a document with a summary of all the topics discussed, agreements, and next steps. Which of the following documents should the project manager prepare?

Options:

A.

Minutes

B.

Project presentation

C.

Memorandum

D.

Issue log

Buy Now
Questions 7

A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?

Options:

A.

Mitigate

B.

Transfer

C.

Accept

D.

Share

Buy Now
Questions 8

A project was selected for an audit years after the project closed. Which of the following is most likely to be needed for the audit?

Options:

A.

Signed contracts

B.

Archived documentation

C.

Project closeout report

D.

Lessons learned

Buy Now
Questions 9

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

Options:

A.

Critical paths

B.

Resources

C.

Milestones

D.

Work breakdown structures

Buy Now
Questions 10

A project manager requests the testing team to figure out if a website allows multiple users to be signed in at the same time. Which of the following testing methods would be best for the testing team to use?

Options:

A.

Regression

B.

Unit

C.

Stress

D.

Smoke

Buy Now
Questions 11

A project team is reviewing the project plan and related documents and identifies tasks that could be spread into smaller deliverables. Which of the following documents should the team edit first?

Options:

A.

Risk assessment

B.

Preliminary scope statement

C.

Work breakdown structure

D.

Milestone chart

Buy Now
Questions 12

Which of the to and allowing interactive feedback from a project team?

Options:

A.

Text message

B.

Chat

C.

Email

D.

Videoconference

Buy Now
Questions 13

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

Options:

A.

Validate against the scope statement and ask for sign-off.

B.

Run a control chart to ensure the quality of the deliverables.

C.

Review the risk register and close up residual risks.

D.

Start the training and handoff for the operations team.

Buy Now
Questions 14

A stakeholder called a project manager on the telephone to ask for a status report. Which of the following describe this type of communication? (Select two).

Options:

A.

Formal

B.

Internal

C.

Informal

D.

Verbal

E.

Indirect

F.

External

Buy Now
Questions 15

The quarterly financial report displays losses from a project even though the project was completed successfully several weeks ago. Which of the following actions should the project manager perform next?

Options:

A.

Remove access.

B.

Complete the project sign-off.

C.

Release the resources.

D.

Outline the lessons learned.

Buy Now
Questions 16

Which of the following contract types in project procurement has the highest risk for the buyer?

Options:

A.

Time and material

B.

Cost-plus

C.

Fixed-price

D.

Unit price

Buy Now
Questions 17

Which of the following best describes why conducting lessons learned sessions is important?

Options:

A.

To discuss as a team how to improve and eliminate all the issues in the project

B.

To conduct the team’s performance evaluation and document the results

C.

To report all the mistakes and ensure others do not make the same ones

D.

To document what went right and wrong, as well as possible improvements

Buy Now
Questions 18

Which of the following can be used to determine whether a sample product is within an acceptable range?

Options:

A.

Scatter diagram

B.

Velocity chart

C.

Control chart

D.

Fishbone diagram

Buy Now
Questions 19

Participant attendance has been poor at the last few weekly meetings. The project manager wants to validate who the participants should be, how often the meetings should occur, and on which day and at what time the meeting should be held. Which of the following is the best place to validate this information?

Options:

A.

Project communication plan

B.

Project management plan

C.

Project business case

D.

Project schedule

Buy Now
Questions 20

A project manager is taking notes along with gathering feedback about a prior project in order to consider known issues with a project enhancement. Which of the following best describes the plan that the project team is working on?

Options:

A.

A plan for capturing issues and conflicts in a project ' s knowledge base

B.

A plan for avoiding potential issues that may arise during project execution

C.

A plan for documenting the outcomes of the project

D.

A plan for addressing and resolving identified issues once the project has been completed

Buy Now
Questions 21

A stakeholder raises a concern that a certain important functionality might be missing and asks the PM to submit a change request so it can be included. The PM is confident the functionality is included. Which of the following has the PM most likely checked?

Options:

A.

Risk register

B.

Detailed scope statement

C.

Requirements Traceability Matrix

D.

Task board

Buy Now
Questions 22

When assigning access, classifying information based on sensitivity is referred to as:

Options:

A.

Digital security

B.

Physical security

C.

Data security

D.

Operational security

Buy Now
Questions 23

Which of the following situations would require a project manager to revise the communication plan during a project ' s execution?

