Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PK0-005 CompTIA Project+ Certification (2026) Questions and Answers

Questions 4

During the project execution, the sponsor would like to have a visual representation indicating the progress of the project The project is being managed using agile methodologies Which of the following tools would best help the sponsor with the request?

Options:

A.

Milestone chart

B.

Velocity chart

C.

Task board

D.

Burndown chart

Buy Now
Questions 5

A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

Options:

A.

Ticketing system

B.

Videoconference

C.

Simple messaging system

D.

Corporate social media

Buy Now
Questions 6

When assigning access, classifying information based on sensitivity is referred to as:

Options:

A.

Digital security

B.

Physical security

C.

Data security

D.

Operational security

Buy Now
Questions 7

A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

Options:

A.

Meeting cadence

B.

Gap analysis

C.

Dashboard

D.

Adoption training

Buy Now
Questions 8

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

Options:

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

Buy Now
Questions 9

A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication. The project manager should update the stakeholder register with:

Options:

A.

the preferred sponsor's communication channel.

B.

the preferred project manager's communication channel.

C.

the preferred reported communication channel.

D.

email communication as the preferred communication channel.

Buy Now
Questions 10

A project was selected for an audit years after the project closed. Which of the following is most likely to be needed for the audit?

Options:

A.

Signed contracts

B.

Archived documentation

C.

Project closeout report

D.

Lessons learned

Buy Now
Questions 11

Which of the following best describes why a project manager would decide to sign a fixed-price contract with a vendor?

Options:

A.

The scope of the project deliverable is clearly defined.

B.

There is a non-disclosure agreement in place.

C.

There are multiple requirements for the product.

D.

The PM wants to simplify the logistics of the required product.

Buy Now
Questions 12

Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?

Options:

A.

Software as a service

B.

Infrastructure as a service

C.

Data as a service

D.

Platform as a service

Buy Now
Questions 13

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

Options:

A.

Validate against the scope statement and ask for sign-off.

B.

Run a control chart to ensure the quality of the deliverables.

C.

Review the risk register and close up residual risks.

D.

Start the training and handoff for the operations team.

Buy Now
Questions 14

A new project manager takes over a project midway through the schedule. Which of the following should the project manager do first before continuing the project?

Options:

A.

Access project artifacts.

B.

Arrange a brainstorming session.

C.

Conduct a kickoff meeting.

D.

Establish communication channels.

Buy Now
Questions 15

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

Options:

A.

Critical paths

B.

Resources

C.

Milestones

D.

Work breakdown structures

Buy Now
Questions 16

Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?

Options:

A.

Social engineering

B.

Phishing

C.

Spoofing

D.

Hacking

Buy Now
Questions 17

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

Options:

A.

Trigger the contingency plan and communicate with the stakeholders.

B.

Work with the functional managers to create a work-around.

C.

Submit a change request to the change control board.

D.

Transfer the risk by hiring a new vendor who was successful on a previous project.

E.

Set up an escalation meeting with the sponsor.

Buy Now
Questions 18

Which of the following concepts represents multiple resources interfaced to run reports?

Options:

A.

Code repository

B.

Data warehouse

C.

Storage server

D.

File-sharing system

Buy Now
Questions 19

Which of the following best describes a benefit of the CI/CD process?

Options:

A.

Software delivery is sped up without compromising quality.

B.

Incremental changes are done at the end of the project.

C.

The software is integrated with other projects easily.

D.

Updates are released every sprint.

Buy Now
Questions 20

A project is not progressing as planned following the departure of the project manager. Which of the following would be the best tool to use to document this information?

Options:

A.

Issue log

B.

Risk register

C.

Change log

D.

Defect log

Buy Now
Questions 21

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

Options:

A.

Escalate to vendor management.

B.

Consult the request for proposal.

C.

Review the meeting cadence.

D.

Reinforce the rules of engagement.

Buy Now
Questions 22

Which of the following is an intended outcome of a stand-up meeting?

Options:

A.

To identify team members for next tasks

B.

