Spring Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PRINCE2-Agile-Foundation PRINCE2 Agile Foundation (Version 2) Exam Questions and Answers

Questions 4

Which artifact identifies risks associated with using an iterative project management approach?

Options:

A.

Project backlog

B.

Agilometer

C.

Risk management approach

D.

Definition of Done

Buy Now
Questions 5

Which statement about timeboxes is CORRECT?

Options:

A.

Flow based working partitions work into timeboxes

B.

A project cannot be referred to as a timebox

C.

A timebox can contain another timebox

D.

Timeboxes should be avoided in business as usual environments

Buy Now
Questions 6

Which is an advantage of using the PRINCE2 Agile behavior ‘collaboration’?

Options:

A.

It ensures that there are no surprises

B.

It allows people to provide cover for one another

C.

It uses experimentation to expand requirements

D.

It uses learning to help improve products

Buy Now
Questions 7

Which statement about the ‘protect the level of quality’ target is CORRECT?

Options:

A.

It is achieved by ensuring that all features are delivered

B.

It is unlikely to be achieved if incomplete user documentation is provided

C.

It allows change at the detailed level to be handled dynamically

D.

It avoids the use of extra people to improve progress during a timebox

Buy Now
Questions 8

Which is a purpose of the ‘managing product delivery’ process?

Options:

A.

To plan the delivery of the products before committing to significant expenditure

B.

To agree on what is required for accepting, executing and delivering project work.

C.

To establish and deliver the project communications to the wider organization

D.

To delegate day-to-day management of the project to the project manager

Buy Now
Questions 9

Which statement about the ‘directing a project’ process is CORRECT?

Options:

A.

The project board should attend regular project progress meetings

B.

The project board should make decisions based on the Agilometer risks

C.

A project board member should fulfill the product owner role within a delivery team

D.

The project board should increase the stage-level time tolerance

Buy Now
Questions 10

Which practice supports identification and assessment of uncertainties?

Options:

A.

Risk

B.

Plans

C.

Quality

D.

Business case

Buy Now
Questions 11

What does velocity typically measure?

Options:

A.

Work packages completed by the team

B.

The rate of progress the team is making

C.

The number of timeboxes completed

D.

The speed that a minimum viable product is created

Buy Now
Questions 12

In which workshop does planning for the next stage occur?

Options:

A.

Team planning workshop

B.

Release planning workshop

C.

Team retrospective workshop

D.

Progress review workshop

Buy Now
Questions 13

How does agile address the risk associated with the project not being fully understood at the beginning?

Options:

A.

By allowing a lot of detail at the start

B.

By avoiding too much detail at the start

C.

By requiring details at the start

D.

By preventing the analysis of details at the start

Buy Now
Questions 14

Which statement describes how the “risk” practice should be applied?

Options:

A.

Agile adoption issues should be identified by using the Agilometer

B.

Trading should be used to handle emerging changes

C.

An objectives and key results framework should be used

D.

A set of criteria in the Definition of Done should be identified

Buy Now
Questions 15

In Scrum, what answers the question ‘what can be done this sprint?’

Options:

A.

Daily scrum

B.

Sprint review

C.

Sprint planning

D.

Increment

Buy Now
Questions 16

How is the “closing a project” process used?

Options:

A.

By controlling the link between the project manager and the delivery team

B.

By ensuring that the project is viable

C.

By accepting the project product

D.

By ensuring the focus remains on delivering the stage’s products

Buy Now
Questions 17

What should the business case state about the minimum viable product (MVP)?

Options:

A.

When the MVP will be defined

B.

That the MVP must go into operational use

C.

What the MVP is

D.

That the MVP is the same as project viability

Buy Now
Questions 18

Which is a benefit of the Lean Startup approach to releasing a product?

Options:

A.

It provide a technique to reduce the testing of a product before release

B.

It enables the release plans to be synchronized with the PRINCE2 plans

C.

It reduces the number of people needed to manage a release of a product

D.

It provides quick feedback that can be responded to at the earliest opportunity

Buy Now
Questions 19

Which statement about the ‘accept that the customer doesn’t need everything’ target is correct?