Options:

A.

A change is approved that impacts the project schedule and budget

B.

The test results are not as expected

C.

The team is unclear which meetings they should attend

D.

A stakeholder requests some changes to the scope

Buy Now
Questions 24

Which of the following best describes the difference between the current state and the desired future state in project management?

Options:

A.

The current state is a high-level view of the project scope, and the desired state is what is happening right now.

B.

The current state is where the business is now, and the desired state is where the project is going to take the business.

C.

The current state is a high-level view of the project scope, and the desired future state is the specific outcome the business wants.

D.

The current state defines the specific outcome the business wants, and the desired state documents what is happening now that prevents it.

Buy Now
Questions 25

Which of the following is a capital expense?

Options:

A.

Building lease

B.

Building purchase

C.

Building maintenance

D.

Building insurance

Buy Now
Questions 26

During a gate review meeting, the deliverable was rejected by the customer.

INSTRUCTIONS

Review the dashboard.

• Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.

• Part 2: Select the proper document(s) to be updated.

If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Part 1:

PK0-005 Question 26

Part 2:

PK0-005 Question 26

Options:

Buy Now
Questions 27

A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?

Options:

A.

Rational Unified Process

B.

Waterfall

C.

Agile

D.

DevOps

Buy Now
Questions 28

Which of the following pieces of data are examples of Pll?

Options:

A.

Medical record and test result values

B.

IP address and email address

C.

Name and year of birth

D.

X-ray and blood type

Buy Now
Questions 29

Which of the following best describes the reason a waterfall approach would be used for a project?

Options:

A.

The executive team still has no clear requirements for the product.

B.

The executive team is looking to review the product only once after the product is finalized.

C.

The executive team is expecting constant delivery of components.

D.

The executive team wants to reduce the budget for development.

Buy Now
Questions 30

A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following best describes this technique?

Options:

A.

Demonstration

B.

Workshop

C.

Brainstorming

D.

Focus group

Buy Now
Questions 31

An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?

Options:

A.

Transfer

B.

Mitigate

C.

Avoid

D.

Accept

Buy Now
Questions 32

A senior PM is working on the development of a tax application and focuses efforts to create an environment to facilitate and motivate teamwork. The team members seem to be in the storming phase. Which of the following best describes the team life cycle?

Options:

A.

The team members are in a conflict that affects their relationship.

B.

The team members perform as a well-organized unit.

C.

The team members have met and are learning about the project.

D.

The team members have completed the work and are moving on from the project.

Buy Now
Questions 33

During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?

Options:

A.

Work breakdown structure

B.

Project charter

C.

Quality plan

D.

Solution design

Buy Now
Questions 34

A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?

Options:

A.

Resource allocation

B.

Communication security

C.

Technological factors

D.

Cultural differences

Buy Now
Questions 35

During a project kickoff meeting, the project manager wants to set expectations for all of the team members. Which of the following actions should the project manager take to accomplish this goal?

Options:

A.

Assign tasks and responsibilities to the team members

B.

Provide an overview of the project objectives and timeline

C.

Develop a project communication plan

D.

Set a meeting cadence for the rest of the project

Buy Now
Questions 36

A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?

Options:

A.

Secure folder

B.

Real-time, multiauthoring editing software

C.

Digital whiteboard

D.

Wiki knowledge base

Buy Now
Questions 37

During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?

Options:

A.

Obtain details from the owner of the project.

B.

Update the critical path for the project.

C.

Apply contingency reserves.

D.

Reestimate epic user stories.

Buy Now
Questions 38

After releasing an application into production, a major defect is detected. The project team implements a work-around that fixes the issue for now. Which of the following should the team do next?

Options:

A.

Provide the change to the CCB.

B.

Perform root cause analysis.

C.

Escalate to the project steering committee.

D.

Update the risk register.

Buy Now
Questions 39

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

Options:

A.

Decline because it is not included in the project scope.

B.

Assess the impact of the request and create a change request

C.

Create new functional and non-functional requirements for mobile devices.

D.

Revise the baseline of the project plan by adding the new requirements.

Buy Now
Questions 40

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

Options:

A.

Decision board

B.

Whiteboard

C.

Task board

D.

Dashboard

Buy Now
Questions 41

After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?

Options:

A.

Smoke test

B.

Stress test

C.

Penetration test

D.

