Winter Special Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 713PS592

PSP Planning & Scheduling Professional (PSP) Exam Questions and Answers

Questions 4

Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:

PSP Question 4

Options:

A.

Predecessor is activity 5001, successor is activity 8001

B.

Predecessor is activity 4001, successor is activity 8001

C.

Predecessor is activity 9001, successor is activity 9002

D.

Predecessor is activity 5001, successor is activity 8002

Buy Now
Questions 5

Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

PSP Question 5

Options:

A.

450 lifts

B.

300 lifts

C.

45 lifts

D.

150 lifts

Buy Now
Questions 6

Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?

Options:

A.

19 Sep 2021

B.

08 Sep 2021

C.

09 Sep 2021

D.

27 Aug 2021

Buy Now
Questions 7

What is the cycle time?

PSP Question 7

Options:

A.

5 minutes

B.

17 minutes

C.

14 minutes

D.

6 minutes

Buy Now
Questions 8

An early start constraint dictates

Options:

A.

An activity's remaining duration.

B.

The planned start of a successor activity

C.

The planned start of an activity.

D.

The actual start of an activity.

Buy Now
Questions 9

What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

Options:

A.

Use the progressed portion of the critical path of all the updates previous to the current update.

B.

Use the progressed portion of the critical path of the baseline schedule.

C.

Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.

D.

Use the forward-looking critical path of the most current updates.

Buy Now
Questions 10

Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

Options:

A.

Use gross building square footages. The pluses and minuses all average out.

B.

Look at each activity independently and don't follow specific logic paths when assigning activity durations.

C.

Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.

D.

Use the people responsible for performing the work as a resource to assign activity durations.

Buy Now
Questions 11

How many entities/subcontractors should a scheduled activity cover?

Options:

A.

More than one it the activity is in a single calendar period

B.

More than one it the subcontractors agree

C.

Only one

D.

More than one if the concurrent work cannot be split between subcontractors

Buy Now
Questions 12

Project schedules help control all of the following EXCEPT for_____________________.

Options:

A.

Quality

B.

Cost

C.

Resources

D.

Time

Buy Now
Questions 13

Schedules are periodically updated to reflect progress. What step should NOT occur before the update is considered complete?

Options:

A.

All managers should be encouraged to review contiguous activity status

B.

The process of each activity should be indicated by the responsible manager

C.

The critical path should not be revisited to ensure all the downstream logic and durations are still accurate

D.

The project team should be asked to review status for accuracy

Buy Now
Questions 14

The best source of project risk or opportunities is:

Options:

A.

A similar project in another state

B.

Rumors from the local Chamber of Commerce

C.

Failures by other contractors

D.

Internal and external stakeholders

Buy Now
Questions 15

Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?

Options:

A.

Subcontract outside forces to accelerate the Phase A Schedule

B.

Allocating forces from other BILCO contracts to the toll road project

C.

Proceeding with the work in advance of the environmental studies

D.

Reduce the phasing from 5 phases to 3 phases

Buy Now
Questions 16

What changes to logic would eliminate Activity B from the critical path?

Options:

A.

Replace the relationship from Activity B to Activity C with SSO

B.

Reduce the lag value of the relationship from Activity A to Activity B from 5 to 0

C.

Add a SS 15 relationship from Activity A to Activity B and replace the relationship from Activity A to Activity B with FFO

D.

Replace the relationship from Activity A to Activity B with FFO and add an FSO relationship from Activity A to Activity C

Buy Now
Questions 17

What activities are concurrent to Activity 2001 in the "normal" schedule?

PSP Question 17

Options:

A.

7001.

B.

1001.

C.

1000.

D.

2003.

Buy Now
Questions 18

Determine the correct formula and date for the late start for the Activity 11001:

PSP Question 18

Options:

A.

LF of 11001 less 27 days plus 1 day equaling 14 Jan 2024

B.

LF of 1000 less 25 days equaling 16 Jan 2024

C.

LF of 11001 less duration of 11001 equaling 16 Jan 2024

D.

LF of 11001 less 25 days plus 1 day equaling 16 Jan 2024

Buy Now
Questions 19

What project cost elements would NOT normally be reflected in the Activity 1000?

Options:

A.

Home office expenses

B.

CPM processing and updating

C.

Materials used in the construction

D.

Job site quality control

Buy Now
Questions 20

Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

Options:

A.

The project plans and specifications

B.

The project geotechnical report

C.

The regulations published by the government aviation agency

D.

The government's report on future high-clearance bridge projects

Buy Now
Questions 21

In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?

Options:

A.

Budgeted cost of work scheduled

B.

Budgeted cost of work performed

C.

Schedule performance index

D.

Actual cost of work scheduled

Buy Now
Questions 22

Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

PSP Question 22

Options:

A.

After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.

B.