To identify future tasks

C.

To identify stakeholders for next tasks

D.

To identify blocking tasks

Buy Now
Questions 23

During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?

Options:

A.

Defect log

B.

Change log

C.

Issue log

D.

Risk log

Buy Now
Questions 24

A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?

Options:

A.

Milestone

B.

Gantt

C.

Burndown

D.

PERT

Buy Now
Questions 25

A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?

Options:

A.

Forcing

B.

Avoiding

C.

Compromising

D.

Smoothing

Buy Now
Questions 26

A meeting agenda included the following items:

. Review the goals of the project.

. Review the progress of the project.

. Discuss if the project is ready to move forward.

Which of the following best describes this type of meeting?

Options:

A.

Stand-up

B.

Monthly status

C.

Gap analysis

D.

Gate review

Buy Now
Questions 27

During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?

Options:

A.

Statement of work

B.

Business case

C.

Requirements document

D.

Work breakdown structure

Buy Now
Questions 28

While a team was in a work session developing the QA plan for a project, the project manager realized that the team lacks the skills required for proper quality assurance. Which of the following steps should the project manager take next?

Options:

A.

Reassess the resource pool.

B.

Review the QA plan from a similar project.

C.

Check on available resources for additional team members.

D.

Escalate the issue to the project sponsor.

Buy Now
Questions 29

Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?

Options:

A.

Data security

B.

Operational security

C.

Physical security

D.

Digital security

Buy Now
Questions 30

Which of the following best describes the meaning of timeboxing in the context of a project kickoff meeting?

Options:

A.

Allowing a discussion to proceed until a decision is made

B.

Allowing the meeting attendees more time for deeper conversation

C.

Allowing for a flexible timeline so all aspects of the project are covered

D.

Allowing a conversation to continue for a predefined period of time

Buy Now
Questions 31

During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?

Options:

A.

Work breakdown structure

B.

Project charter

C.

Quality plan

D.

Solution design

Buy Now
Questions 32

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

Options:

A.

Performing

B.

Adjourning

C.

Forming

D.

Norming

Buy Now
Questions 33

Project members are based in three countries and each work remotely Which of the following would a project manager use to improve internal project communication?

Options:

A.

Progress reporting

B.

Meeting minutes

C.

Team touch points

D.

Change management

Buy Now
Questions 34

A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?

Options:

A.

Use a software tool during the meeting that can create a transcript of what is discussed.

B.

Have a standing agenda that is vague enough so that it can be used again.

C.

Delegate the roles and responsibilities to improve meeting management.

D.

Reprimand project team members for not completing assigned action items.

Buy Now
Questions 35

A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following describes the grouping of the smaller components?

Options:

A.

An issue

B.

A goal

C.

A backlog item

D.

An epic

Buy Now
Questions 36

Which of the following is the main reason for documenting artifacts?

Options:

A.

To provide a record of the project's progress and achievements for future reference

B.

To show stakeholders that the project is on track and progressing as planned

C.

To help team members be aware of roles and responsibilities

D.

To ensure that the project team understands the importance of the project to the organization

Buy Now
Questions 37

Which of the following best describes a manufacturer's obligation to repair or change, without extra costs, any part of a product that is not functioning?

Options:

A.

Service-level agreement

B.

Functional testing

C.

Warranty period

D.

Audit

Buy Now
Questions 38

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

PK0-005 Question 38

Which of the following issues should be addressed FIRST?

Options:

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.

Buy Now
Questions 39

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

Options:

A.

Determine budget constraints.

B.

Validate the business case.

C.

Update the project charter.

D.

Create a project schedule

Buy Now
Questions 40

Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?

Options:

A.

Update the issue log.

B.

Apply the contingency plan.

C.

Transfer the risk.

D.

Submit a change request.

Buy Now
Questions 41

Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?

Options:

A.

Daily stand-up

B.

Project momentum

C.

Performance feedback

D.

Meeting minutes

Buy Now
Questions 42

A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?

Options:

A.

Reassigning resources

B.

Removing access

C.