Regression test

Buy Now
Questions 42

During a functional validation exercise, two end users request changes to the product that cannot be implemented without altering the already constrained project budget. The project manager convinces the end users to simplify the change request so it can be accomplished. Which of the following conflict resolution techniques did the project manager use?

Options:

A.

Collaborating

B.

Smoothing

C.

Avoiding

D.

Compromising

Buy Now
Questions 43

A project is about to start; however, the client is uncertain about the desired details for the final product. Which of the following methodologies should the project manager use?

Options:

A.

Agile

B.

SDLC

C.

Waterfall

D.

PRINCE2

Buy Now
Questions 44

Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?

Options:

A.

Communicate with the affected stakeholders.

B.

Initiate a formal change request to modify the cost

C.

Adjust the scope to stay within the cost.

D.

Set a new cost using a lightweight estimation method.

Buy Now
Questions 45

A new project manager takes over a project midway through the schedule. Which of the following should the project manager do first before continuing the project?

Options:

A.

Access project artifacts.

B.

Arrange a brainstorming session.

C.

Conduct a kickoff meeting.

D.

Establish communication channels.

Buy Now
Questions 46

A data center is under construction, and the project manager wants to address the risks related to physical injuries. Which of the following is the best risk response method for this scenario?

Options:

A.

Avoid injuries by using robots to perform tasks.

B.

Transfer risk to an insurance company.

C.

Mitigate risk by training the construction workers.

D.

Accept the risks inherent to construction.

Buy Now
Questions 47

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

Options:

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Buy Now
Questions 48

Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?

Options:

A.

Concept of operations

B.

WBS

C.

Integrated master schedule

D.

RACI

Buy Now
Questions 49

A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?

Options:

A.

Project scope

B.

Quality plan

C.

Contract obligations

D.

Work breakdown structure

Buy Now
Questions 50

A PM is reviewing objectives for a project in a new industry. Which of the following items should the PM review first?

Options:

A.

Applicable regulations and standards

B.

Relevance to the global environment

C.

Company vision, mission, and values

D.

Impact to the corporate brand

Buy Now
Questions 51

Which of the following best describes a benefit of the CI/CD process?

Options:

A.

Software delivery is sped up without compromising quality

B.

Incremental changes are done at the end of the project

C.

The software is integrated with other projects easily

D.

Updates are released every sprint

Buy Now
Questions 52

During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:

Average worked hours

Which of the following describes the result?

Options:

A.

A negative correlation exists between the number of mistakes and the working hours.

B.

No correlation exists between the number of mistakes and the working hours.

C.

A low correlation exists between the working hours and the number of mistakes.

D.

A positive correlation exists between the number of mistakes and the working hours.

Buy Now
Questions 53

A project ' s QA team needs to validate functionality in a timely and cost-effective way to ensure good coverage every time a new change is integrated. Which of the following test should the team execute?

Options:

A.

Sanity

B.

Manual

C.

Automated

D.

Regression

Buy Now
Questions 54

Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?

Options:

A.

Social engineering

B.

Phishing

C.

Spoofing

D.

Hacking

Buy Now
Questions 55

A project sponsor tells the project manager that new regulatory environment changes are coming in the next month. Which of the following should the project manager do next?

Options:

A.

Register the issue in the issue log.

B.

Provide the change to the CCB.

C.

Implement a work-around.

D.

Add risk into the risk register.

Buy Now
Questions 56

Which of the following best represents an intellectual property breach?

Options:

A.

Internal developers use code from a legacy in-house system to develop a new solution for the marketing department.

B.

The price list to end customers was stored on a stolen external hard drive.

C.

A service provider that worked on a project uses the developed software on a project for a new customer.

D.

Customer data is stored on a shared network drive that is accessible by employees from all departments.

Buy Now
Questions 57

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).

Options:

A.

Risk report

B.

Defect log

C.

Issue log

D.

Backlog

E.

Change log

F.

Progress report

Buy Now
Questions 58

A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?

Options:

A.

Quality assurance

B.

Organizational branding restrictions

C.

State privacy acts

D.

Country legal regulations

Buy Now
Questions 59

A project manager is responsible for implementing a large, centralized repository that stores raw information from various sources in a structured and organized way. Which of the following should the project manager implement?

Options:

A.

Shared folder

B.

Infrastructure

C.

