PMI-SP PMI Scheduling Professional Questions and Answers

Questions 4

You are the project manager of the NHQ project. This project deals with a new technology that your company has never used before. You have petitioned the management to hire a consultant to help you and the project team to create the WBS, the activity list, and complete the duration estimates. The management is concerned about the costs of the consultant, but agrees to your request because of the nature of this new work. The consultant can best be described as what type of resource for this project?

Options:

A.

Direct expense

B.

External requirement

C.

Temporary resource

D.

Expert judgment

Buy Now
Questions 5

You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the difference between total float and free float. What is the difference between total float and free float?

Options:

A.

Total float is the amount of time an activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.

B.

Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project successors.

C.

Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project predecessors.

D.

Total float is the amount of time a non-critical activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.

Buy Now
Questions 6

You have been hired as a project manager for Tech Perfect Inc. You are studying the documentation of planning of a project. The documentation states that there are twenty-five stakeholders with the project. What will be the number of communication channels for the project?

Options:

A.

300

B.

50

C.

600

D.

25

Buy Now
Questions 7

You are the project manager of a research project. Because much of the project work will be based on what is discovered in each stage of the project work, you are directing the project time to focus on creating time estimates for the most imminent research work and broad estimates for the project work that is coming later in the project. What type of planning are you using in this project?

Options:

A.

Milestone planning

B.

Rolling wave planning

C.

Phase gates

D.

Decomposition

Buy Now
Questions 8

Don is the project manager of the NQP project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have government regulations. Management is concerned with the regulations and would like Don to report on the activities that will be affected by the regulations. Which of the following documents should Don refer to, for the information on the activities and the regulations?

Options:

A.

Risk management plan

B.

Activity list

C.

Activity list and attributes

D.

Risk register

Buy Now
Questions 9

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone, which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. Based on the budget at completion, what is this project ' s to-complete performance index?

Options:

A.

-$108,120

B.

0.98

C.

$2,500.000

D.

1.02

Buy Now
Questions 10

Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?

Options:

A.

Precedence Diagramming Method

B.

Schedule network template

C.

Dependency determination

D.

Activity on the Node

Buy Now
Questions 11

Tom works as the project manager for BlueWell Inc. He is working with his project to ensure timely and appropriate generation, retrieval, distribution, collection, storage, and ultimate disposition of project information. What is the process in which Tom is working?

Options:

A.

Work performance measurement

B.

Stakeholder expectation management

C.

Project communication management

D.

Stakeholder analysis

Buy Now
Questions 12

Which of the group creativity techniques enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or prioritization?

Options:

A.

Idea/mind mapping

B.

Delphi technique

C.

Nominal group technique

D.

Affinity diagram

Buy Now
Questions 13

Fill in the blank with the appropriate word. ____ management sets the boundaries for the project and is the foundation on which the other project elements are built.

Options:

Buy Now
Questions 14

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure:

PMI-SP Question 14

Options:

A.

Communications bull ' s eye

B.

Performance goals

C.

Earned value management goals

D.

Project exception report

Buy Now
Questions 15

The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?

PMI-SP Question 15

Options:

A.

Static

B.

Deterrent

C.

Noise

D.

Barrier

Buy Now
Questions 16

Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?

Options:

A.

Archive the project records.

B.

Summarize the project risks costs.

C.

Summarize the project variance.

D.

Close the project office.

Buy Now
Questions 17

You are the project manager for your company. You are working with the management regarding the exact end date of your project. Management needs to know what day of the week your project will complete. Assuming that your project will not require any work to be completed over the upcoming weekends and that the remaining project work will commence on a Tuesday, what day of the week will the project end if there are 67 days of project work left to complete?

Options:

A.

Wednesday

B.

Thursday

C.

Monday

D.

Tuesday

Buy Now
Questions 18

What is the term assigned to graphic in the figure given below?

PMI-SP Question 18

Options:

A.

Communications bull ' s eye

B.

Performance goals

C.

Earned value management goals

D.