Closing contracts

D.

Evaluating the project

Buy Now
Questions 43

Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

Options:

A.

Maintenance window

B.

Risk assessment

C.

Operational security

D.

Validation check

Buy Now
Questions 44

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Options:

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Buy Now
Questions 45

A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?

Options:

A.

Assign more resources to complete similar stories in the future.

B.

Break the stories into workable items that can be completed within one sprint.

C.

Extend the sprint duration when required with the approval of the product owner.

D.

Release the current progress into production and carry over the rest of the code for the next sprint.

Buy Now
Questions 46

A team found a deficiency in an application and is proposing improvements, but the sponsor requests a business case. Which of the following best describes the intended objective of the business case?

Options:

A.

To identify the potential risk and issues for the project

B.

To determine the timeline and budget of the project

C.

To define the specific tasks required to create the project

D.

To specify what problem is being solved by the project

Buy Now
Questions 47

A project manager is meeting with stakeholders to identify objectives and success criteria. Which of the following artifacts is the project manager working on?

Options:

A.

Project charter

B.

Requirements traceability matrix

C.

Project communications plan

D.

Project risk register

Buy Now
Questions 48

Which of the following software programs would be BEST to use lo store information related to business transactions?

Options:

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Buy Now
Questions 49

Which of the following BEST illustrates how team members with different roles should interact on the team?

Options:

A.

SOW

B.

WBS

C.

RACI

D.

PERT

Buy Now
Questions 50

Which of the following project types is best managed as a waterfall project?

Options:

A.

Data analytics

B.

Research

C.

Software development

D.

Real property

Buy Now
Questions 51

A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

Options:

A.

Status report

B.

Project plan

C.

Change log

D.

Meeting minutes

Buy Now
Questions 52

An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).

Options:

A.

Rollback plans

B.

Project management plan

C.

Deployment plan

D.

Asset management plan

E.

Communication plan

F.

Resource management plan

Buy Now
Questions 53

During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

A)

B)

PK0-005 Question 53

C)

PK0-005 Question 53

D)

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Buy Now
Questions 54

A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?

Options:

A.

Agile

B.

Waterfall

C.

Standard

D.

Hybrid

Buy Now
Questions 55

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

Options:

A.

Project change management plan

B.

Project management plan

C.

Project transition plan

D.

Project communication plan

Buy Now
Questions 56

A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?

Options:

A.

Monte Carlo simulation

B.

Root cause analysis

C.

Quantitative risk analysis

D.

Risk response analysis

Buy Now
Questions 57

A client continues to present the project team with additional changes. To help with agreeing upon an expected delivery date, the project manager sets up a meeting with stakeholders. Which of the following should this meeting identify?

Options:

A.

Project scope

B.

Project communication

C.

Project budget

D.

Project objectives

Buy Now
Questions 58

After new capabilities were deployed in a system, issues with preexisting capabilities were reported. Which of the following testing cycles should be used to prevent this issue?

Options:

A.

Performance testing

B.

User acceptance testing

C.

Stress testing

D.

Unit testing

Buy Now
Questions 59

Which of the following tools is best to use when conducting project meetings across time zones?

Options:

A.

Text

B.

Calendaring tools

C.

Videoconference

D.

Email

Buy Now
Questions 60

Which of the following demonstrates awareness of regulations and standards when conducting a project?

Options:

A.

Establishing a measurement system for the team members' performance

B.

Controlling project costs to fall within the company-approved variance

C.

Reviewing advertising trends in the market before launching a new product

D.

Submitting architectural plans for approval before commencing construction

Buy Now
Questions 61

Which of the following considers factors such as reliability, scalability, security, and cost-effectiveness within project goals and objectives?

Options:

A.

DevOps architecture

B.

Computing services

C.

Data warehouse

D.

Networking and connectivity

Buy Now
Questions 62

A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?

Options:

A.

Validation check

B.

Downtime window schedule

C.

Customer notifications

D.

Risk analysis

Buy Now
Questions 63

Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?

Options:

A.