Multitiered architecture

D.

Data warehouse

Buy Now
Questions 60

During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?

Options:

A.

Waterfall method

B.

Simulation method

C.

Precedence diagramming method

D.

Cost ratio analysis

Buy Now
Questions 61

Which of the following BEST identifies the intent and purpose of a project closeout report?

Options:

A.

To provide documentation of lessons learned

B.

To document variances from the initial project baseline

C.

To validate that a project has been successfully completed

D.

To release resources and terminate all access rights

Buy Now
Questions 62

Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?

Options:

A.

Progress reporting

B.

Meeting minutes

C.

Team touch points

D.

Change management

Buy Now
Questions 63

Which of the following is required to provide a hardware installation with a Tier 5 redundancy level?

Options:

A.

Storage project

B.

Computer services project

C.

Database project

D.

Multitiered architecture project

Buy Now
Questions 64

A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?

Options:

A.

Use an on-premises project management scheduling tool.

B.

Limit access to members of the project team.

C.

Mandate overtime to get the project completed sooner.

D.

Ensure all team members have signed a non-disclosure agreement.

Buy Now
Questions 65

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

• Purpose

• Scope of work

• Location of work

• Period of performance

• Deliverables schedule

• Applicable standards

• Acceptance criteria

• Special requirements

• Payment schedule

Which of the following documents did the client provide to the project manager?

Options:

A.

RFP

B.

WBS

C.

SLA

D.

SOW

Buy Now
Questions 66

Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?

Options:

A.

The scope of the project deliverable is clearly defined.

B.

There is a non-disclosure agreement in place.

C.

There are multiple requirements for the product.

D.

The PM wants to simplify the logistics of the required product.

Buy Now
Questions 67

During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

A)

B)

PK0-005 Question 67

C)

PK0-005 Question 67

D)

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Buy Now
Questions 68

A new stakeholder has joined a project and has a different vision of the scope. The sponsor is requiring the project manager to provide a document in which the initial scope of the project is defined. Which of the following should the project manager do next to clarify the differences?

Options:

A.

Create a new project management plan.

B.

Collect all project meeting minutes.

C.

Perform project scope management.

D.

Review the project charter.

Buy Now
Questions 69

A project manager is leading the implementation of a new service for a well-known, global company for which brand image is most important. The project will rely on contracted services. As part of the request for proposal process, the project team has identified a short list of vendors to submit proposals. Which of the following items should the project team consider as a primary factor to remove a vendor from consideration?

Options:

A.

The vendor ' s proposed schedule does not align with the desired schedule.

B.

The vendor is new and not well established in the market.

C.

The vendor has been linked to ESG concerns within the past month

D.

The vendor ' s quote was the highest of all the proposals.

Buy Now
Questions 70

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

Options:

A.

ROI.

B.

SOW.

C.

RFI.

D.

RPR

Buy Now
Questions 71

During a phase review, two stakeholders discuss the approval of a deliverable. The project manager convinces the stakeholders to agree on a common solution. Which of the following best describes what the project manager did to gain approval from both stakeholders?

Options:

A.

Force

B.

Smooth

C.

Compromise

D.

Avoid

Buy Now
Questions 72

Functional managers are reluctant to provide a project manager with resources for a project because they think the project should include a certain scope. The project manager reviews the project documentation and confirms the items the functional managers wanted to include were out of scope. Which of the following would be the best course of action for the project manager to take?

Options:

A.

Satisfy the functional managers by agreeing with their point of view in order to get the necessary resources.

B.

Advise the functional managers to submit a change request, record the issue in the issue log. and escalate the issue to the project sponsor

C.

Schedule a team meeting to discuss creative ways to incorporate the scope without having to formally submit a scope change request.

D.

Inform the functional managers that the project will produce only what has been approved and project modifications cannot be made at this point.

Buy Now
Questions 73

A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?

Options:

A.

Validate the scope.

B.

Create the work breakdown structure.

C.

Define the scope.

D.

Collect the requirements.

Buy Now
Questions 74

A software development team implemented an approved change but does not obtain the expected results. The team notifies the change control board (CCB) about the failed change. Which of the following control processes is being followed?

Options:

A.

Scope creep

B.

Recovery plan

C.

Incident report

D.

Risk response

Buy Now
Questions 75

An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?

Options:

A.

Development

B.

Production

C.

