At Marks4sure, we are dedicated to providing IT professionals with the most accurate and reliable preparation materials for the PRINCE2 PRINCE2-7-Practitioner exam. To support your certification journey, we have made a selection of our premium 2026 PRINCE2 Certification practice questions and answers available completely free. You can take this practice test as many times as you need. Every question includes a detailed, expertly verified explanation to ensure you fully grasp the core security concepts before test day.

Questions 4

RISK

Here are three items of information relating to the ‘risk’ practice.

In which management product (A–E) should each item be recorded?

Choose only ONE management product for each item of information. Each management product may be used once, more than once, or not at all.

Options:

A.

Risk register

B.

Issue register

C.

Quality management approach

D.

Issue report

E.

Risk management approach

Item 1:

A cracked pane has already been identified and replacement is planned for next week. The project manager records the separate uncertainty that the supplier may miss that future replacement date and delay subsequent work.

Item 2:

The agreed procedure states that the project board and project manager will review all open risks during every end stage assessment.

It

Buy Now
Questions 5

During ‘closing a project’, the project manager updates the arrangements that specify how and when the Head of the Portfolio Office will measure the increase in business opportunities after LouisShopping enters operational use.

During which closing activity should this be done?

Options:

A.

Prepare planned closure

B.

Confirm project acceptance

C.

Evaluate the project

D.

Request project closure

Buy Now
Questions 6

At project closure, the project manager prepares the end project report, noting that the project exceeded its budget by 10% and planned duration by 15% because of additional heritage protection work. The findings are summarized for the project board and shared with the LOB Portfolio Director so that other projects can learn from them.

Which practice is being applied?

Options:

A.

Business case

B.

Plans

C.

Progress

D.

Quality

Buy Now
Questions 7

The target state for LouisShopping requires the car park to be monitored continuously, 24 hours a day and seven days a week, as an ongoing safety routine.

Under which heading of the change management approach should this requirement be recorded?

Options:

A.

State characteristics

B.

Enabling activities

C.

Resources

D.

Responsibilities

Buy Now
Questions 8

The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.

Is this an appropriate approach to leading a successful team, and why?

Options:

A.

Yes, because bringing in a replacement subcontractor with the necessary technical skills will enable stage 4 activities to resume and reduce the risk of further delays to the overall project

B.

Yes, because the project manager has the authority to source a subcontractor when an existing team member lacks the technical competence required for their assigned work package

C.

No, because before recommending full team replacement the project manager should first seek to understand the nature of the competency gap and explore support options

D.

No, because the project manager and the survey team manager jointly developed and agreed the terms of the work package, and replacing the team contradicts the co-created ways of working

Buy Now
Questions 9

A high-level requirement that the design should be consistent with its surroundings was recorded during ‘starting up a project’. During initiation, the project manager works with Council members, residents, retailers and BuildyBrick to clarify the required design characteristics and define measurable acceptance criteria.

Which management product should be updated with this information?

Options:

A.

Project product description

B.

Work package

C.

Product flow diagram

D.

Project plan

Buy Now
Questions 10

During stage 2, the Heritage Director, acting as senior user, reviews the design and raises a concern that the previously requested heritage trail has not been addressed.

Is this an appropriate use of the ‘give ongoing direction’ activity, and why?

Options:

A.

Yes, because a project board member may raise concerns and provide ongoing direction within the authority delegated to the board

B.

Yes, because the senior user has an obligation to formally approve key specialist products produced during stages 2 and 3 as a standard action within the ‘give ongoing direction’ activity

C.

No, because the ‘give ongoing direction’ activity is only triggered when the project manager proactively requests a review by the project board, not when individual board members identify concerns independently

D.

No, because the Heritage Director should first seek the agreement of the full project board before raising individual concerns, to ensure a unified project board position is presented to the project manager

Buy Now
Questions 11

While preparing the project plan during initiation, the project manager proposes that stage 2 should end at the Council’s financial year-end. This would allow the decision on funding for stage 3 to coincide with the Council’s annual budget process.

Is this an appropriate application of the ‘manage by stages’ principle, and why?

Options:

A.

Yes, because a stage boundary may be aligned with an important external decision point, such as a funding approval

B.

Yes, because every stage may end immediately after one specialist product has been completed and funding has been approved

C.

No, because stage length must be determined solely by the level of risk

D.

No, because stage length must be determined by the technical complexity of the work

Buy Now
Questions 12

As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.

Under which ‘directing a project’ activity is this informal consultation provided?

Options:

A.

Authorize a stage or exception plan

B.

Give ongoing direction

C.

Authorize initiation

D.

Authorize the project

Buy Now
Questions 13

Before the end of stage 2, the project board authorizes a change that adds more trees and seating to the external landscaping. The change can be delivered in stage 3 without any forecast breach of project tolerance. While preparing the next stage plan, the project manager incorporates the additional products and work, updates the relevant product descriptions and product register entries, and reviews whether the project initiation documentation needs to be updated.

Is this an appropriate application of ‘prepare the next stage plan’, and why?

Options:

A.

Yes, because the next stage plan should reflect authorized changes, with affected product information and the project initiation documentation updated where necessary

B.

Yes, because every authorized change must be implemented through an exception plan before the related work may enter the following stage

C.

No, because authorized changes should remain outside the next stage plan until the project has been re-authorized by the business layer

D.

No, because project assurance should prepare the next stage plan and update the affected product information independently of the project manager

Buy Now
Questions 14

During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.

Is this an appropriate application of the business case practice, and why?

Options:

A.

Yes, because developing the business case includes comparing credible business options to select the most appropriate investment

B.

Yes, because customer and supplier organizations must always maintain completely separate project business cases regardless of the given investment

C.

No, because a requirement in the initial scope may never be tested as part of an alternative option

D.

No, because anticipated parking income means that no alternative should be assessed

Buy Now
Questions 15

BuildyBrick’s planning specialist suggests that the project manager should prepare stage plans only for stages 2 and 4, while BuildyBrick should prepare the stage plans for stages 3 and 5 because suppliers will deliver most of the work.

Is this an appropriate application of the plans practice, and why?

Options:

A.

Yes, because the specialist supplier should own the stage plan whenever it delivers most of the stage products, and team managers can prepare the relevant information

B.

Yes, because the project manager should prepare stage plans only for stages involving more than one supplier

C.

No, because each external supplier should prepare the complete stage plan for the stage in which it works

D.

No, because the project manager remains responsible for preparing each stage plan; team managers may prepare team plans and detailed work package information

Buy Now
Questions 16

PROCESSES

During the ‘starting up a project’ process, the Head of the Portfolio Office explains to the prospective project executive that LouisShopping is strategically important to the LOB portfolio, must support increased business opportunities and is expected to open by the end of financial year three.

During which activity should this clarification of the mandate and business expectations take place?

Options:

A.

Appoint the project management team

B.

Appoint the project executive and manager

C.

Select the project approach

D.

Plan the initiation stage

Buy Now
Exam Name: PRINCE2 Project Management Practitioner (Version 7)
Last Update: Sep 27, 2026
Questions: 56

PDF + Testing Engine

$55.71   $185.69

Testing Engine

$42.85   $142.83

PDF (Q&A)

$47.13   $157.11