Options:

A.

It gives confidence on the progress of the project

B.

It can result in the early delivery of a minimum viable product

C.

It allows misunderstandings to be dealt with appropriately

D.

It is achieved by managing the culture of the team carefully

Buy Now
Questions 20

Which TWO project board responsibilities are specifically assigned to the senior user?

1) Demonstrating the achievement of benefits.

2) Specifying the needs of those impacted by the outputs.

3) Balancing business, user and supplier demands.

4) Ensuring that the project delivers value for money.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 21

Which statement about the waterfall methodology definition is CORRECT?

Options:

A.

It prevents earlier phases of development being revisited

B.

It uses an iterative and incremental approach

C.

It focuses on responding to changing requirements

D.

It delivers products more frequently in shorter phases

Buy Now
Questions 22

Which practice has the purpose of controlling uncertainties that would affect the project’s objectives?

Options:

A.

Plans

B.

Issues

C.

Quality

D.

Risk

Buy Now
Questions 23

Which should be an objective of a retrospective?

Options:

A.

To identify many process improvements and implement them

B.

To identify key process improvements to implement in the next sprint

C.

To encourage the team to bond by allowing social activities to take place

D.

To focus on objective learning rather than subjective feelings and emotions

Buy Now
Questions 24

Which statement describes the Kanban approach?

Options:

A.

It is used to make system improvements using visualization and by controlling work in progress

B.

It is an iterative timeboxed approach that helps teams generate value

C.

It was originally focused in creating new companies and is now used to speed up product delivery

D.

It has defined processes, products and roles used to iteratively deliver outputs using timeboxing

Buy Now
Questions 25

What should be included in the project management team structure?

Options:

A.

The procurement and contract needs

B.

A full and firm foundation for the initiation of the project

C.

The arrangements for co-location of remote teams

D.

A description of how products are to be produced

Buy Now
Questions 26

How is the ‘learn from experience’ principle applied in an agile context?

Options:

A.

By ensuring control through lots of short stages during innovative projects

B.

By using the Agilometer to assess risks associated with the agile way of working

C.

By continual customer involvement to obtain feedback during the project

D.

By prioritizing quality criteria to focus the project on the delivery of value

Buy Now
Questions 27

What should be emphasized when tailoring the PRINCE2 Progress theme?

Options:

A.

Monitoring what is being delivered

B.

Tracking time and cost

C.

Planning resources

D.

Assessing the impact of risks

Buy Now
Questions 28

Which of the following is used to support the “progress” practice?

Options:

A.

Agilometer

B.

Burn charts

C.

Trading/swapping

D.

Team skills matrix

Buy Now
Questions 29

In which process should the requirements for delivery of specialist products be agreed?

Options:

A.

Initiating a project

B.

Managing product delivery

C.

Starting up a project

D.

Managing a stage boundary

Buy Now
Questions 30

Which statement about the ‘keep teams stable’ target is CORRECT?

Options:

A.

It applies primarily to the long term, such as a project or a program

B.

It is the primary reason why the tolerance for cost is set to zero

C.

It prevents compromising the overall quality level of the product

D.

It results in the early delivery of a minimum viable product

Buy Now
Questions 31

Which of the following is a challenge when merging project management and agile?

Options:

A.

No common ground in terminology

B.

No clear processes to follow

C.

Lack of guidance at delivery level

D.

Lack of guidance on doing agile

Buy Now
Questions 32

What is typically added to a user story as the understanding of the requirement evolves?

Options:

A.

An epic

B.

Acceptance criteria

C.

Definition of ‘ready’

D.

Effort actually expended

Buy Now
Questions 33

Which workshop enables participants to collaboratively define the Definition of Ready?

Options:

A.

Starting up workshop

B.

Project kickoff workshop

C.

Project initiation workshop

D.

Agile enablement workshop

Buy Now
Questions 34

Which is a collaborative technique for defining decision-making within teams?

Options:

A.

Delegation poker

B.

Team skills matrix

C.

Personas

D.

Magic estimation

Buy Now
Questions 35

Which statement explains the PRINCE2 Agile behavior of ‘exploration’?