Start-to-start

B.

Start-to-finish

C.

Finish-to-finish

D.

Finish-to-start

Buy Now
Questions 64

A project manager provided details regarding the completion of the following tasks:

Vendor selection took less time than planned.

Equipment procurement took less time than estimated.

Equipment installation went according to schedule.

Which of the following should the project manager update?

Options:

A.

Change log

B.

Project Gantt

C.

Issue log

D.

Requirements traceability matrix

Buy Now
Questions 65

Which of the following PRINCE2 processes includes creating the project plan?

Options:

A.

Starting up a project

B.

Initiating a project

C.

Managing product delivery

D.

Directing a project

Buy Now
Questions 66

An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?

Options:

A.

Development

B.

Production

C.

Testing

D.

QA

Buy Now
Questions 67

Which of the following is the most important activity for the project manager during the closure of a project?

Options:

A.

Obtain project sign-off.

B.

Capture lessons learned.

C.

Document historical information.

D.

Release resources.

Buy Now
Questions 68

As a result of an internal assessment, the steering committee states that the company does not currently have the required skill set or technical tools to develop a particular feature in the project. Which of the following procurement methods would help the company?

Options:

A.

Subscription

B.

Subcontract

C.

Lease

D.

Build

Buy Now
Questions 69

As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?

Options:

A.

Executing the approved contingency plan

B.

Constructing an Ishikawa diagram to determine the root cause

C.

Using a Pareto chart to prioritize the different causes

D.

Engaging the senior management team in regard to the issue

Buy Now
Questions 70

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

Options:

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Statement of work

E.

Cost-plus agreement

Buy Now
Questions 71

A quality assurance team is based in three different locations To validate the project deliverables, a project manager sent the hardware for testing purposes to the team in each of the locations. Two teams confirmed the hardware arrived, but one group did not receive it because of local customs Which of the following ESG factors is the project team facing?

Options:

A.

Awareness of the company vision, mission statement, and values

B.

Impact of the project on the company's brand value

C.

Awareness of applicable regulations and standards

D.

Impact of the project on the local and global environments

Buy Now
Questions 72

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

Options:

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Buy Now
Questions 73

An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

A)

PK0-005 Question 73

B)

C)

PK0-005 Question 73

D)

PK0-005 Question 73

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Buy Now
Questions 74

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

Options:

A.

Escalate the change to the CCB.

B.

Review the requested change.

C.

Document the change recommendations.

D.

Validate the implementation of the requested change.

Buy Now
Questions 75

Which of the following is a quality assurance tool?

Options:

A.

Defining project goals

B.

Identifying the root cause analysis

C.

Assessing employee efficiency

D.

Assessing skill gaps

Buy Now
Questions 76

A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?

Options:

A.

Project scope

B.

Quality plan

C.

Contract obligations

D.

Work breakdown structure

Buy Now
Questions 77

An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?

Options:

A.

Transfer

B.

Mitigate

C.

Avoid

D.

Accept

Buy Now
Questions 78

A team member needs to make an emergency update. The team member is unable to return to the office. Which of the following is the most secure way to make the update?

Options:

A.

At home, using home internet and the company’s computer

B.

At a coffee shop, using free Wi-Fi and the corporate computer

C.

At home, using home internet and the corporate virtual private network

D.

Anywhere the team member would like, using a mobile device and mobile internet

Buy Now
Questions 79

During schedule planning, a project manager determined the logical dependencies required to complete the project. Which of the following activities should the project manager do next?

Options:

A.

Determine the stakeholders positively impacted in the project.

B.

Determine the escalation reporting tool to be used in the project.

C.

Determine the resources required to complete the tasks.

D.

Determine the total cost incurred in the project's execution.

Buy Now
Questions 80

During a PMO audit, an auditor notices a discrepancy between the existing financial report and the financial information provided by the project manager at the end of the project in the previous quarter. Which of the following activities would have most likely avoided this discrepancy?

Options:

A.

Validation of deliverables

B.

Closing contracts

C.

