Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Project-Management ARE 5.0 Project Management (PjM) Exam Questions and Answers

Questions 4

Project-Management Question 4

Refer to the exhibit.

The following changes occur during the project:

    The owner delayed the project kickoff until September Year 1 due to delays in finalizing the Owner-Architect Agreement.

    The architect did not have enough staff available to start the project on time, so the firm hired temporary staff for 2 months.

    The owner made a design change in January Year 2 that added 2 weeks to the schedule.

    Not enough bids were received, and the project was bid a second time with additional advertising.

    The owner made design changes in May and July of Year 2 that each added 3 weeks to the schedule.

When were the construction documents completed based on the project changes?

Options:

A.

September Year 2

B.

November Year 2

C.

June Year 3

D.

August Year 3

Buy Now
Questions 5

Which of the following best describes the architect’s role in cost estimating during schematic design?

Options:

A.

Developing a detailed quantity takeoff and vendor pricing

B.

Providing a preliminary opinion of probable construction cost

C.

Verifying contractor bids and change order pricing

D.

Approving final project budget with the owner

Buy Now
Questions 6

Project-Management Question 6

In the chart shown, what is typically a part of the "Bidding Documents"?

Options:

A.

A

B.

B

C.

C

Buy Now
Questions 7

What does “substantial completion” mean in the context of a construction contract?

Options:

A.

The project is 50% complete

B.

The work is sufficiently complete for occupancy or use

C.

All punch list items have been finished

D.

The contractor has been paid in full

Buy Now
Questions 8

A new restaurant design must incorporate specific light fixtures to meet the franchise requirements. The owner conveys this to the architect, who must make sure that prospective bidders do not overlook specific fixtures.

Which method should the architect use during the construction documents phase?

Options:

A.

Identify the fixtures in the performance specification

B.

Issue an addenda that highlights the franchise branding requirements

C.

Note and clearly identify the specific light fixture in the drawings

Buy Now
Questions 9

Construction of a gymnasium is scheduled to be complete 365 days from the date of the notice to proceed. On Friday, day 355 of the schedule, the contractor submits a punch list to the architect for substantial completion. The architect agrees to review the punch list on-site after the weekend.

On Monday, the architect discovers that a subcontractor left open a skylight over the weekend, allowing heavy rain to fall into the courtyard area and damage the gymnasium floor. It was determined the flooring must be replaced. The lead time for new flooring is 8–10 weeks, and installation will take 14 days. The architect's agreement with the owner is contracted to end 30 days after substantial completion.

Which of the following documents must the architect prepare immediately? Check the two that apply.

Options:

A.

A revised schedule for owner approval

B.

A request for liquidated damages for contractor review

C.

An invoice for additional services for owner payment

D.

A punch list for areas not damaged for contractor approval

E.

A notice to the contractor for withholding final payment

F.

A change order to purchase new flooring

Buy Now
Questions 10

An architectural firm is developing construction documents (CDs) for a multi-story manufacturing facility. The project requirements include high-volume ventilation and filtration air distribution systems and heavy floor load design to accommodate the manufacturing equipment and processes. The project manager (PM) is planning for coordination and constructability review of the project documents at 80% CDs.

What actions should the PM take to ensure an effective quality control review? Check the three that apply.

Options:

A.

send the structural drawings to a construction management firm for review

B.

arrange for a peer review of the mechanical design and distribution drawings

C.

request that the mechanical engineer flag potential conflicts on the structural drawings

D.

request that the owner provide a constructability review of the documents

E.

submit the document package to the local code official for a preliminary review

F.

exchange consultant documents among the disciplines for coordination comments

Buy Now
Questions 11

Subsequent to the preparation of construction documents, prior to permitting, the enactment of codes or laws requires changes to the project.

Which of the following should occur?

Options:

A.

The architect should be compensated for the changes as an additional service.

B.

The architect should seek compensation from the governing body.

C.

The architect should seek no compensation.

D.

The owner should seek compensation from the governing body.

Buy Now
Questions 12

While conducting a site visit for a residential tower delivered through the design-build method, an architect observes several construction workers without hard hats and other unsafe working conditions.

How should the architect proceed?

Options:

A.

Immediately instruct construction workers on which safety precautions need to be taken.

B.

Document the unsafe working conditions and send a memo to the contractor copying the owner.

C.

