Summer Certification Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Free Practice Questions for the CompTIA Project+ PK0-005 Exam (2026 Updated)

At Marks4sure, we are dedicated to providing IT professionals with the most accurate and reliable preparation materials for the CompTIA PK0-005 exam. To support your certification journey, we have made a selection of our premium 2026 Project+ practice questions and answers available completely free. You can take this practice test as many times as you need. Every question includes a detailed, expertly verified explanation to ensure you fully grasp the core security concepts before test day.

Questions 4

Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

Options:

A.

Memorandum of understanding

B.

Request for information

C.

Statement of work

D.

Non-disclosure agreement

Buy Now
Questions 5

A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?

Options:

A.

Update the WBS.

B.

Escalate to the CCB.

C.

Accept the change.

D.

Implement the change.

Buy Now
Questions 6

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

Options:

A.

Kanban board

B.

Pareto chart

C.

Ishikawa diagram

D.

Decision tree

Buy Now
Questions 7

A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?

Options:

A.

Validation check

B.

Downtime window schedule

C.

Customer notifications

D.

Risk analysis

Buy Now
Questions 8

A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?

Options:

A.

Bringing attention to the project sponsor

B.

Sharing lessons learned

C.

Collecting feedback

D.

Celebrating the team ' s hard work

Buy Now
Questions 9

Which of the following is the best alternative to allow multiple users to edit a project plan in real time?

Options:

A.

Send the file through email as an attachment

B.

Share access to the file on a wiki knowledge base.

C.

Access the file through an online application.

D.

Schedule an in-person meeting to review the plan

Buy Now
Questions 10

After a weekly status meeting, a project manager needs to prepare and distribute a document with a summary of all the topics discussed, agreements, and next steps. Which of the following documents should the project manager prepare?

Options:

A.

Minutes

B.

Project presentation

C.

Memorandum

D.

Issue log

Buy Now
Questions 11

A project manager is concerned about the performance of a developer who is struggling with the new coding language. Which of the following actions should the project manager take?

Options:

A.

Send a request to the project sponsor to add an additional developer.

B.

Provide the developer with only non-critical tasks.

C.

Assign the developer training to improve the developer ' s skills.

D.

Remove the developer from the project team.

Buy Now
Questions 12

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

Options:

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

Buy Now
Questions 13

After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?

Options:

A.

Withdraw the offer to the candidate and raise this as a risk.

B.

Ignore a potential lawsuit since this is a critical project.

C.

Use a third-party company for the contract to legally avoid responsibility.

D.

Have a meeting with the project sponsor to discuss the situation.

Buy Now
Questions 14

Which of the following concepts represents multiple resources interfaced to run reports?

Options:

A.

Code repository

B.

Data warehouse

C.

Storage server

D.

File-sharing system

Buy Now
Questions 15

A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?

Options:

A.

Flat

B.

Projectized

C.

Weak matrix

D.

Functional

Buy Now
Questions 16

For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

Options:

A.

Resource plan

B.

Organizational chart

C.

Project charter

D.

RACI chart

Buy Now
Questions 17

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

Options:

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Buy Now
Questions 18

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

Options:

A.

Escalate the change to the CCB.

B.

Review the requested change.

C.

Document the change recommendations.

D.

Validate the implementation of the requested change.

Buy Now
Questions 19

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the

following has the project manager identified?

Options:

A.

Technological factors

B.

Poor sample data

C.

Language barriers

D.

Scope creep

Buy Now
Questions 20

During the planning phase, a project manager is mapping out the full scope, calculating task durations, and identifying dependencies. Which of the following is the best tool for the project manager to use?

Options:

A.

Gantt chart

B.

Milestone chart

C.

Velocity chart

D.

PERT chart

Buy Now
Questions 21

A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following best describes this technique?

Options:

A.

Demonstration

B.

Workshop

C.

Brainstorming

D.

Focus group

Buy Now
Questions 22

Which of the following is the main reason for documenting artifacts?

Options:

A.

To provide a record of the project ' s progress and achievements for future reference

B.

To show stakeholders that the project is on track and progressing as planned

C.

To help team members be aware of roles and responsibilities

D.

To ensure that the project team understands the importance of the project to the organization

Buy Now
Questions 23

PK0-005 Question 23

Which of the following best describes the results?