Project sign-off

D.

Removing access

Buy Now
Questions 81

A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?

Options:

A.

Train the team members.

B.

Assess the resource pool.

C.

Develop a QA plan.

D.

Create RACI matrix.

Buy Now
Questions 82

A project is about to start; however, the client is uncertain about the desired details for the final product. Which of the following methodologies should the project manager use?

Options:

A.

Agile

B.

SDLC

C.

Waterfall

D.

PRINCE2

Buy Now
Questions 83

During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?

Options:

A.

Waterfall method

B.

Simulation method

C.

Precedence diagramming method

D.

Cost ratio analysis

Buy Now
Questions 84

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

Options:

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Buy Now
Questions 85

In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?

Options:

A.

Add a new risk.

B.

Perform an impact analysis.

C.

Escalate to the sponsor.

D.

Raise a change request.

Buy Now
Questions 86

An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?

Options:

A.

The ticket system provided access by default without any approval.

B.

The project manager did not perform proper project planning.

C.

The system is lacking proper access controls.

D.

Sensitive data was incorrectly classified during the audit process.

Buy Now
Questions 87

A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?

Options:

A.

Create a list of tasks and share it with the team.

B.

Resend the scope of work to the team.

C.

Review the Gantt chart weekly with the team.

D.

Have the project sponsor meet with the team.

Buy Now
Questions 88

A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to

identify the level of engagement among project team members. Which of the following would be the best tool for the project manager to use?

Options:

A.

Meeting chat

B.

Email

C.

Real-time survey

D.

Whiteboard

Buy Now
Questions 89

Which of the following is a capital expense?

Options:

A.

Building lease

B.

Building purchase

C.

Building maintenance

D.

Building insurance

Buy Now
Questions 90

A project manager is conducting an evaluation of a product to determine whether it is meeting the requirements. The manager needs to compare the current status of the product with its optimal future status and determine what, if anything, needs to be done to improve it. Which of the following types of evaluations would be best for the manager to use?

Options:

A.

Gap analysis

B.

External status report

C.

Cost-benefit analysis

D.

Project closeout report

Buy Now
Questions 91

Which of the following would be considered operational security?

Options:

A.

Mobile device compliance

B.

Background screening

C.

Multifactor authentication

D.

Facility access

Buy Now
Questions 92

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

Options:

A.

RFB

B.

RFQ

C.

RF

D.

RFP

Buy Now
Questions 93

Which of the following tasks should the project manager complete first when validating deliverables?

Options:

A.

Assess the documentation.

B.

Obtain stakeholder feedback.

C.

Review the project objectives.

D.

Mitigate risks.

Buy Now
Questions 94

A project manager and team are reviewing a task that is supposed to take 9 days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional 5 days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

Options:

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

13 days and $3,600

Buy Now
Questions 95

Which of the following is an activity related to operational security?

Options:

A.

Processing background screening

B.

Setting up a firewall

C.

Establishing a zone of trust

D.

Implementing multifactor authentication

Buy Now
Questions 96

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

Options:

A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.

Buy Now
Questions 97

A project team that handles sensitive data analysis recently onboarded three new employees. Which of the following should the PM do first?

Options:

A.

Check employee security clearance

B.

Allow access to the internet on corporate computers

C.

Train the new employees to handle sensitive data

D.

Execute an analysis of the sensitive data

Buy Now
Questions 98

Which of the following BEST identifies the intent and purpose of a project closeout report?

Options:

A.

To provide documentation of lessons learned

B.

To document variances from the initial project baseline

C.

To validate that a project has been successfully completed

D.

To release resources and terminate all access rights

Buy Now
Questions 99

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

Options:

A.

The project manager did not release the resources.

B.

The project is in the verification testing phase.

C.

The project manager did not complete the project closure phase.

D.

The project manager did not remove access.

Buy Now
Questions 100

A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?

Options:

A.

Use an on-premises project management scheduling tool.

B.

Limit access to members of the project team.

C.

Mandate overtime to get the project completed sooner.

D.