After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

C.

After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

Buy Now
Questions 23

If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?

Options:

A.

Reduce the duration of 'A' from 20 days to 10 days and replace the relationship from B' to 'C with FSO.

B.

Replace the relationship from 'B’ to 'C’ with SSO

C.

Reduce the duration of B" from 10 days to 5 days by compressing work effort

Buy Now
Questions 24

The data date or status date of a schedule represents the:

Options:

A.

date the monthly update is performed

B.

date the project manager turns in the schedule update

C.

system date when the software calculates the update

D.

date on which progress is based

Buy Now
Questions 25

Determine the correct formula and date for the late start for Activity 9001.

PSP Question 25

Options:

A.

The early finish is required in order to determine the answer.

B.

LS.6001 Dur.6001 -> 11-20-02.

C.

There is insufficient data provided to calculate the answer.

D.

LF.9001 Dur.9001 -> 11-20-02.

Buy Now
Questions 26

Determine the correct formula and date for the late finish for Activity 2002.

Options:

A.

LS of 2003 less 1 day equaling to 06 Oct 2021

B.

LS of 2003 less 1 day equaling to 06 Nov 2021

C.

LS of 2003 plus 1 day equaling to 07 Oct 2021

D.

LS of 2003 less 1 day equaling to 05 Oct 2021

Buy Now
Questions 27

Which of the following is NOT a tool or technique used to perform scope planning?

Options:

A.

Benefit cost analysis.

B.

Schedule performance indexing.

C.

Expert Judgment.

D.

Alternatives identification.

Buy Now
Questions 28

You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor has included codes for each activity that identify {1) the category of work and (2) the trade/subcontract performing the work. What can this code information be used for?

Options:

A.

Group schedule activities together based on their start dates

B.

Display detailed information regarding the sequencing of activities in the schedule

C.

Organize reports to group related work activities

D.

Display resources me contractor plans to use on each activity

Buy Now
Questions 29

Which is NOT an industry-recognized methodology for quantifying critical delay?

Options:

A.

Gantt Chart.

B.

Periodic Windows.

C.

Collapsed As-Built.

D.

Time Impact.

Buy Now
Questions 30

In a "crashed" schedule, which is a chain of activities that precede activity 2004?

PSP Question 30

Options:

A.

1001, 2001, 2002, 2003

B.

2001, 2002, 2003, 2007

C.

1001, 2002, 2003

D.

1001, 2002, 2002, 2003, 3001

Buy Now
Questions 31

The expected remaining cost needed to complete an activity, group of activities or the project is the____________.

Options:

A.

Budget at completion (BAC)

B.

Budgeted cost of work performed (BCWP)

C.

Estimate to complete (ETC)

D.

Estimate at completion (EAC)

Buy Now
Questions 32

How many work days does it take to move the product from testing to sale?

PSP Question 32

Options:

A.

60.

B.

70.

C.

100.

D.

90.

Buy Now
Questions 33

Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

PSP Question 33

Options:

A.

These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.

B.

These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.

C.

The activities occur in series with a 15-day lag.

D.

The activities run concurrently.

Buy Now
Questions 34

In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

Options:

A.

The delay must affect the critical path.

B.

The delay must be concurrent with the delay attributable to both parties.

C.

The delay must not cause monetary harm to the defendant.

D.

The delay must affect the contractor's planned construction schedule.

Buy Now
Questions 35

Background

Your name is Evan Marshal. You are the corporate scheduler for Happy Insurance Corporation (HIC), a general health insurance company located in Ridgemond, Illinois. HIC is very busy with 49 unique software development projects. The organization structure at HIC gives the project scheduling responsibility to the Project Manager assigned to each project. You are charged with coordination of the project schedules into a Master Schedule and quality control for scheduling on the individual development projects. You report directly to the Director of Information Services (DIS), Desmond Rayburn.

It has come to your attention Project JP-114 has fallen behind schedule and Rita Belateau, the Project Manager, wants to accelerate the project in order to reclaim lost time. Rita is a strong supporter of Total Quality Management and strives for zero failures; therefore she is assessing the need for overtime for resources assigned to an activity that is not projecting a completion prior to the early finish depicted in the current schedule.

You and Rita review the current schedule to identify which activities are on the critical path and which activities have plenty of float. The review reveals several activities have suffered less than planned productivity and have contributed to falling behind. In the process of this review, you and Rita also review the budget for Project JP-114 and notice not only the schedule has fallen behind but the cost to date is more than she had expected. To total budget is $150,000, planned to date is $30,000; expended to date is $37,000.

With nine months remaining until baseline contract completion, Rita needs to bring Project JP-114 back on track; knowing overtime for an extended period of time is not always the right answer, especially with the cost to date already over planned.