Options:

A.

No correlation exists between the extra hours worked and the number of defects in the code.

B.

A positive correlation exists between the extra hours worked and the number of defects in the code.

C.

A non-linear correlation exists between the extra hours worked and the number of defects in the code.

D.

A negative correlation exists between the extra hours worked and the number of defects in the code.

Buy Now
Questions 24

Which of the following best describes the reason a chat messaging service would be used as the primary form of communication for a project team?

Options:

A.

The team is working in different rooms within the same building.

B.

The team is working remotely two days per week.

C.

The team has members distributed around the world in different time zones.

D.

The team is based in the same office but has a large number of members.

Buy Now
Questions 25

A project manager and team are currently in the planning phase of a project. Which of the following should the team do during this phase?

Options:

A.

Identify and assess stakeholders.

B.

Hold daily status meetings.

C.

Remove access and plan the project sign-off.

D.

Review assumptions and constraints for input to the risk register.

Buy Now
Questions 26

Which of the following pieces of data are examples of Pll?

Options:

A.

Medical record and test result values

B.

IP address and email address

C.

Name and year of birth

D.

X-ray and blood type

Buy Now
Questions 27

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

Options:

A.

Trigger the contingency plan and communicate with the stakeholders.

B.

Work with the functional managers to create a work-around.

C.

Submit a change request to the change control board.

D.

Transfer the risk by hiring a new vendor who was successful on a previous project.

E.

Set up an escalation meeting with the sponsor.

Buy Now
Questions 28

Which of the following can help identify opportunities for future improvement following the successful closure of a project?

Options:

A.

Contract review

B.

Archived documents

C.

Postmortem

D.

Project rewards

Buy Now
Questions 29

A project manager is receiving reports of the actual project expenditures and, based on this information, is making adjustments to the budget. In which of the following phases does this occur?

Options:

A.

Planning

B.

Closure

C.

Initiation

D.

Execution

Buy Now
Questions 30

A company is adapting its strategy almost every quarter, and the product might be different at the end of the project. Which of the following is the best methodology for the project manager to use?

Options:

A.

Scrum

B.

Extreme programming

C.

Waterfall

D.

Kanban

Buy Now
Questions 31

During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.

INSTRUCTIONS

Review the email with the latest updates sent by the project sponsor and respond in

the following order:

1. Select the best tool for tracking the server migration progress.

2. Select the new critical path.

3. Select the correct number of engineers required for the server migration phase.

If at any time you would like to bring back the initial state of the simulation, please click

the Reset All button.

Select the Appropriate Tool:

PK0-005 Question 31

PK0-005 Question 31

Select the new critical path.

Option A

Option B

Option C

PK0-005 Question 31

Options:

Buy Now
Questions 32

A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to

identify the level of engagement among project team members. Which of the following would be the best tool for the project manager to use?

Options:

A.

Meeting chat

B.

Email

C.

Real-time survey

D.

Whiteboard

Buy Now
Questions 33

A software development team implemented an approved change but does not obtain the expected results. The team notifies the change control board (CCB) about the failed change. Which of the following control processes is being followed?

Options:

A.

Scope creep

B.

Recovery plan

C.

Incident report

D.

Risk response

Buy Now
Questions 34

A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?

Options:

A.

Escalate the communication issues.

B.

Implement a communication platform.

C.

Review the communication plan.

D.

Talk with the head of the PMO.

Buy Now
Questions 35

A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?

Options:

A.

Forcing

B.

Avoiding

C.

Compromising

D.

Smoothing

Buy Now
Questions 36

The sales department accidentally has access to all project files, including employee personal information. Which of the following security concepts is this violating?

Options:

A.

Need-to-know

B.

Intellectual property

C.

Multifactor authentication

D.

Facility access

Buy Now
Questions 37

A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?

Options:

A.

Mitigate

B.

Transfer

C.

Accept

D.

Share

Buy Now
Questions 38

A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

Options:

A.

Identify project risks and plans to address them.

B.

Identify business needs and product descriptions.

C.

Create a work breakdown structure for the project.

D.

Create a work schedule for the project team to follow.

Buy Now
Questions 39

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

Options:

A.

Critical paths

B.

Resources

C.

Milestones

D.