Ensure all team members have signed a non-disclosure agreement.

Buy Now
Questions 101

Which of the following statements best describes a content management system?

Options:

A.

A system to manage electronic signatures and document workflow

B.

A system to manage database integration and provide messaging services

C.

A system to manage shared data on the web, allowing multiple contributors to create, edit, and publish

D.

A system to manage documents archival, such as emails, spreadsheets, and support tickets

Buy Now
Questions 102

A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?

Options:

A.

Application deployment

B.

Rollback plans

C.

Validation checks

D.

Maintenance window schedules

Buy Now
Questions 103

Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?

Options:

A.

Send out a survey to the potential end users to gather information about the best functional setup for work productivity.

B.

Provide clear instructions based on personal preference and aesthetics for setup of the work areas.

C.

Explain to team members that the placement of the items is not too important, as long as everything is connected and working.

D.

Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.

Buy Now
Questions 104

A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?

Options:

A.

Build

B.

Subscription

C.

Lease

D.

Buy

Buy Now
Questions 105

Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?

Options:

A.

Gantt chart

B.

Maintenance window schedule

C.

Functional requirements

D.

Test results

Buy Now
Questions 106

A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?

Options:

A.

Transfer

B.

Avoid

C.

Accept

D.

Mitigate

Buy Now
Questions 107

A software engineer notices that the newest update to the reporting software includes many new features that were not defined in the requirements document. Which of the following steps should the engineer take next?

Options:

A.

Seek approval before continuing

B.

Edit the requirements document

C.

Disregard the update

D.

Notify the users of the new features

Buy Now
Questions 108

A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

Options:

A.

Task log

B.

Cadence

C.

Milestones

D.

Work breakdown structure

Buy Now
Questions 109

A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?

Options:

A.

Flat

B.

Projectized

C.

Weak matrix

D.

Functional

Buy Now
Questions 110

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

Options:

A.

Scope creep

B.

Collecting requirements

C.

Decision-making

D.

Project change

Buy Now
Questions 111

Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?

Options:

A.

Telephone

B.

Videoconference

C.

Face-to-face

D.

Email

Buy Now
Questions 112

Which of the following would a scrum team discuss during a daily stand-up meeting?

Options:

A.

The likelihood of uncertain events occurring, the impact of the uncertain events, and the responses to take

B.

Actions to continue, actions to stop, and recommendations on how to proceed in the future for similar endeavors

C.

Buffer utilization and reallocation, critical resources with schedule impacts, and path convergence coordination

D.

Progress from the previous day, projected accomplishments for today, and foreseen issues that may interfere with work

Buy Now
Questions 113

Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?

Options:

A.

SaaS

B.

IaaS

C.

DaaS

D.

PaaS

Buy Now
Questions 114

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

Options:

A.

Update the work breakdown structure.

B.

Review the backlog.

C.

Seek baseline approval.

D.

Establish the resource pool.

Buy Now
Questions 115

A project team selected a random sample of patient accounts for testing the deliverable. The data was masked since it contained patient names. Which of the following describes this type of data?

Options:

A.

Confidential information

B.

Protected health information

C.

Personally identifiable information

D.

Security clearance

Buy Now
Questions 116

A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?

Options:

A.

Milestone chart

B.

Work breakdown structure

C.

Project charter

D.

Detailed scope statement

Buy Now
Questions 117

A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?

Options:

A.

Inform the CCB to stop communication.

B.

Establish a RACI matrix.

C.

Escalate the communication issues.

D.

Revise the communication plan.

Buy Now
Questions 118

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

PK0-005 Question 118

Which of the following most likely represents the number of items in the backlog?

Options:

A.

23

B.

5

C.

10

D.

15

Buy Now
Questions 119

A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?

Options:

A.

Key stakeholder identification

B.

Preliminary procurement

C.

Solution design determination

D.

Critical factor enlistment

Buy Now
Questions 120

During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

Options:

A.

PERT chart

B.

Milestone chart

C.

Gantt chart

D.