Testing

D.

QA

Buy Now
Questions 76

Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?

Options:

A.

Daily stand-up

B.

Project momentum

C.

Performance feedback

D.

Meeting minutes

Buy Now
Questions 77

A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

Options:

A.

Data management

B.

Issue management

C.

Work breakdown structure

D.

Document management

E.

Communication management

F.

Risk management

Buy Now
Questions 78

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

PK0-005 Question 78

Which of the following issues should be addressed FIRST?

Options:

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.

Buy Now
Questions 79

A principle states 80% of the issues are the result of 20% of the causes. Which of the following types of diagrams is based on this principle?

Options:

A.

Pareto

B.

Scatter

C.

Network

D.

Fishbone

Buy Now
Questions 80

Which of the following can help identify opportunities for future improvement following the successful closure of a project?

Options:

A.

Contract review

B.

Archived documents

C.

Postmortem

D.

Project rewards

Buy Now
Questions 81

During a PMO audit, an auditor notices a discrepancy between the existing financial report and the financial information provided by the project manager at the end of the project in the previous quarter. Which of the following activities would have most likely avoided this discrepancy?

Options:

A.

Validation of deliverables

B.

Closing contracts

C.

Project sign-off

D.

Removing access

Buy Now
Questions 82

A project team evaluates the potential risks to a project that uses legacy applications. Which of the following should be the main concern of the project team?

Options:

A.

Infrastructure end of life

B.

Company reorganization

C.

Digital transformation

D.

Major cybersecurity event

Buy Now
Questions 83

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

Options:

A.

Review the detailed plan.

B.

Develop a preliminary scope.

C.

Develop a transition plan.

D.

Develop a project management plan.

E.

Review the resource pool.

F.

Review the project objectives.

Buy Now
Questions 84

A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?

Options:

A.

Project transition

B.

Project management

C.

Project communications

D.

Project quality assurance

Buy Now
Questions 85

A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?

Options:

A.

Project network diagram

B.

Fishbone diagram

C.

Burndown chart

D.

Milestone chart

Buy Now
Questions 86

A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?

Options:

A.

Assign a scribe to take notes.

B.

Record the meeting and transcribe the notes later.

C.

Instruct each team member to take notes.

D.

Get a facilitator for the meetings.

Buy Now
Questions 87

A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:

PK0-005 Question 87

Based on the chart, which of the following is the current status of the project?

Options:

A.

Behind schedule and over budget

B.

Behind schedule and under budget

C.

Ahead of schedule and over budget

D.

Ahead of schedule and under budget

Buy Now
Questions 88

Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?

Options:

A.

Risk

B.

Change

C.

Defect

D.

Issue

Buy Now
Questions 89

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

Options:

A.

Issue log

B.

Defect log

C.

Change log

D.

Task board

Buy Now
Questions 90

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the

following has the project manager identified?

Options:

A.

Technological factors

B.

Poor sample data

C.

Language barriers

D.

Scope creep

Buy Now
Questions 91

The project manager must create a project charter. Which of the following should be included in the charter?

Options:

A.

Project schedule

B.

Resource allocation

C.

Risk plan

D.

Stakeholder identification

Buy Now
Questions 92

Which of the following is a reason to use a SOW on a project?

Options:

A.

To find out the contact information for the vendors

B.

To review the list of stakeholders

C.

To ensure the team stays within the scope of the contract

D.

To give explicit instruction on how to execute the work

Buy Now
Questions 93

Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?

Options:

A.

The scope of the project deliverable is clearly defined

B.

There is a non-disclosure agreement in place

C.

There are multiple requirements for the product

D.

The PM wants to simplify the logistics of the required product

Buy Now
Questions 94

In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?

Options:

A.

Assemble a new project with existing resources.

B.

Obtain the final report from release management.

C.

Notify the functional manager that resources are released.

D.

Allocate resources in a different project

Buy Now
Questions 95

A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?

Options:

A.

Data plan

B.

Contingency plan

C.

Rollback plan

D.

Recovery plan

Buy Now
Questions 96

A team found a deficiency in an application and is proposing improvements, but the sponsor requests a business case. Which of the following best describes the intended objective of the business case?

Options:

A.

To identify the potential risk and issues for the project

B.

To determine the timeline and budget of the project

C.

To define the specific tasks required to create the project

D.