Work breakdown structures

Buy Now
Questions 40

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?

Options:

A.

RFI

B.

RFP

C.

RFQ

D.

RFB

Buy Now
Questions 41

A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?

Options:

A.

Start-to-finish

B.

Finish-to-finish

C.

Finish-to-start

D.

Start-to-start

Buy Now
Questions 42

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).

Options:

A.

Risk report

B.

Defect log

C.

Issue log

D.

Backlog

E.

Change log

F.

Progress report

Buy Now
Questions 43

Which of the following is an activity related to operational security?

Options:

A.

Processing background screening

B.

Setting up a firewall

C.

Establishing a zone of trust

D.

Implementing multifactor authentication

Buy Now
Questions 44

A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?

Options:

A.

Secure folder

B.

Real-time, multiauthoring editing software

C.

Digital whiteboard

D.

Wiki knowledge base

Buy Now
Questions 45

During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?

Options:

A.

Statement of work

B.

Business case

C.

Requirements document

D.

Work breakdown structure

Buy Now
Questions 46

An external developer working on a project at an hourly rate provides an invoice at the end of a month for 80 hours spent on a project. The project manager realizes that there were no tasks assigned to this developer last month. Which of the following actions should the project manager take first?

Options:

A.

Consult other developers.

B.

Escalate the issue to the project steering committee.

C.

Request the developer provide justification.

D.

Decline the invoice.

Buy Now
Questions 47

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

Options:

A.

Make an impact assessment.

B.

Prepare a new purchase order.

C.

Select a new vendor.

D.

Create a risk register.

Buy Now
Questions 48

A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?

Options:

A.

Cultural differences

B.

Technological factors

C.

Time zones

D.

Language barriers

Buy Now
Questions 49

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

Options:

A.

Update the work breakdown structure.

B.

Review the backlog.

C.

Seek baseline approval.

D.

Establish the resource pool.

Buy Now
Questions 50

Which of the following can be used to determine whether a sample product is within an acceptable range?

Options:

A.

Scatter diagram

B.

Velocity chart

C.

Control chart

D.

Fishbone diagram

Buy Now
Questions 51

Which of the following would be considered operational security?

Options:

A.

Mobile device compliance

B.

Background screening

C.

Multifactor authentication

D.

Facility access

Buy Now
Questions 52

After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?

Options:

A.

Smoke test

B.

Stress test

C.

Penetration test

D.

Regression test

Buy Now
Questions 53

A web designer is currently verifying that the website data is compliant. Which of the following data types will be protected after confirming that the controls are in place?

Options:

A.

Credit cards

B.

Mission statements

C.

Site certificates

D.

Trademarks

Buy Now
Questions 54

Which of the following is an intended outcome of a stand-up meeting?

Options:

A.

To identify team members for next tasks

B.

To identify future tasks

C.

To identify stakeholders for next tasks

D.

To identify blocking tasks

Buy Now
Questions 55

Which of the following is a reason to use a SOW on a project?

Options:

A.

To find out the contact information for the vendors

B.

To review the list of stakeholders

C.

To ensure the team stays within the scope of the contract

D.

To give explicit instruction on how to execute the work

Buy Now
Questions 56

During a functional validation exercise, two end users request changes to the product that cannot be implemented without altering the already constrained project budget. The project manager convinces the end users to simplify the change request so it can be accomplished. Which of the following conflict resolution techniques did the project manager use?

Options:

A.

Collaborating

B.

Smoothing

C.

Avoiding

D.

Compromising

Buy Now
Questions 57

A project manager working in a strong matrix organization was selected to manage a new project with trending technologies. During the kickoff meeting, one of the stakeholders mentions that the company has never worked with such technologies. Which of the following should the project manager do next?

Options:

A.

Train the project team members and develop a detailed scope statement.

B.

Assign project resources and procure additional team members.

C.

Perform a preliminary procurement needs assessment and determine budget considerations.

D.

Define units of work and develop a project schedule.

Buy Now
Questions 58

Which of the following provides a layered approach to logging in to systems that contain an organization ' s most valuable intellectual property?

Options:

A.

Remote access

B.

Password protection

C.

Multifactor authentication

D.