Document the unsafe working conditions and send a memo to the owner copying the contractor.

D.

Request that the contractor review safety precautions that need to be taken with construction workers.

Buy Now
Questions 13

In response to a request for qualifications for a prospective project, the architect assembles a project team of mechanical, electrical, plumbing, and fire protection engineers.

What is the project?

Options:

A.

a new school for grades K-12

B.

a research university campus master plan

C.

the renovation of a commercial office building

D.

seismic upgrades of a 1950s era hospital

Buy Now
Questions 14

Which insurance policy protects the architect against claims of negligence?

Options:

A.

Builder’s Risk Insurance

B.

Professional Liability Insurance

C.

General Liability Insurance

D.

Workers’ Compensation Insurance

Buy Now
Questions 15

A contractor has hired a subcontractor to construct a parking lot for 60 cars. The parking lot will be 60 feet x 270 feet. The subcontractor has quoted a price of $13.25 per square yard to the contractor.

If the contractor adds a mark-up of 15%, what is the cost of each parking space?

Options:

A.

$398

B.

$457

C.

$3,578

D.

$4,115

Buy Now
Questions 16

During the CD phase, it is discovered that the owner's food service consultant made a mistake that results in the owner asking the architect to revise the design.

How should the architect proceed?

Options:

A.

Issue a change order

B.

Submit an additional services request

C.

Proceed to bidding and make changes in construction

Buy Now
Questions 17

Which document defines the architect’s scope of services and responsibilities?

Options:

A.

Owner-Architect Agreement (B101)

B.

General Conditions (A201)

C.

Contractor’s Bid Proposal

D.

Construction Documents

Buy Now
Questions 18

What is the architect’s role regarding shop drawings?

Options:

A.

Preparing and submitting them to the owner

B.

Reviewing them for compliance with design intent

C.

Issuing shop drawings to subcontractors

D.

Approving changes without owner input

Buy Now
Questions 19

An architecture firm has a C401 agreement with their consultants for a new design-bid-build residential tower. The architect has approved a schedule provided by the mechanical engineer that includes a two-week quality control review after each delivery milestone.

During the design development phase, the owner requests that the architect change the 8,000-square-foot business center amenity for tenants to a private restaurant. The mechanical engineer informs the architect that their schedule must be extended by four weeks to meet the owner's request.

What should the architecture firm do first to maintain the start of construction?

Options:

A.

Request that compensation be adjusted by the owner to reflect the change in scope.

B.

Approve the design loads of the new mechanical system following the next quality control review.

C.

Receive the owner's approval of the schedule change in writing from the consultant.

D.

Change the C401 agreement to reflect the additional four-week extension.

Buy Now
Questions 20

Preparation of space standards, furniture assessment, and documentation of equipment requirements are most effectively done during which of the following project phases?

Options:

A.

Programming

B.

Schematic Design

C.

Design Development

Buy Now
Questions 21

What is the architect’s role in project closeout?

Options:

A.

Conduct final inspections and issue certificates of substantial completion

B.

Approve contractor payroll records

C.

Manage post-occupancy maintenance

D.

Conduct all warranty repairs

Buy Now
Questions 22

The owner and architect sign a Basic Services Agreement for the design of a museum.

Based on AIA Document B101-2017, Owner and Architect Agreement, which line items should be excluded from the architect's cost estimate? Check the two that apply.

Options:

A.

Doors and windows

B.

Roofing material

C.

Landscape plants

D.

HVAC equipment

E.

Furniture, furnishings, and equipment design

F.

Plumbing fixtures

Buy Now
Questions 23

The architect's estimate of the cost of the work at the end of the construction documents phase exceeds the owner's stated budget for the cost of the work.

According to AIA Document B101, what should the architect recommend to the owner?

Options:

A.

Change the quality of materials, with additional compensation

B.

Make reductions in the project program, with additional compensation

C.

Revise project scope, without additional compensation

D.

Alter the project delivery method, without additional compensation

Buy Now
Exam Code: Project-Management
Exam Name: ARE 5.0 Project Management (PjM) Exam
Last Update: Aug 15, 2025
Questions: 79

PDF + Testing Engine

$63.52  $181.49

Testing Engine

$50.57  $144.49
buy now Project-Management testing engine

PDF (Q&A)

$43.57  $124.49
buy now Project-Management pdf