Project exception report

Buy Now
Questions 19

You work as a project manager for BlueWell Inc. You want to increase the overall duration of the project. If the management elects to use resource leveling, then what will happen to the project duration?

Options:

A.

The duration will increase, but the labor will stay the same.

B.

The duration will decrease as new team members are brought onto the project.

C.

Nothing, new resources will be incorporated into the project team.

D.

The duration will increase, but the labor will decrease.

Buy Now
Questions 20

Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Procurement document

B.

Contract

C.

Business case

D.

Project statement of work

Buy Now
Questions 21

Which of the following documents captures and defines the work activities, deliverables, and a timeline that a vendor will execute against in performance of work for a customer?

Options:

A.

Project charter

B.

Scope of statement

C.

SOW

D.

WBS

Buy Now
Questions 22

The Define Activities process is the first process in the project time management knowledge are a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?

Options:

A.

Activity list

B.

Milestone list

C.

Activity attributes

D.

Project document updates

Buy Now
Questions 23

Harry is the project manager of a large network installation project. This project requires Harry to add network cable to each office and cubicle of a 14-story office building. Harry will receive a bonus for good time and cost performance in this project. What law of economics would prevent Harry from exponentially adding labor to the project work in an effort to complete the work in a very small amount of time?

Options:

A.

Parkinson ' s Law

B.

Law of Diminishing Returns

C.

Law of Economics

D.

Moore ' s Law

Buy Now
Questions 24

John works as the project manager for Blue Well Inc. He is identifying the phases within the scope of work for the project plan. Which of the following can be categorized as a project phase? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Concrete

B.

Pre-construction

C.

Engineering

D.

Conceptual engineering

Buy Now
Questions 25

You are the project manager for your organization. You are working with your virtual team to create activity duration estimates for your current project. This virtual team is comprised of team members from around the world. Much of this process will be completed by geographical locations though some conferences will require all the team members to participate and to coordinate the activities that will interact between the different sites. The project manager must consider all of the following when creating the activity duration estimates except for which one?

Options:

A.

Project calendar

B.

Critical path

C.

Resource calendar

D.

Time zone differences

Buy Now
Questions 26

Jeff is the project manager of the GHY Project for his organization. He has created the project network diagram as shown in the figure:

PMI-SP Question 26

Management is reviewing the network diagram, and they are concerned about the latest date that Activity I can finish. What is the latest day Activity I can finish without affecting the project end date?

Options:

A.

Day 20

B.

Day 22

C.

Day 17

D.

Day 19

Buy Now
Questions 27

You are the project manager for your organization. You are discussing an upcoming project with management and they would like you to begin decomposing the project work packages into activities as soon as possible. You have explained to the management that you would like to involve your roject team before the decomposition of the work packages begins. Why would you want your project team to involve in this activity?

Options:

A.

To understand the exact type of work the project team will be completing

B.

To help the activity go faster

C.

To get better and more accurate results through the decomposition

D.

To create assignments for the project team as the activities are discussed

Buy Now
Questions 28

You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record this communication requirements based on your stakeholder analysis?

Options:

A.

Project communications management plan

B.

Project reporting structure

C.

Project schedule

D.

Project scope management plan

Buy Now
Questions 29

You work as a project manager for BlueWell Inc. By referring to the figure given below, you along with your project team is calculating the latest completion of an activity.

PMI-SP Question 29

What is the latest your project team can complete Activity I?

Options:

A.

Day 29

B.

Day 26

C.

Day 25

D.

Day 30

Buy Now
Questions 30

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly ' s schedule variance for this project?

Options:

A.

$163,626

B.

$130,901

C.

-$985,040

D.

0.16

Buy Now
Questions 31

Terri is the project manager for her organization and she is working with her project team to develop the project schedule. She has identified the float in her project although some of the activities where float exists may be susceptible to risk in the project execution. She is also concerned that the critical path may change during the project if the risk events come into execution. What scheduling method is Terri using in this example?

Options:

A.

Critical chain method

B.

Risk analysis method

C.