Virtual private network

Buy Now
Questions 59

As part of a global project, the project manager wants to ensure there is no disruption in the day-to-day performance among project team members around the world Which of the following should the project manager consider doing as part of the project planning?

Options:

A.

Monitoring the project team

B.

Creating a handoff process

C.

Colocating the project team

D.

Creating a separate statement of work

Buy Now
Questions 60

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

Options:

A.

Work with the project scheduler to update the project timeline.

B.

Communicate to the stakeholders about the updated timeline.

C.

Ask the development team to fast-track upcoming activities.

D.

Add two resources so the critical activities will finish on time.

Buy Now
Questions 61

Project team members enter their time sheets into a system that also displays incurred project cost. Which of the following systems can perform this task?

Options:

A.

EDRMS

B.

CRM

C.

CMS

D.

ERP

Buy Now
Questions 62

Which of the following software programs would be BEST to use lo store information related to business transactions?

Options:

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Buy Now
Questions 63

A project sponsor requires a system that is capable of providing integrated management of all the business ' s core functions. Which of the following systems is the project sponsor describing?

Options:

A.

CMS

B.

CRM

C.

EDRMS

D.

ERP

Buy Now
Questions 64

During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following:

PK0-005 Question 64

Which of the following was the initial cause of the issue?

Options:

A.

Inadequate memory

B.

Incorrect configuration

C.

Lack of infrastructure

D.

Inadequate instructions

Buy Now
Questions 65

An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens ' complaints. Which of the following solutions would be BEST?

Options:

A.

Enterprise resource planning and end user applications

B.

Electronic document and record management systems

C.

Customer relationship management and databases

D.

Content management and financial systems

Buy Now
Questions 66

A company plans to install new servers. The project manager receives a notification that the manufacturer may be in financial trouble, so the servers will be sourced from another vendor. Which of the following risk management strategies should the project manager use?

Options:

A.

Share

B.

Exploit

C.

Mitigate

D.

Avoid

Buy Now
Questions 67

A stakeholder called a project manager on the telephone to ask for a status report. Which of the following describe this type of communication? (Select two).

Options:

A.

Formal

B.

Internal

C.

Informal

D.

Verbal

E.

Indirect

F.

External

Buy Now
Questions 68

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

Options:

A.

Issue log

B.

Defect log

C.

Change log

D.

Task board

Buy Now
Questions 69

During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

Options:

A.

PERT chart

B.

Milestone chart

C.

Gantt chart

D.

Budget burndown chart

Buy Now
Questions 70

A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following describes the grouping of the smaller components?

Options:

A.

An issue

B.

A goal

C.

A backlog item

D.

An epic

Buy Now
Questions 71

Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?

Options:

A.

Smoke testing

B.

Regression testing

C.

Unit testing

D.

User acceptance testing

Buy Now
Questions 72

Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?

Options:

A.

Social engineering

B.

Phishing

C.

Spoofing

D.

Hacking

Buy Now
Questions 73

A project was selected for an audit years after the project closed. Which of the following is most likely to be needed for the audit?

Options:

A.

Signed contracts

B.

Archived documentation

C.

Project closeout report

D.

Lessons learned

Buy Now
Questions 74

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

Options:

A.

Document the request in the change control log.

B.

Communicate the change deployment.

C.

Conduct an impact assessment.

D.

Implement the change.

Buy Now
Questions 75

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

Options:

A.

Project change management plan

B.

Project management plan

C.

Project transition plan

D.

Project communication plan

Buy Now
Questions 76

During project initiation, a project manager is drafting a document that includes an outline of the high-level goals, objectives, milestones, and requirements. This document will be modified and finalized as more information becomes available. Which of the following best meets the requirements?

Options:

A.

Preliminary scope statement

B.

Procurement needs assessment

C.

Project success criteria

D.

Work breakdown structure

Buy Now
Questions 77

Which of the following best describes the reason a waterfall approach would be used for a project?

Options:

A.

The executive team still has no clear requirements for the product.

B.

The executive team is looking to review the product only once after the product is finalized.

C.

The executive team is expecting constant delivery of components.

D.

The executive team wants to reduce the budget for development.

Buy Now
Questions 78

An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?

Options:

A.

The ticket system provided access by default without any approval.

B.

The project manager did not perform proper project planning.

C.

The system is lacking proper access controls.

D.