In order to truly understand the options available to help remedy the current situation, you and Rita brainstorm on several potential courses of action. All the potential courses of action will require an evaluation of budget impact versus schedule correction.

1. Pull the project team together and ensure everyone understands which activities are on the critical path. Rita would like to use the existing project team and focus them on these critical path activities, laying out a plan for periodic overtime when needed to crunch through a deliverable. This approach could add approximately 20% to the budget.

2. Outsource various modules of activities to qualified and known consultants. This could drive up the costs and must be evaluated before implemented. Having an outside source working in parallel with the project team could also accelerate the schedule to mitigate some of the delays, as well as keep overtime down to a minimum for the project team. Potentially this could add as much as 40% to the budget, but could also be very productive schedule wise.

3. Mandatory overtime for the project team - entire project goes on a 50-hour work week. If the entire project team works overtime for an extended period of time, the budget could see an additional 60% increase.

4. The project continues as is completes the project late and accepts the penalties imposed. Penalties imposed for late delivery could add as much as 50% to the budget.

Assignment

Draft a proper memorandum to Desmond Raybum, IS Director, explaining in your own words:

a. the current problem and potential impact(s);

b. each course of action, stating advantages and disadvantages as appropriate;

c. your recommendations, properly supported.

Please be sure to include the rationale for your recommendations. Be sure to summarize your thoughts and address (To, From, Date, and Subject/Project Name) and close the memo appropriately. If you are uncomfortable with the courses of action noted, provide your own with appropriate substantiation for your position. Limit your answer to one, full typewritten page (roughly three handwritten pages).

While your email can be a detailed as you like, be sure to write sufficiently to address each element of the assignment, yet not so long that you go beyond the scope of the exercise.

Take time to read the problem and consider what you want Evan to say. Good luck!

Options:

Buy Now
Questions 36

Using the normal schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

Options:

A.

407 days

B.

255 days

C.

267 days

D.

477 days

Buy Now
Questions 37

Prior to the beginning work on Activity 6001, the scope is changed by executed change order to increase the activity duration by thirty days and rock fill by 100.000 cubic meters If the project has progressed as scheduled up to the point of the executed change order, what activities would be changed on the next project update?

Options:

A.

1001 and 6001

B.

1000. 1001. and 6001

C.

9001 and 6002 and 6002

D.

1000 and 6001

Buy Now
Questions 38

What does the narrow band at "Y" represent?

PSP Question 38

Options:

A.

Resource limitation period.

B.

A rework period.

C.

Activity inactivity.

D.

You cannot tell with the information supplied.

Buy Now
Questions 39

If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?

Options:

A.

The Eichleay formula

B.

Historical production rates

C.

Time impact analysis

D.

Black-Scholes model

Buy Now
Questions 40

When project risk is reflected in scheduled activities, what is the most significant characteristic of those activities?

Options:

A.

The level of resources available to the activity

B.

The Remaining Duration of the activity

C.

The criticality of toe activities

D.

The Late Start of the last activity in that float path

Buy Now
Questions 41

: 20

Constraints control events or activities that __________________.

Options:

A.

Affect only the forward pass.

B.

Are not based on project relationships.

C.

Affect only the backward pass.

D.

May be over-ridden by activity logic.

Buy Now
Questions 42

The schedule or budget at completion less the estimate at completion is___________.

Options:

A.

the schedule variance

B.

the variance at completion

C.

the cost variance

D.

the profit or loss for the project

Buy Now
Questions 43

Control Level Schedule activities are NOT one of the following:

Options:

A.

always analogous with Control Accounts

B.

always used to establish the scope and track the status of automation control systems

C.

may be composed form multiple WBS deliverable packages

D.

always reporting the status of phase deliverables

Buy Now
Questions 44

The Work Breakdown Structure (WBS) is established to reflect the:

Options:

A.

lowest level of the project estimate

B.

lowest level reporting back to the program WBS

C.

lowest level of effort scope

D.

lowest level where the work is managed

Buy Now
Questions 45

Determine the correct formula and date for the late finish for Activity 6002.

Options:

A.

LS of 6003 plus 1 day equaling 09 Mar 2023

B.

LS of 6003 less 1 day equaling 09 Mar 2022

C.

LS of 6003 less 1 day equaling 09 Mar 2023

D.

LS of 6003 plus 1 day equaling 09 Mar 2022

Buy Now
Questions 46

Which of the following is NOT input data to the construction planning process?

Options:

A.

Input from the owner

B.

The contract

C.

Bonding capacity of subcontractors

D.

Input from the contractor

Buy Now
Questions 47

Constructability is NOT intended to:

Options:

A.

optimize engineering and procurement

B.

correct deficiencies in the project design

C.

balance project and environment goals

D.

integrate construction knowledge into the design

Buy Now
Questions 48

If all other work proceeds according to the Baseline plan, how many times will the critical path change?