Activity on the arrow method

D.

Critical path method

Buy Now
Questions 32

You are the project manager of the HGH Project. Thomas, your project sponsor, asked you to submit status reports every week, but now he wants you to submit the status reports every other week. What project management plan would you need to update to reflect this change from Thomas?

Options:

A.

Scope management plan

B.

Performance management plan

C.

Communications management plan

D.

Project management plan

Buy Now
Questions 33

You are the project manager of the NHQ project. You are working with your project team to create the project schedule and the project network diagram. In order to start the sequencing of the project activities, you will need a document to identify the result of project phases, key project deliverables, and significant, timeless events in the project. Which of the following documents will you need to help sequence the project work?

Options:

A.

Activity attributes

B.

Activity list

C.

Project scope statement

D.

Milestone list

Buy Now
Questions 34

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

Options:

A.

Project change control process

B.

Perform integrated change control process

C.

Configuration management

D.

Communications management

Buy Now
Questions 35

What formula would you use if your project had a BAC of $450,000, you have spent $191,000, and you are 40 percent complete though you are supposed to be 55 percent done and management wants to know your project ' s schedule performance index?

Options:

A.

($450,000 - $180,000) / ($450,000 - $191,000)

B.

$450,000 - $477,500

C.

$180,000 / $247,500

D.

$180,000 - $247,500

Buy Now
Questions 36

Tom works as the project manager for BlueWell Inc. He spends the majority of his time communicating with team members and the project stakeholders. Various communication skills are involved in the communication processes. Which communication skills are involved in this process? Each correct answer represents a part of the solution. Choose all that apply.

Options:

A.

Internal and External

B.

Vertical and Horizontal

C.

Confronting and problem solving

D.

Formal and Informal

Buy Now
Questions 37

You are the project manager for the NQQ Project for your organization. You and the project team are creating the activity list for the NQQ Project. You have instructed the project team members that they should include an activity identifier and a scope of work description for each activity in the activity list. Why is this information needed?

Options:

A.

To track the work to the project requirements

B.

To maintain profit and loss statements for the project

C.

To help the project team understand what work is required to be completed

D.

To communicate the work to be completed to the project stakeholders

Buy Now
Questions 38

You work as a scheduler for your organization. You are developing a schedule and its constraints for the SAP project. There are nine inputs to develop a project schedule. Which of the following is NOT an input to the schedule development process?

Options:

A.

Work breakdown structure

B.

Activity attributes

C.

Resource calendars

D.

Activity list

Buy Now
Questions 39

Which of the following allows activities to be done in parallel that would normally be done in sequence?

Options:

A.

Lag time

B.

Lead time

C.

Fast tracking

D.

Crashing

Buy Now
Questions 40

Joseph works as the project manager of the NHQ Project. He has created the project network diagram as shown in the figure:

PMI-SP Question 40

Based on the network diagram, find out which path is the critical path for this project?

Options:

A.

ABEHJ

B.

ABDIJ

C.

ABDHJ

D.

ACFIJ

Buy Now
Questions 41

John is a scheduler in ABC Company. He has to plan an activity for the schedule models. Which of the following activities will he use to make the schedule models? . Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Hammocks

B.

Critical path scheduling

C.

Flags

D.

Tasks

Buy Now
Questions 42

You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets and four other documents as inputs to this process. Which of the following is NOT one of the four documents you will need for activity sequencing?

Options:

A.

Project scope statement

B.

Milestone list

C.

Project schedule network diagrams

D.

Activity list

Buy Now
Questions 43

You are the project manager of the NHQ project. Your project has a budget of $1,258,456, and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Management would like to create a report telling them how much more the project will need to complete. What value should you tell management?

Options:

A.

$566,305

B.

$787,504

C.

$1,312,504

D.

$733,456

Buy Now
Questions 44

You are the project manager of the GHQ Project. You have to prioritize activities for the effective management of project. For this, you have created a network diagram to schedule a set of project activities as shown in the figure:

PMI-SP Question 44

Based on this figure, what is the critical path of this project?