Sensitive data was incorrectly classified during the audit process.

Buy Now
Questions 79

A project manager and team are reviewing a task that is supposed to take 9 days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional 5 days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

Options:

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

13 days and $3,600

Buy Now
Questions 80

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

Options:

A.

Evaluating the project

B.

Releasing the resources

C.

Closing the contracts

D.

Reconciling the budget

Buy Now
Questions 81

Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project ' s timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?

Options:

A.

Smoothing

B.

Confronting

C.

Forcing

D.

Compromising

Buy Now
Questions 82

A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?

Options:

A.

Planning

B.

Initiating

C.

Controlling

D.

Executing

Buy Now
Questions 83

A project team is reviewing the project plan and related documents and identifies tasks that could be spread into smaller deliverables. Which of the following documents should the team edit first?

Options:

A.

Risk assessment

B.

Preliminary scope statement

C.

Work breakdown structure

D.

Milestone chart

Buy Now
Questions 84

A company purchases new software. The project manager needs to present the new software’s features to the stakeholders. Which of the following meeting types should the project manager and stakeholders have?

Options:

A.

Status

B.

Focus

C.

Brainstorming

D.

Informative

Buy Now
Questions 85

A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

Options:

A.

Issue log

B.

Gantt chart

C.

Milestone chart

D.

Change control log

Buy Now
Questions 86

A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?

Options:

A.

Validate the scope.

B.

Create the work breakdown structure.

C.

Define the scope.

D.

Collect the requirements.

Buy Now
Questions 87

Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

Options:

A.

Approving the change request

B.

Developing a rollback plan

C.

Gathering necessary resources

D.

Defining requirements

Buy Now
Questions 88

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

Options:

A.

ESG

B.

PHI

C.

Pll

D.

ROI

Buy Now
Questions 89

Which of the following best describes the role of a PM for a CRM system?

Options:

A.

To track sales

B.

To store customer information

C.

To implement new features

D.

To pay vendors

Buy Now
Questions 90

Given the following information:

Which of the following represents the critical path of the project?

Options:

A.

A-C-F-I-J

B.

A-C-F-H-J

C.

A-B-D-G-J

D.

A-B-E-G-J

Buy Now
Questions 91

Which of the following is a characteristic that defines a project?

Options:

A.

Will produce a profit

B.

Uses outside resources

C.

Requires a well-defined scope

D.

Has a defined start and finish

Buy Now
Questions 92

A project manager is responsible for implementing a large, centralized repository that stores raw information from various sources in a structured and organized way. Which of the following should the project manager implement?

Options:

A.

Shared folder

B.

Infrastructure

C.

Multitiered architecture

D.

Data warehouse

Buy Now
Questions 93

A team found a deficiency in an application and is proposing improvements, but the sponsor requests a business case. Which of the following best describes the intended objective of the business case?

Options:

A.

To identify the potential risk and issues for the project

B.

To determine the timeline and budget of the project

C.

To define the specific tasks required to create the project

D.

To specify what problem is being solved by the project

Buy Now
Questions 94

Which of the following is a typical characteristic of Scrum?

Options:

A.

Large teams

B.

Low-risk scope

C.

Self-organized team

D.

Well-defined scope

Buy Now
Questions 95

Which of the following statements best describes Kanban?

Options:

A.

A workflow management method to maximize efficiency and enable continuous improvement.

B.

A board representing the different stages of a software solution.

C.

A dashboard used to facilitate scope alignment with the project team.

D.

A spreadsheet representing development tasks and how they relate to the business process being improved.

Buy Now
Questions 96

A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?

Options:

A.

Discovery

B.

Execution

C.

Initiating

D.

Planning

Buy Now
Questions 97

A team member is not completing deliverables on time or responding to emails while the project manager is on vacation. Which of the following actions should the technical lead take?

Options:

A.

Inform all stakeholders.

B.

Update the issue register.

C.

Follow the escalation path.

D.

Initiate a change request.

Buy Now
Questions 98

Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?

Options:

A.

Daily stand-up

B.

Project momentum

C.

Performance feedback

D.

Meeting minutes

Buy Now
Questions 99

The project manager sends individual messages to team members about what must be accomplished. However, the team communicates confusion about the tasks assigned. Which of the following communication methods would be best to use?

