Refer to the exhibit.
The following changes occur during the project:
The owner delayed the project kickoff until September Year 1 due to delays in finalizing the Owner-Architect Agreement.
The architect did not have enough staff available to start the project on time, so the firm hired temporary staff for 2 months.
The owner made a design change in January Year 2 that added 2 weeks to the schedule.
Not enough bids were received, and the project was bid a second time with additional advertising.
The owner made design changes in May and July of Year 2 that each added 3 weeks to the schedule.
When were the construction documents completed based on the project changes?
Which of the following best describes the architect’s role in cost estimating during schematic design?
What does “substantial completion” mean in the context of a construction contract?
A new restaurant design must incorporate specific light fixtures to meet the franchise requirements. The owner conveys this to the architect, who must make sure that prospective bidders do not overlook specific fixtures.
Which method should the architect use during the construction documents phase?
Construction of a gymnasium is scheduled to be complete 365 days from the date of the notice to proceed. On Friday, day 355 of the schedule, the contractor submits a punch list to the architect for substantial completion. The architect agrees to review the punch list on-site after the weekend.
On Monday, the architect discovers that a subcontractor left open a skylight over the weekend, allowing heavy rain to fall into the courtyard area and damage the gymnasium floor. It was determined the flooring must be replaced. The lead time for new flooring is 8–10 weeks, and installation will take 14 days. The architect's agreement with the owner is contracted to end 30 days after substantial completion.
Which of the following documents must the architect prepare immediately? Check the two that apply.
An architectural firm is developing construction documents (CDs) for a multi-story manufacturing facility. The project requirements include high-volume ventilation and filtration air distribution systems and heavy floor load design to accommodate the manufacturing equipment and processes. The project manager (PM) is planning for coordination and constructability review of the project documents at 80% CDs.
What actions should the PM take to ensure an effective quality control review? Check the three that apply.
Subsequent to the preparation of construction documents, prior to permitting, the enactment of codes or laws requires changes to the project.
Which of the following should occur?
While conducting a site visit for a residential tower delivered through the design-build method, an architect observes several construction workers without hard hats and other unsafe working conditions.
How should the architect proceed?
In response to a request for qualifications for a prospective project, the architect assembles a project team of mechanical, electrical, plumbing, and fire protection engineers.
What is the project?
A contractor has hired a subcontractor to construct a parking lot for 60 cars. The parking lot will be 60 feet x 270 feet. The subcontractor has quoted a price of $13.25 per square yard to the contractor.
If the contractor adds a mark-up of 15%, what is the cost of each parking space?
During the CD phase, it is discovered that the owner's food service consultant made a mistake that results in the owner asking the architect to revise the design.
How should the architect proceed?
An architecture firm has a C401 agreement with their consultants for a new design-bid-build residential tower. The architect has approved a schedule provided by the mechanical engineer that includes a two-week quality control review after each delivery milestone.
During the design development phase, the owner requests that the architect change the 8,000-square-foot business center amenity for tenants to a private restaurant. The mechanical engineer informs the architect that their schedule must be extended by four weeks to meet the owner's request.
What should the architecture firm do first to maintain the start of construction?
Preparation of space standards, furniture assessment, and documentation of equipment requirements are most effectively done during which of the following project phases?
The owner and architect sign a Basic Services Agreement for the design of a museum.
Based on AIA Document B101-2017, Owner and Architect Agreement, which line items should be excluded from the architect's cost estimate? Check the two that apply.
The architect's estimate of the cost of the work at the end of the construction documents phase exceeds the owner's stated budget for the cost of the work.
According to AIA Document B101, what should the architect recommend to the owner?