Options:

A.

ABEHJ

B.

ACFIJ

C.

ADGJ

D.

ACFGJ

Buy Now
Questions 45

You are the project manager for your organization. You are working with your project team to create the schedule baseline for your project. You will also be creating the schedule data for this project. The schedule data typically includes all of the following except for which one?

Options:

A.

Risk activities

B.

Schedule activities

C.

Activity attributes

D.

Schedule milestones

Buy Now
Questions 46

Which of the following processes fall under the Project Integration Management knowledge area? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Quality Assurance

B.

Project Plan Development

C.

Integrated Change Control

D.

Project Plan Execution

Buy Now
Questions 47

You are the project manager for the NGH project. The figure given below represents the small project you are completing for your organization.

PMI-SP Question 47

How much float can you use on Activity G if Activity B actually takes eight days to complete?

Options:

A.

Four

B.

Three

C.

Seven

D.

Zero

Buy Now
Questions 48

You are the project manager for your organization. Your current project has a schedule variance of -$37,500 and a schedule performance index of 0.94. What do these values mean in regard to project performance?

Options:

A.

Your project is likely to be late and over budget.

B.

Your project is performing well.

C.

Your project has a planned value of $600,000.

D.

Your project is six percent off schedule and has a considerable schedule variance.

Buy Now
Questions 49

A project team installs 2,500 light fixtures in a new office building, and each light fixture takes one hour to install. The project manager can predict that it will take 2,500 hours to complete the work. However, which of the following statements most accurately describes this parametric estimate assumption?

Options:

A.

As workers complete the installation, efficiency will increase and durations will decrease.

B.

As workers complete the installation, errors and risks will increase the actual completion.

C.

As workers complete the installation, effort will diminish and efficiency will decrease.

D.

As workers complete the installation, labor will diminish so duration will increase.

Buy Now
Questions 50

You have been hired as a contract project manager for Tech Perfect Inc. The project has already been started. Sufficient details of the project have already been structured. You are working with your team for cost estimation of the project. Which of the following estimating techniques will you use for the highest degree of accuracy?

Options:

A.

Parametric modeling

B.

Analogous

C.

Top-down

D.

Bottom-up

Buy Now
Questions 51

You are the project manager of a project that has a budget of $875,000 and you have completed 40 percent of the project work. Due to some errors, however, you have actually spent $425,000 of the budget. Management wants to know what the project ' s cost performance index is. What value do you report?

Options:

A.

-$75,000

B.

$350,000

C.

.82

D.

-$187,500

Buy Now
Questions 52

Fill in the blank with an appropriate phrase. The ________is defined in terms of either the product or the type of customer or industry sector.

Options:

Buy Now
Questions 53

You are the project manager of the OOI Project and you ' re forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should be at the 45 percent milestone today, but due to some early delays you ' re running late. What is the planned value of your project?

Options:

A.

$950,000

B.

$2,375,000

C.

$1,055,543

D.

$938,260

Buy Now
Questions 54

You are the project manager of the NHQ Project. You are coaching Alice, a new project manager, on the relationships in a project network diagram. Which relationship type between activities are the most common?

Options:

A.

SS

B.

FS

C.

FF

D.

SF

Buy Now
Questions 55

Fill in the blank with an appropriate phrase. The _______contains the schedule components and the rules for relating and using the components to represent the process for completing a project.

Options:

Buy Now
Questions 56

You work as a project manager for BlueWell Inc. You would like to crash your project to help the project schedule to get back on track. What is the primary danger of crashing?

Options:

A.

Crashing increases project costs.

B.

Crashing is a top-down approach to project completion.

C.

Crashing restricts resource utilization.

D.

Crashing always increases project risks.

Buy Now
Questions 57

You are the project manager of the QAQ Project. The QAQ Project has a BAC of $2,786,121. You are currently 20 percent complete with this project, though you should be 25 percent complete with the project work. The project has consumed $595,000 of the project budget to date. Management has asked you, based on the current project performance, what the project ' s estimate to complete will be considering the current project schedule variance. What is the ETC for this project?