Options:

A.

Informal internal

B.

Asynchronous verbal

C.

Synchronous external

D.

Formal written

Buy Now
Questions 100

Which of the following statements best represents a network issue?

Options:

A.

The development team on the fourth floor is unable to access servers and email services.

B.

Cell phones served by a specific telecom company are getting a " no service " message.

C.

A user cannot connect to Wi-Fi because of a wrong ID or password.

D.

A user is receiving an automatic reply message saying that an email address does not exist.

Buy Now
Questions 101

A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

Options:

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

14 days and $4,000

Buy Now
Questions 102

During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?

Options:

A.

Waterfall

B.

SDLC

C.

XP

D.

Scrum

Buy Now
Questions 103

Which of the to and allowing interactive feedback from a project team?

Options:

A.

Text message

B.

Chat

C.

Email

D.

Videoconference

Buy Now
Questions 104

Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?

Options:

A.

Start-to-start

B.

Start-to-finish

C.

Finish-to-finish

D.

Finish-to-start

Buy Now
Questions 105

Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?

Options:

A.

The scope of the project deliverable is clearly defined

B.

There is a non-disclosure agreement in place

C.

There are multiple requirements for the product

D.

The PM wants to simplify the logistics of the required product

Buy Now
Questions 106

During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?

Options:

A.

Baseline

B.

RBS

C.

WBS

D.

Milestones

Buy Now
Questions 107

A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?

Options:

A.

Use a software tool during the meeting that can create a transcript of what is discussed.

B.

Have a standing agenda that is vague enough so that it can be used again.

C.

Delegate the roles and responsibilities to improve meeting management.

D.

Reprimand project team members for not completing assigned action items.

Buy Now
Questions 108

A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?

Options:

A.

RFP

B.

RFQ

C.

RFB

D.

RFI

Buy Now
Questions 109

Which of the following project types is best managed as a waterfall project?

Options:

A.

Data analytics

B.

Research

C.

Software development

D.

Real property

Buy Now
Questions 110

Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users ' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?

Options:

A.

Send out a survey to the potential end users to gather information about the best functional setup for work productivity.

B.

Provide clear instructions based on personal preference and aesthetics for setup of the work areas.

C.

Explain to team members that the placement of the items is not too important, as long as everything is connected and working.

D.

Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.

Buy Now
Questions 111

A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?

Options:

A.

Project network diagram

B.

Gantt chart

C.

Issue log

D.

Risk report

Buy Now
Questions 112

During project initiation, a project manager needs to establish the communication channel that will be used to deliver weekly presentations to stakeholders who are across the country. Which of the following would be the best communication channel to use?

Options:

A.

In-person meetings

B.

Email

C.

Telephone

D.

Videoconference

Buy Now
Questions 113

A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

Options:

A.

Status report

B.

Project plan

C.

Change log

D.

Meeting minutes

Buy Now
Questions 114

The PM is concerned with multiple copies of the same file causing confusion. Which of the following would prevent this issue?

Options:

A.

Print media

B.

Knowledge base

C.

Ticketing system

D.

Collaboration tool

Buy Now
Questions 115

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

Options:

A.

Remove the team member ' s access.

B.

Release the project resources.

C.

Collect the stakeholders’ feedback.

D.

Have the closeout report approved.

Buy Now
Questions 116

As a result of an unpredicted risk, a project manager is documenting a request in the change control log. Which of the following change control processes should the project manager do last?

Options:

A.

Escalate to the change control board.

B.

Update the project plan.

C.

Test the implemented change request.

D.

Communicate the change deployment.

Buy Now
Questions 117

Which of the following are primary features provided by a standard laaS solution? (Select two).

Options:

A.

Encryption

B.

Storage

C.

Networking

D.

User interface

E.

Access

F.

Database

Buy Now
Questions 118

A principle states 80% of the issues are the result of 20% of the causes. Which of the following types of diagrams is based on this principle?

Options:

A.

Pareto

B.

Scatter

C.

Network

D.

Fishbone

Buy Now
Questions 119

A project team is developing an application that will allocate a building ' s parking spaces. The building owner does not agree with using corporate colors in the application and has blocked

the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

Options:

A.

Review of existing artifacts

B.

Development of an issue log

C.

