TMMi-P_Syll2020 TMMi - Test Maturity Model Integration Professional Questions and Answers
Improvement models can have a staged and/or continuous representation. The TMMi has been developed as a staged model.
Which of the following statements regarding a staged improvement model is TRUE?
In a TMMi assessment, one of the shortcomings stated was the lack of coherency across various test levels and test types being performed. Establishing a master test plan was an improvement action recommended by the assessors. Which TMMi process area addresses a specific goal and specific practices for establishing a master test plan?
Which of the following is an Agile practice that can be applied as a way to establish a test strategy (SG2) within the Test Policy and Strategy process area?
Consider the following characteristics of an assessment:
* the assessment is performed by an accredited TMMi assessor.
* only interviews are used as evidence.
To which type of assessment do these characteristics relate?
To which TMMi level do the process areas Test Organization and Test Training Program belong?
Which of the following are specific goals of maturity level 4 process area Advanced Reviews?
1. Coordinate the peer review approach with the dynamic test approach
2. Perform peer reviews
3. Adjust the test approach based on review results early in the life cycle
4. Establish test performance indicators
5. Testing is performed using statistical methods
Which of the following statements is TRUE regarding relevance of the CMMI model version 2 for testing?
To which TMMi level 4 process area does the specific practice "Define a co approach is defined that co-ordinates both static and dynamic testing?
Which of the following statements best describes the difference between a Specific Goal and a Generic Goal in the TMMi model?
TMMi has various types of components. Match the component types with the appropriate description.
Component types:
A test process assessment against TMMi levels 2 and 3 has been performed on an international outsourcing software organization. Although many practices, as required by the TMMi model, are already in place, projects suffer from poor test estimations.
Which of the following process areas would need specific attention to address the above mentioned shortcoming?
The Learning phase completes the improvement cycle. One of the goals of the IDEAL model is to continuously improve the ability to implement change. Which of the following activities is part of the Learning phase?
Which of the following activities are part of the Acting phase of a test improvement cycle?
1) Set Priorities
2) Create Solutions
3) Plan Actions
4) Pilot Solutions
Your organization performs code reviews and architectural reviews on a regular basis, in order to measure product quality early in the lifecycle.
This is an example of implementation of a specific practice from which TMMi level 4 process area?
A test process assessment has been performed at an embedded software organization. All process areas at TMMi Levels 2 and 3 were in scope of the assessment. Many practices required by the TMMi model are already in place, but the organization is missing a master test plan spanning multiple test levels.
Which of the following process areas would most likely need specific attention to address the above-mentioned shortcoming?
Which of the following are NOT specific goals of the TMMi level 5 process area Test Process Optimization?
1. Select test process improvements
2. Determine, plan and implement test process improvements
3. Evaluate New Testing Technologies to Determine their Impact on the Testing Process
4. Deploy test process improvements
5. Monitor product quality against plan and expectations
Consider the following five statements about TMMi level 2 process areas in an Agile context. Which of these statements are true, and which ones are false?
a. Test performance indicators in an Agile context at TMMi level 2 are always more related to team performance (for example, Velocity) than to the end-results of iterations (such as escaped defects).
b. The product risk assessment process for Agile projects will normally take a more lightweight approach than with a sequential lifecycle model.
c. The process area Test Monitoring and Control in an Agile context is not as important as in a traditional methodology, since sticking to a rigid plan is not one of the tenets of the Agile manifesto nor one of the principles of Agile.
d. For TMMi in an Agile project, it is not necessary to have traceability between requirements, test conditions and tests, because test conditions are not part of an Agile methodology.
e. Following the principles of Agile development, the specification of test environments is normally performed closer to test execution than in a sequential methodology, to provide the opportunity for late changes to be implemented.
Which of the following activities is one that will typically be performed as part of the Diagnosing phase of the IDEAL test improvement cycle?
A test process assessment has been performed on a company developing systems for the medical industry. Their systems are classified as safety critical. One of the shortcomings identified during the assessment is related to reliability testing. Although reliability was identified by the business as a critical issue, no formal approach and test techniques are being used for reliability testing.
Which of the following process areas would need specific attention to address the above mentioned shortcoming?
Which of the following is a typical business reason for starting a test improvement program?
During a TMMi assessment the percentage of process achievement for the Test Planning process area has been determined at 40%.
Which of the following compliance ratings would you assign to Test Planning?
The evolutionary testing model of Gelperin and Hetzel has served as a foundation for historical level differentiation in the TMMi. The evolutionary testing model describes a number of test phases.
Which of the following phases of the evolutionary testing model is associated with Maturity Level 1 “Initial” of the TMMi?
Which of the following statements is NOT a typical business reason for test improvement?
Consider the following specific goal “Project Goals for Product Quality and their Priorities are Established”.
To which of the following process areas does this specific goal belong?