Options:

A.

$2,975,000

B.

1.02

C.

$139,306

D.

$2,380,000

Buy Now
Questions 58

You work as a Project Manager for Media Perfect Inc. Several projects are running under your supervision. Rick, team leader of a project, provides you performance indexes of his project. The schedule variance (SV) of his project is 25. What does this figure depict?

Options:

A.

Project is behind the schedule.

B.

Costs are higher than planned.

C.

Project is right on target.

D.

Project is ahead of the schedule.

Buy Now
Questions 59

You work as the project manager for BlueWell Inc. You are recording the activity status for your project team ' s performance in the project. Based on the current performance your project is likely to be three months late. What type of communication should be generated based on this performance issue?

Options:

A.

Issue report

B.

Exceptions report

C.

Variance analysis

D.

Performance report

Buy Now
Questions 60

Holly is a new project manager in your organization. She is working with you on the JHG project and she is confused as to why the project needs a schedule management plan and a schedule baseline. What is the difference between the schedule management plan and the schedule baseline?

Options:

A.

The schedule management plan describes how the schedule will be managed and controlled. The schedule baseline is used to compare with actual results to determine if a change, corrective action, or preventive action is needed.

B.

The schedule management plan describes how the schedule will be managed and controlled. The schedule baseline is used to determine how accurate the schedule management plan has been throughout the project execution.

C.

The schedule baseline describes how the schedule will be managed and controlled. The schedule management plan is used to compare with actual results to determine if a change, corrective action, or preventive action is needed.

D.

The schedule management plan describes how the schedule will be created. The schedule baseline is used to compare with actual results with what the project manager intended.

Buy Now
Questions 61

John is the project manager for his organization. Management has asked John to fast track his project in order to reach a particular date for the project completion. When John fast tracks the project what project management component must be updated to reflect this decision? Choose the best answer.

Options:

A.

Organizational process assets

B.

Cost management plan

C.

Resource calendars

D.

Risk register

Buy Now
Questions 62

In which of the following group decision making techniques does the largest block in a group decide the group decision even if a bulk is not achieved?

Options:

A.

Majority

B.

Unanimity

C.

Dictatorship

D.

Plurality

Buy Now
Questions 63

Which of the following techniques is used to perform progressive elaboration planning where the work to be accomplished in the near future is planned in detail at a low level of the work breakdown structure?

Options:

A.

Imminent activity management

B.

Predecessor-only diagramming

C.

Rolling wave planning

D.

Decomposition

Buy Now
Questions 64

You work as a project manager for BlueWell Inc. You are in the process of identifying all the people and organization impacted by the project. Mark, a project team member, has some doubts about the inputs of the Identify Stakeholder process. What is referred to as an input to the identify stakeholder process in project communication management?

Options:

A.

Expert judgment

B.

Project charter

C.

Stakeholder analysis

D.

Stakeholder register

Buy Now
Questions 65

You work as a project manager for BlueWell Inc. You and your project team is undergoing the decision making process for the project. You want to involve key participants to gain acceptance and commitment to make the solution work. Which of the following phases of the decision- making model defines this process of work?

Options:

A.

Ideas to action

B.

Problem definition

C.

Problem solution generation

D.

Solution action planning

Buy Now
Questions 66

Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy ' s project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

Options:

A.

-$75,000

B.

-$42,000

C.

-$45,000

D.

-$65,000

Buy Now
Questions 67

Winnie is the project manager for her company. She has been recording the actual durations of the project work to determine the actual progress of her project. Winnie needs to generate an updated project schedule based on project performance. She is using the supporting schedule data, manual scheduling methods, and her project management software to perform schedule network analysis. What other tool Winnie can use to help and generate an updated project schedule?

Options:

A.

Critical path method

B.

Schedule management plan

C.

Scheduling tool

D.

Critical chain method

Buy Now
Questions 68

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project ' s schedule variance?

Options:

A.