Budget burndown chart

Buy Now
Questions 121

A new stakeholder has joined a project and has a different vision of the scope. The sponsor is requiring the project manager to provide a document in which the initial scope of the project is defined. Which of the following should the project manager do next to clarify the differences?

Options:

A.

Create a new project management plan.

B.

Collect all project meeting minutes.

C.

Perform project scope management.

D.

Review the project charter.

Buy Now
Questions 122

During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.

INSTRUCTIONS

Review the email with the latest updates sent by the project sponsor and respond in

the following order:

1. Select the best tool for tracking the server migration progress.

2. Select the new critical path.

3. Select the correct number of engineers required for the server migration phase.

If at any time you would like to bring back the initial state of the simulation, please click

the Reset All button.

Select the Appropriate Tool:

PK0-005 Question 122

PK0-005 Question 122

Select the new critical path.

Option A

Option B

Option C

PK0-005 Question 122

Options:

Buy Now
Questions 123

Which of the following best describes the difference between the current state and the desired future state in project management?

Options:

A.

The current state is a high-level view of the project scope, and the desired state is what is happening right now.

B.

The current state is where the business is now, and the desired state is where the project is going to take the business.

C.

The current state is a high-level view of the project scope, and the desired future state is the specific outcome the business wants.

D.

The current state defines the specific outcome the business wants, and the desired state documents what is happening now that prevents it.

Buy Now
Questions 124

A project team is developing an application that will allocate a building's parking spaces. The building owner does not agree with using corporate colors in the application and has blocked

the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

Options:

A.

Review of existing artifacts

B.

Development of an issue log

C.

Identification and assessment of stakeholders

D.

Establishment of accepted communication channels

Buy Now
Questions 125

Which of the following should be the PRIMARY basis for establishing metrics that measure the effectiveness of an information security program?

Options:

A.

Residual risk

B.

Regulatory requirements

C.

Risk tolerance

D.

Control objectives

Buy Now
Questions 126

Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?

Options:

A.

Escalate directly to the project sponsor

B.

Push the kickoff meeting out by one week

C.

Proceed with the kickoff as planned

D.

Identity replacements for project stakeholders

Buy Now
Questions 127

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

Options:

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

Buy Now
Questions 128

Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?

Options:

A.

Social

B.

Regulatory

C.

Environmental

D.

Governmental

Buy Now
Questions 129

Which of the following should a product manager choose in order to enable collaboration between team members located in different regions? (Select two).

Options:

A.

Real-time surveys/polling

B.

Wiki knowledge base

C.

Spreadsheets

D.

Meetings/face-to-face

E.

Real-time, multi-authoring editing software

F.

Charting/diagramming

Buy Now
Questions 130

The project manager sends individual messages to team members about what must be accomplished. However, the team communicates confusion about the tasks assigned. Which of the following communication methods would be best to use?

Options:

A.

Informal internal

B.

Asynchronous verbal

C.

Synchronous external

D.

Formal written

Buy Now
Questions 131

The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

Options:

A.

Data warehouse

B.

SQL database

C.

Multitier architecture

D.

Content management system

Buy Now
Questions 132

A project team has been assigned to improve the customer service of a retail company. The team has conducted a thorough analysis of the existing process, determined areas of improvement, and identified the desired outcomes of the project. Which of the following best describes this analysis?

Options:

A.

Process improvement

B.

Business objectives

C.

Current state vs. future state

D.

Project success criteria

Buy Now
Questions 133

Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement Which of the following would be the best tool the project manager can use to provide this information to the stakeholders?

Options:

A.

Risk register

B.

Change log

C.

Traceability matrix

D.

Project status report

Buy Now
Questions 134

A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?

Options:

A.

SOW

B.

RFI

C.

RFQ

D.

WBS

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2026)
Last Update: Mar 28, 2026
Questions: 447

PDF + Testing Engine

$63.52  $181.49

Testing Engine

$50.57  $144.49
buy now PK0-005 testing engine

PDF (Q&A)

$43.57  $124.49
buy now PK0-005 pdf