To specify what problem is being solved by the project

Buy Now
Questions 97

A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?

Options:

A.

Forcing

B.

Avoiding

C.

Compromising

D.

Smoothing

Buy Now
Questions 98

Which of the following statements best represents a network issue?

Options:

A.

The development team on the fourth floor is unable to access servers and email services.

B.

Cell phones served by a specific telecom company are getting a " no service " message.

C.

A user cannot connect to Wi-Fi because of a wrong ID or password.

D.

A user is receiving an automatic reply message saying that an email address does not exist.

Buy Now
Questions 99

A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?

Options:

A.

Monte Carlo simulation

B.

Root cause analysis

C.

Quantitative risk analysis

D.

Risk response analysis

Buy Now
Questions 100

Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?

Options:

A.

Data security

B.

Operational security

C.

Physical security

D.

Digital security

Buy Now
Questions 101

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

Options:

A.

Schedule

B.

Status report

C.

Issue log

D.

Task board

Buy Now
Questions 102

Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?

Options:

A.

Variable costs

B.

Fixed costs

C.

Front-loaded

D.

Time and materials

Buy Now
Questions 103

A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?

Options:

A.

SOW

B.

RFI

C.

RFQ

D.

WBS

Buy Now
Questions 104

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

Options:

A.

Document the request in the change control log.

B.

Communicate the change deployment.

C.

Conduct an impact assessment.

D.

Implement the change.

Buy Now
Questions 105

As part of a global project, the project manager wants to ensure there is no disruption in the day-to-day performance among project team members around the world Which of the following should the project manager consider doing as part of the project planning?

Options:

A.

Monitoring the project team

B.

Creating a handoff process

C.

Colocating the project team

D.

Creating a separate statement of work

Buy Now
Questions 106

A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?

Options:

A.

Define the WBS.

B.

Develop a RAM.

C.

Manage the vendors.

D.

Assess the resource pool.

Buy Now
Questions 107

Stakeholders ask the PM to provide an updated budget. Which of the following is the most important reason to update a project ' s budget during the execution phase?

Options:

A.

Evaluate the project ' s communication plan.

B.

Track and manage the project’s financial condition.

C.

Report the project’s risks and issues.

D.

Distribute resources to the project.

Buy Now
Questions 108

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

Options:

A.

Procurement

B.

Communication

C.

Quality assurance

D.

Risk

Buy Now
Questions 109

The PM is concerned with multiple copies of the same file causing confusion. Which of the following would prevent this issue?

Options:

A.

Print media

B.

Knowledge base

C.

Ticketing system

D.

Collaboration tool

Buy Now
Questions 110

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

Options:

A.

Performing

B.

Adjourning

C.

Forming

D.

Norming

Buy Now
Questions 111

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

Options:

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

Buy Now
Questions 112

A project stakeholder has asked the project manager to provide the performance data of a project. Which of the following should the project manager send to the stakeholder?

Options:

A.

Issue log

B.

Dashboard

C.

WBS

D.

Milestone chart

Buy Now
Questions 113

While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?

Options:

A.

Instruct the team members to set their speakers to maximum volume and mute their microphones.

B.

Require everyone to turn on their cameras and use the same background filter.

C.

Encourage the use of the chat and use plain language when speaking.

D.

Allow one person to speak at a time after receiving acknowledgment from the facilitator.

Buy Now
Questions 114

During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

Options:

A.

Ishikawa diagram

B.

Scatter diagram

C.

Pareto chart

D.

Decision tree

Buy Now
Questions 115

Which of the following would help a project manager identify that project goals have been reached?

Options:

A.

Audit report

B.

Key performance indicators

C.

Backlog

D.

Lessons learned

Buy Now
Questions 116

A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do next?

Options:

A.

Buy a replacement for the faulty equipment.

B.

Get the maintenance team to resolve the issue.

C.

Escalate the issue to the project sponsor.

D.

Rate the severity of the impact the issue has on the project.

Buy Now
Questions 117

A company wants to move its data from on premises to off premises. Which of the following cloud models should be pursued?

Options:

A.

XaaS

B.

SaaS

C.

PaaS

D.

laaS

Buy Now
Questions 118

While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

Options:

A.

Escalate the finding to the change control board.

B.

Add a risk to the risk register for validation.

C.

Consult the RACI matrix to identify ownership of the risk.