-$48,654

B.

13 percent

C.

-$225,000

D.

0.98

Buy Now
Questions 69

Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy ' s project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

Options:

A.

-$75,000

B.

-$42,000

C.

-$45,000

D.

-$65,000

Buy Now
Questions 70

You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure:

PMI-SP Question 70

Mary, a project team member, reports that an identified risk is likely to happen in the project that will affect the completion date of Activity D . She reports that the risk event will likely cause the duration of the activity to increase by six days. If this happens what is the earliest the project can complete?

Options:

A.

32 days

B.

29 days

C.

27 days

D.

26 days

Buy Now
Questions 71

Which of the following statements best describes an activity in a project?

Options:

A.

It is a defined set of functions a resource must complete for the project scope to be considered complete.

B.

It is the effort needed to complete a work package.

C.

It is the unit of resource utilization needed to complete a project deliverable.

D.

It is a listing of all project work that must be accomplished for the project scope to be considered complete.

Buy Now
Questions 72

You are the project manager of the AHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive a bonus of $5,000 per day of early completion. Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible, but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?

Options:

A.

Adding leads to the project work

B.

Fast tracking

C.

Crashing

D.

Using the critical chain method

Buy Now
Questions 73

You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project. What project management process are you working with when you create a new target schedule?

Options:

A.

Estimate activity durations

B.

Estimate activity resources

C.

Control schedule

D.

Develop schedule

Buy Now
Questions 74

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that Fred needs to report to management?

Options:

A.

$122,845

B.

-$51,000

C.

-$85,000

D.

Zero

Buy Now
Questions 75

Tom is the project manager of the GHQ Project for his organization. He is working on recovering the project schedule. As Tom examines his schedule he is especially aware of project activities with soft logic. What is soft logic?

Options:

A.

Soft logic describes activities that do not have particular resources assigned to them.

B.

Soft logic describes activities that can be completed in any order.

C.

Soft logic describes activities that can have lead time added to them.

D.

Soft logic describes activities that can be crashed because they are effort-driven.

Buy Now
Questions 76

Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.

Options:

A.

Quality inspections and compliance

B.

Location, logistics, and resource availability analysis

C.

Labor productivity studies from previous similar projects in the area

D.

The average price of general labor in the area

Buy Now
Questions 77

You are the project manager of the JKM Project for your organization. Your project is supposed to be 60 percent complete but you are only 45 percent complete. The project has an assigned budget of $765,000 but you have already spent $365,000 to reach this point in the project due to some errors and rework. Management is pressing you on when you ' ll complete the project and how much the project will likely cost based on the current performance. You need to tell management what the project ' s current cost performance index (CPI) is. What value should you report to management based on your project ' s performance?

Options:

A.

$306,000

B.

.94

C.

$344,250

D.

.75

Buy Now
Questions 78

You are the project manager of the NHG. The following figure represents your project network diagram.

PMI-SP Question 78

Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they ' ll affect Activity I. The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?

Options:

A.

The critical path will now take 26 days.

B.

The critical path will now take 17 days.

C.

The critical path will now take 23 days.

D.

The critical path will now take 20 days.

Buy Now
Questions 79

You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?

Options:

A.

Push technique

B.

Many-to-many

C.

One-to-one

D.

Pull technique

Buy Now
Questions 80

You work as a project manager for BlueWell Inc. Your project is falling behind though the project team reports that the actual durations of their work is what they estimated. You investigate the cause and determine that the project team is not starting their assignments early enough to finish their work on time. While the duration of the assignments may be in synchronization with the duration estimates, the completion time is causing the project schedule to slip from the baseline. What can you do to rectify this problem?

Options:

A.

Increase the duration estimates for each activity.

B.

Discipline the project team.

C.

Add management reserve.

D.

Corrective actions.

Buy Now
Questions 81

Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the project completion date, so Gina is stressing to her project team members that while they need to provide and account for all of the project activities, they should focus on one work package in the WBS at a time. In order to start the decomposition of the project work packages into activities, Gina will need all of the following except for which one?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

WBS

D.