Identification and assessment of stakeholders

D.

Establishment of accepted communication channels

Buy Now
Questions 120

Participant attendance has been poor at the last few weekly meetings. The project manager wants to validate who the participants should be, how often the meetings should occur, and on which day and at what time the meeting should be held. Which of the following is the best place to validate this information?

Options:

A.

Project communication plan

B.

Project management plan

C.

Project business case

D.

Project schedule

Buy Now
Questions 121

Which of the following situations would require a project manager to revise the communication plan during a project ' s execution?

Options:

A.

A change is approved that impacts the project schedule and budget

B.

The test results are not as expected

C.

The team is unclear which meetings they should attend

D.

A stakeholder requests some changes to the scope

Buy Now
Questions 122

A project manager is meeting with stakeholders to identify objectives and success criteria. Which of the following artifacts is the project manager working on?

Options:

A.

Project charter

B.

Requirements traceability matrix

C.

Project communications plan

D.

Project risk register

Buy Now
Questions 123

Given the information in the chart,

PK0-005 Question 123

which of the following techniques should the project manager use to improve the project schedule in Sprint 1?

Options:

A.

Validating

B.

Crashing

C.

Training

D.

Avoiding

Buy Now
Questions 124

Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

Options:

A.

Maintenance window

B.

Risk assessment

C.

Operational security

D.

Validation check

Buy Now
Questions 125

Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).

Options:

A.

Creating a backlog

B.

Managing the quality of deliverables

C.

Updating the issue log

D.

Performing a risk assessment

E.

Validating the deliverables

F.

Reconciling the project budget

Buy Now
Questions 126

Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?

Options:

A.

Software as a service

B.

Infrastructure as a service

C.

Data as a service

D.

Platform as a service

Buy Now
Questions 127

A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?

Options:

A.

SOW

B.

RFI

C.

RFQ

D.

WBS

Buy Now
Questions 128

A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?

Options:

A.

To move the system to a production environment

B.

To obtain project sign-off

C.

To formalize the end of the contract

D.

To release resources

Buy Now
Questions 129

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

Options:

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Buy Now
Questions 130

A project manager is managing a virtual team across the country. As reported in the retrospective, the team morale has decreased due to additional production issues. Which of the following meeting tools is the best option to record results in the retrospective?

Options:

A.

Presentation

B.

Wiki

C.

Chat

D.

Polling

Buy Now
Questions 131

A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?

Options:

A.

Multiauthoring software

B.

Word processor

C.

Real-time polling

D.

Conferencing platforms

Buy Now
Questions 132

Which of the following should be the PRIMARY basis for establishing metrics that measure the effectiveness of an information security program?

Options:

A.

Residual risk

B.

Regulatory requirements

C.

Risk tolerance

D.

Control objectives

Buy Now
Questions 133

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

Options:

A.

Avoiding

B.

Smoothing

C.

Forcing

D.

Compromising

Buy Now
Questions 134

A project manager is comparing the documentation attached to invoices from main vendors with the requirements described in the SOW in order to decide if all are correct. Which of the following best describes what is being performed?

Options:

A.

Approving deliverables

B.

Enforcing vendor rules of engagement

C.

Reporting overall process

D.

Scheduling team touch points

Buy Now
Questions 135

Which of the following provides the best justification for undertaking a project?

Options:

A.

Scope statement

B.

Business case

C.

Sponsor request

D.

Project charter

Buy Now
Questions 136

A project manager makes a list of the smallest activity components in the project. Which of the following is the project manager building?

Options:

A.

Milestone chart

B.

Task board

C.

Work breakdown structure

D.

Detailed project plan

Buy Now
Questions 137

The executive leadership of an agile company has launched a new strategy. This new strategy impacts new features that are in development with the project team. Which of the following describes what the team should do next?

Options:

A.

Resource loading

B.

Analyzing the critical path

C.

Prioritizing backlog

D.

Determining contingency reserves

Buy Now
Questions 138

A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?

Options:

A.

Rational Unified Process

B.

Waterfall

C.

Agile

D.

DevOps

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2026)
Last Update: Jun 29, 2026
Questions: 460

PDF + Testing Engine

$64.99   $185.69

Testing Engine

$49.99   $142.83

PDF (Q&A)

$54.99   $157.11