D.

Have a meeting with the project sponsor and main stakeholders.

Buy Now
Questions 119

A sponsor is working on a document that states the objectives and success criteria of the project, as well as the person to be appointed as project manager Which of the following should the newly appointed project manager do next?

Options:

A.

Conduct a risk assessment.

B.

Create a project scope document

C.

Identify stakeholders

D.

Perform a lessons learned.

Buy Now
Questions 120

Which of the following would be best to utilize when managing communications for project teams across multiple time zones?

Options:

A.

Business collaboration tool

B.

Email

C.

Virtual meetings

D.

Enterprise CMS

Buy Now
Questions 121

Which of the following should be considered first when determining the privacy management for project data?

Options:

A.

Evaluating the current privacy protection program

B.

Understanding applicable privacy regulations

C.

Maintaining awareness of industry best practices

D.

Implementing security role-based controls

Buy Now
Questions 122

Which of the following activities are performed during the closing phase? (Select three).

Options:

A.

Requesting project charter sign-off

B.

Recognizing project team efforts and rewarding team members

C.

Working with the financial team to obtain return of investment

D.

Revoking resource credentials from the system

E.

Updating the risk register with new findings

F.

Informing the functional manager about the release of resources

G.

Monitoring project team performance

Buy Now
Questions 123

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

Options:

A.

Determine budget constraints.

B.

Validate the business case.

C.

Update the project charter.

D.

Create a project schedule

Buy Now
Questions 124

The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project’s level of compliance with the budget. Which of the following best describes what the project manager should do to assist the client?

Options:

A.

Grant the client access to the project repository.

B.

Create a chat to communicate in real time.

C.

Schedule a weekly status meeting.

D.

Send a weekly status report by email.

Buy Now
Questions 125

A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?

Options:

A.

Each feature will have a different owner.

B.

The majority of the team can only meet on a weekly basis.

C.

The stakeholders have provided a specific deadline to meet.

D.

Each feature has a specific budget allocation.

Buy Now
Questions 126

Which of the following is a typical characteristic of Scrum?

Options:

A.

Large teams

B.

Low-risk scope

C.

Self-organized team

D.

Well-defined scope

Buy Now
Questions 127

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?

Options:

A.

RFI

B.

RFP

C.

RFQ

D.

RFB

Buy Now
Questions 128

A project team member recalls a specific chat with another member that contained key information related to a previous project, which no one else on the project team is aware of. Which of the following best describes what was needed to address this concern?

Options:

A.

Integrity

B.

Security

C.

Archival

D.

Lessons learned

Buy Now
Questions 129

Which of the following is a quality assurance tool?

Options:

A.

Defining project goals

B.

Identifying the root cause analysis

C.

Assessing employee efficiency

D.

Assessing skill gaps

Buy Now
Questions 130

A project team wants to compare two potential vendors ' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?

Options:

A.

Scatter diagram

B.

Decision tree

C.

Pareto chart

D.

Histogram

Buy Now
Questions 131

Which of the following aspects are true of agile as compared to waterfall? (Select two).

Options:

A.

Agile works through larger integrated teams.

B.

Agile promotes project manager ownership over deliverables.

C.

Agile reinforces the importance of comprehensive documentation.

D.

Agile has more customer involvement throughout development.

E.

Agile is more flexible to allow for changes in scope.

F.

Agile is comprised of well-defined phases.

Buy Now
Questions 132

A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?

Options:

A.

To move the system to a production environment

B.

To obtain project sign-off

C.

To formalize the end of the contract

D.

To release resources

Buy Now
Questions 133

Which of the following is the best alternative to allow multiple users to edit a project plan in real time?

Options:

A.

Send the file through email as an attachment

B.

Share access to the file on a wiki knowledge base.

C.

Access the file through an online application.

D.

Schedule an in-person meeting to review the plan

Buy Now
Questions 134

Which of the following should a project manager consult when deciding how to send updates regarding deliverables?

Options:

A.

Dashboard

B.

Status report

C.

Meeting minutes

D.

Communication plan

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2026)
Last Update: May 17, 2026
Questions: 447

PDF + Testing Engine

$64.99  $185.69

Testing Engine

$49.99  $142.83
buy now PK0-005 testing engine

PDF (Q&A)

$54.99  $157.11
buy now PK0-005 pdf