Enterprise environmental factors

Buy Now
Questions 82

John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure:

PMI-SP Question 82

Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?

Options:

A.

Zero

B.

One

C.

Four

D.

Five

Buy Now
Questions 83

You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?

Options:

A.

It means the largest schedule variance you can have is five percent.

B.

It is the earned value divided by the planned value for your project.

C.

It is the expectation of management to be 95 on schedule at 95 percent of the project.

D.

It means you will need to earn at least 95 cents per dollar invested in the project.

Buy Now
Questions 84

Beth is the project manager for her organization. Her current project has many deliverables that have been defined at a high level, but the details of the deliverables are still unknown. In her project, Beth is planning in detail only the activities that are most imminent in the project work. This approach to project management planning is known as what?

Options:

A.

Imminent activity management

B.

Rolling wave planning

C.

Predecessor-only diagramming

D.

Decomposition

Buy Now
Questions 85

Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project, the duration of the project activities, and the sequence in which the project work must be completed. During several phases of her project, the project team will need to work more than fifty hours per week. The project team members have agreed this is necessary and they ' re willing to do the work to complete the project. Management, however, has not approved Holly ' s schedule based on the overtime the scheduling will require. They have set a limit on the project schedule of 45 hours per week. What is this limit technically called? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Constraint

B.

Assumption

C.

Execution variance analysis

D.

Resource leveling heuristic

Buy Now
Questions 86

You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activity process will help you in identifying the typical schedule milestones?

Options:

A.

Expert Judgment

B.

Decomposition

C.

Rolling Wave Planning

D.

Templates

Buy Now
Questions 87

You are the project manager of the NHQ project. This project deals with a new technology that your company has never used before. You have petitioned the management to hire a consultant to help you and the project team to create the WBS, the activity list, and complete the duration estimates. The management is concerned about the costs of the consultant, but agrees to your request because of the nature of this new work. The consultant can best be described as what type of resource for this project?

Options:

A.

Direct expense

B.

External requirement

C.

Temporary resource

D.

Expert judgment

Buy Now
Questions 88

Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal resource that can complete several of the project activities that deal with the fiber optic cables. Because Tim is a highly-skilled resource, he is already scheduled on several projects within the organization and is not available when Beth needs him to complete some of the project activities. This is an example of which term?

Options:

A.

Resource calendar conflict

B.

Matrix network

C.

Organizational process assets

D.

Activity resource requirements

Buy Now
Questions 89

Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response?

Options:

A.

Diane

B.

Project sponsor

C.

Risk owner

D.

Subject matter expert

Buy Now
Questions 90

Tom is the project manager of the HQQ Project. His project has a schedule variance of -$34,500 due to some errors early in the project. Management would like to know how Tom will respond to these variances. What action can help Tom to manage the errors in the project and to ensure that the errors would not occur again?

Options:

A.

Lesson learned documentation

B.

Risk analysis

C.

Preventive action

D.

Corrective action

Buy Now
Questions 91

Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort. Which of the following is the best example of apportioned effort?

Options:

A.

Adding features to the project ' s product that is not included in the project scope.

B.

Managing the day-to-day events of a project.

C.

Creating software as defined in the project scope.

D.

Completing project activities as start-to-start events.

Buy Now
Questions 92

Which one of the following estimate types is a form of expert judgment?

Options:

A.

Parametric estimate

B.

Analogous estimate

C.

Bottom-up estimate

D.

Definitive estimate

Buy Now
Questions 93

You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?

Options:

A.

Cost variance report

B.

Exceptions report

C.

Performance management report

D.

Schedule variance report

Buy Now
Exam Code: PMI-SP
Exam Name: PMI Scheduling Professional
Last Update: Apr 30, 2026
Questions: 323

PDF + Testing Engine

$63.52  $181.49

Testing Engine

$50.57  $144.49
buy now PMI-SP testing engine

PDF (Q&A)

$43.57  $124.49
buy now PMI-SP pdf