At Marks4sure, we are dedicated to providing IT professionals with the most accurate and reliable preparation materials for the PRINCE2 PRINCE2-7-Practitioner exam. To support your certification journey, we have made a selection of our premium 2026 PRINCE2 Certification practice questions and answers available completely free. You can take this practice test as many times as you need. Every question includes a detailed, expertly verified explanation to ensure you fully grasp the core security concepts before test day.
RISK
Here are three items of information relating to the ‘risk’ practice.
In which management product (A–E) should each item be recorded?
Choose only ONE management product for each item of information. Each management product may be used once, more than once, or not at all.
During ‘closing a project’, the project manager updates the arrangements that specify how and when the Head of the Portfolio Office will measure the increase in business opportunities after LouisShopping enters operational use.
During which closing activity should this be done?
At project closure, the project manager prepares the end project report, noting that the project exceeded its budget by 10% and planned duration by 15% because of additional heritage protection work. The findings are summarized for the project board and shared with the LOB Portfolio Director so that other projects can learn from them.
Which practice is being applied?
The target state for LouisShopping requires the car park to be monitored continuously, 24 hours a day and seven days a week, as an ongoing safety routine.
Under which heading of the change management approach should this requirement be recorded?
The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.
Is this an appropriate approach to leading a successful team, and why?
A high-level requirement that the design should be consistent with its surroundings was recorded during ‘starting up a project’. During initiation, the project manager works with Council members, residents, retailers and BuildyBrick to clarify the required design characteristics and define measurable acceptance criteria.
Which management product should be updated with this information?
During stage 2, the Heritage Director, acting as senior user, reviews the design and raises a concern that the previously requested heritage trail has not been addressed.
Is this an appropriate use of the ‘give ongoing direction’ activity, and why?
While preparing the project plan during initiation, the project manager proposes that stage 2 should end at the Council’s financial year-end. This would allow the decision on funding for stage 3 to coincide with the Council’s annual budget process.
Is this an appropriate application of the ‘manage by stages’ principle, and why?
As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.
Under which ‘directing a project’ activity is this informal consultation provided?
Before the end of stage 2, the project board authorizes a change that adds more trees and seating to the external landscaping. The change can be delivered in stage 3 without any forecast breach of project tolerance. While preparing the next stage plan, the project manager incorporates the additional products and work, updates the relevant product descriptions and product register entries, and reviews whether the project initiation documentation needs to be updated.
Is this an appropriate application of ‘prepare the next stage plan’, and why?
During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.
Is this an appropriate application of the business case practice, and why?
BuildyBrick’s planning specialist suggests that the project manager should prepare stage plans only for stages 2 and 4, while BuildyBrick should prepare the stage plans for stages 3 and 5 because suppliers will deliver most of the work.
Is this an appropriate application of the plans practice, and why?
PROCESSES
During the ‘starting up a project’ process, the Head of the Portfolio Office explains to the prospective project executive that LouisShopping is strategically important to the LOB portfolio, must support increased business opportunities and is expected to open by the end of financial year three.
During which activity should this clarification of the mandate and business expectations take place?