PSP Question 48

Options:

A.

2.

B.

1.

C.

Does not change.

D.

3.

Buy Now
Questions 49

What owner action could have mitigated the late completion of the project?

Options:

A.

Hire a more senior project manager.

B.

Self-perform more of the work.

C.

Use a procurement agent to monitor and expedite equipment deliveries.

D.

Prepare better structural steel drawings.

Buy Now
Questions 50

In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:

Options:

A.

ahead of schedule

B.

on schedule

C.

complete

D.

behind schedule

Buy Now
Questions 51

Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?

Options:

A.

Avoiding a late delivery penalty from the owner

B.

Maximizing the $500,000 bonus

C.

Avoiding the 2023-2024 winter/wet weather season

D.

Minimizing the indirect expenditure chargeable to the contractor

Buy Now
Questions 52

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor subsequently submits a CPM schedule for its baseline schedule submittal. As part of your review, you look at the durations for each activity in the schedule. How do you determine if a duration of 10 work days for drywall installation is accurate?

Options:

A.

The duration for drywall installation should De proportional to how critical the activity is

B.

Review the drywall quantity, methods and location with the project superintendent to determine a reasonable duration

C.

Review the location of drywall work in the contract drawings

D.

Divide the quantity of drywall by the construction crew's dairy production rate for this work

Buy Now
Questions 53

Which of the following statements is true?

Options:

A.

In the absence of contrary contractual language network float, as opposed to project float, there is a shared commodity between the owner and contractor

B.

In the absence of a contrary contractual language total float, as opposed to free float, there is a commodity belonging to the contractor

C.

In the absence of contrary contractual language total float, as opposed to tree float, there is a commodity belonging to the owner

D.

In the absence of contrary contractual language free float, as opposed to project float, there is not a shared commodity between the owner and the contractor

Buy Now
Questions 54

The linear scheduling velocity diagram has the following two-axis:

Options:

A.

Location and crew size

B.

Time and location

C.

Time and rate of progress

D.

Time and crew size

Buy Now
Questions 55

Using one crane capable of 30 lifts per day. for 3 column pours requiring 28 lifts each, plus assorted work in the area requiring an additional 150 lifts, what are the lowest planned workdays for this work?

Options:

A.

3 workdays

B.

18 workdays

C.

8 workdays

D.

7 workdays

Buy Now
Questions 56

Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?

Options:

A.

to highlight a time when there are more holidays and work therefore will be slower and there will be more absenteeism

B.

to denote a time during which work may not progress as fast as planned and cost and risk may be elevated

C.

to provide a key to co-a weather for safety meetings

D.

to show a difference in the calendar year

Buy Now
Questions 57

What is the workweek period for this project?

PSP Question 57

Options:

A.

Monday through Friday

B.

Sunday through Friday

C.

Monday through Saturday

D.

Sunday through Saturday

Buy Now
Questions 58

What is a key first step in developing a critical path method schedule?

Options:

A.

Drawing a bar chart of the key phrases of the work.

B.

Defining the execution plan to meet the required scope of work.

C.

Setting out the resource to be used and its limitations.

D.

Drawing the logic diagram.

Buy Now
Questions 59

Which of the following parties is NOT a stakeholder of the Spring Highway project?

Options:

A.

ALPHA

B.

GOUGE

C.

BILCO

D.

DEVCO

Buy Now
Questions 60

Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

PSP Question 60

Options:

A.

09-28-01.

B.

09-08-01.

C.

09-15-01.

D.

09-18-01.

Buy Now
Questions 61

Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?

PSP Question 61

Options:

A.

36 lifts

B.

24 lifts

C.

30 lifts

D.

48 lifts

Buy Now
Questions 62

Value engineering is:

Options:

A.

targeted at the design itself

B.

intended to provide the least life-cycle cost

C.

established to provide the greatest value

D.

intended to determine if the project will be completed economically

Buy Now
Questions 63

Using the normal schedule, what is the early finish date and total float of Activity 10002?

Options:

A.

24 Nov 2023. and 24 days of tree float

B.

24 Dec 2023. and 24 days of tree float

C.

17 Dec 2023. and 4 days of total float

D.

21 Dec 2023. and 4 days of total float

Buy Now
Questions 64

What are Phases based on and derived from?

Options:

A.

Resources

B.

Constructability

C.

Score of Work

D.

Budget

Buy Now
Exam Code: PSP
Exam Name: Planning & Scheduling Professional (PSP) Exam
Last Update: Nov 10, 2025
Questions: 216

PDF + Testing Engine

$72.6  $181.49

Testing Engine

$57.8  $144.49
buy now PSP testing engine

PDF (Q&A)

$49.8  $124.49
buy now PSP pdf