Options:

A.

It empowers the project management team at the delivery level

B.

It uses the most effective channel to communicate information

C.

It displays the progress rate to everyone using burn-down charts

D.

It seeks out feedback collaboratively from project stakeholders

Buy Now
Questions 36

Which is a reason for releasing a product into a staging area?

Options:

A.

It enables the faster delivery of changes

B.

It supports regulatory compliance checking

C.

It enables a phased Waterfall approach

D.

It supports management by exception

Buy Now
Questions 37

What is used to address aspects of project and product development such as problem solving and release planning?

Options:

A.

Delegation matrix

B.

Project log

C.

Agilometer

D.

Agile workshops

Buy Now
Questions 38

Which is the BEST method of communication to gather feedback?

Options:

A.

Receiving emailed diagrams to encourage discussion

B.

Conducting online surveys to obtain a range of opinions

C.

Meeting face-to-face to encourage an exchange of views

D.

Discussing over the telephone to gather feedback quickly from stakeholders

Buy Now
Questions 39

Which statement about the ‘be on time and hit deadlines’ target is CORRECT?

Options:

A.

It allows change to be handled dynamically

B.

It is achieved by keeping the delivery teams stable

C.

It helps with planning dependencies within a project

D.

It ensures that the level of quality is protected

Buy Now
Questions 40

Which statement about the ‘embrace change’ target is CORRECT?

Options:

A.

It re-establishes team dynamics when a new member joins the team

B.

It trades user stories for those of a similar size

C.

It results in the late delivery of the minimum viable product

D.

It degrades the performance of the features that are delivered

Buy Now
Questions 41

Which describes the Scrum Master role in Scrum?

Options:

A.

It is authorized to run the project on a day-to-day basis on behalf of the project board

B.

It is responsible for ensuring that product backlog items are clearly expressed on the product backlog

C.

It is empowered to organize and manage its own work to create a valuable, useful increment every sprint

D.

It is servant-leadership to help everyone change their interactions to maximize the value created by the team

Buy Now
Questions 42

Who needs to be aware that flexing what is delivered may affect the expected benefits of the project?

Options:

A.

Customer subject matter expert and the supplier representative

B.

The team manager and the senior supplier

C.

The project manager and the project board

D.

The team quality assurance and project support

Buy Now
Questions 43

For which process is the agreement on the requirements for delivery of specialist products necessary?

Options:

A.

Initiating a project

B.

Starting up a project

C.

Controlling a stage

D.

Managing product delivery

Buy Now
Questions 44

Which is a purpose of the quality theme?

Options:

A.

To define the specific conditions that enable a product to be usable

B.

To determine how the means of delivering products is communicated

C.

To evaluate whether the project continues to be achievable

D.

To assess any potential improvements to a product

Buy Now
Questions 45

What is the purpose of the ‘agile enablement’ workshop?

Options:

A.

To identify, assess, and plan for risks associated with transitioning products into operations

B.

To identify, assess, and plan for risks associated with agile adoption

C.

To identify, assess, and plan for risks associated with project delivery

D.

To identify, assess, and plan for risks associated with business as usual

Buy Now
Questions 46

What is an epic?

Options:

A.

A low-level requirement

B.

A fine-grained user story

C.

A detailed feature

D.

A high-level requirement

Buy Now
Questions 47

Which artifact is used to describe the project ' s major products in the form of epic user stories?

Options:

A.

Project dashboard

B.

Release map

C.

Product backlog

D.

Project backlog

Buy Now
Questions 48

Which BEST describes the senior user role when tailoring the organization theme?

Options:

A.

An ‘agile sponsor’

B.

An ‘executive sponsor’

C.

A ‘coach’

D.

A ‘super product owner’

Buy Now
Exam Name: PRINCE2 Agile Foundation (Version 2) Exam
Last Update: Apr 30, 2026
Questions: 162

PDF + Testing Engine

$63.52  $181.49

Testing Engine

$50.57  $144.49
buy now PRINCE2-Agile-Foundation testing engine

PDF (Q&A)

$43.57  $124.49
buy now PRINCE2-Agile-Foundation pdf